Professional Documents
Culture Documents
5119652/PR-REP-001/Rev 0
July 2013
Pharaonic Petroleum Company
Independent Verification of WHX New Flare and Blowdown System -
A Report Prepared by
Atkins
On Behalf of
Pharaonic Petroleum Company
COMMERCIAL IN CONFIDENCE
Document History
Notice
This report was produced by WS Atkins International Limited for Pharaonic Petroleum Company for
the specific purpose of Independent Verification of WHX New Flare and Blowdown System.
This report may not be used by any person other than Pharaonic Petroleum Company without
Pharaonic Petroleum Company’s express permission. In any event, Atkins accepts no liability for any
costs, liabilities or losses arising as a result of the use of or reliance upon the contents of this report
by any person other than Pharaonic Petroleum Company.
Contents
Section Page
Summary ................................................................................................................................................ 7
1. Introduction .............................................................................................................................. 8
2. Glossary of Terms .................................................................................................................... 9
3. Recommendations .................................................................................................................10
4. Compliance with ETPs and International Standards ..........................................................18
4.1 Applicable Engineering Standards ...........................................................................................18
4.2 Areas of Non-Conformance .....................................................................................................18
5. Relief Load Verification .........................................................................................................21
5.1 100% Area Checks ..................................................................................................................21
5.1.1 Vapour PSVs ............................................................................................................................21
5.1.2 Liquid PSVs ..............................................................................................................................22
5.1.3 Blowdown Valves .....................................................................................................................22
5.2 Critical Device Verification .......................................................................................................23
5.2.1 Findings – General ...................................................................................................................23
5.2.2 Findings – Undersized Devices ...............................................................................................24
5.2.3 Findings – Oversized Relief Devices .......................................................................................31
6. Verification of Disposal Systems .........................................................................................33
6.1 Disposal System Design ..........................................................................................................33
6.1.1 Flare Loads ..............................................................................................................................33
6.2 Relief Device Selection ............................................................................................................34
6.2.1 Backpressure limitations ..........................................................................................................34
6.2.2 Service .....................................................................................................................................35
6.2.3 Speed of Response ..................................................................................................................36
6.2.4 Multiple Relief Valves ...............................................................................................................36
6.2.5 Design Temperature .................................................................................................................. 1
6.3 Relief Device Inlet Piping ........................................................................................................... 1
6.3.1 Drainage and Blockages ............................................................................................................ 1
6.3.2 Inlet Pressure Drop .................................................................................................................... 1
6.3.3 Winterisation .............................................................................................................................. 2
6.4 Relief Device Tailpipes and Flare Headers................................................................................ 2
6.4.1 Flare Model ................................................................................................................................ 2
6.5 Liquids Handling ......................................................................................................................... 2
6.5.1 Piping ......................................................................................................................................... 2
6.5.2 Flare Knock Out Drums.............................................................................................................. 3
6.6 Design and Construction ............................................................................................................ 4
6.6.1 Relief Segregation ...................................................................................................................... 4
6.6.2 Low Temperature Relief ............................................................................................................. 4
6.6.3 Facilities for Drainage ................................................................................................................ 4
6.6.4 Facilities for Isolation .................................................................................................................. 5
6.6.5 Structural Supports .................................................................................................................... 5
7. Emergency Shutdown and Depressurisation ....................................................................... 6
List of Tables
Table 2.1 – Glossary of Terms 9
Table 4.1 – Non-conformances with ETPs 20
Table 5.1 – Over-sized vapour safety valves 22
Table 5.2 –Liquid relief valves 22
Table 5.3 – Relief Loads for Glycol/HC Separator 24
Table 5.4 – Relief Loads for Condensate Preheater Tubeside 24
Table 5.5 – Relief Loads for Condensate Preheater Shellside 25
Table 5.6 – Relief Loads for Condensate Stabiliser 25
Table 5.7 – Relief Loads for Ha’py Slugcatcher 26
Table 5.8 – Relief Loads for Gas/Gas Exchanger Shellside 26
Table 5.9 – Relief Loads for HP Fuel Gas KO Drum 27
Table 5.10 – Relief Loads for LP Fuel Gas KO Drum 27
Table 5.11 – Relief Loads for Nitrogen Distribution Header 28
Table 5.12 – Relief Loads for Water/HC Separator 29
Table 5.13 – Relief Loads for Condensate Train 30
Table 5.14 – Relief Loads for Taurt Slugcatcher 30
Table 5.15 – Relief Loads for Methanol Storage Tank 31
Table 5.16 – Relief Loads for Compressor Suction Drum 31
Table 5.17 – Relief Loads for Compressor Discharge Drum 32
Table 6.1 – Balanced bellows valves exceeding backpressure allowance 35
Table 6.2 - Critical PSV’s with Inlet line pressure drop outside acceptable limits 1
Table 6.3 - Flare model constraints 2
Table 9.1 - Summary of Current Flare Documentation against GP44-70 15
List of Figures
No table of figures entries found.
Appendices
Appendix A 100% Area Checks ....................................................................................................... A-1
A.1 Vapour PSV Area Check........................................................................................................ A-2
A.2 Liquid PSV Area Check.......................................................................................................... A-7
A.3 Blowdown Orifice Area Check ............................................................................................... A-8
Appendix B Critical Relief Device Evaluation ................................................................................ B-1
B.1 Critical Relief Device Summary ............................................................................................. B-2
Appendix C Relief Device Selection ................................................................................................ C-1
C.1 Relief Device Selection .......................................................................................................... C-2
Appendix D Inlet Line Verification ................................................................................................... D-1
D.1 Inlet piping drainage, isolation and winterisation ............................................................ D-2
D.2 Inlet Line Losses Calculations ............................................................................................. D-14
Appendix E Tail Pipe and Flare Header Summary ......................................................................... E-1
E.1 Tail Pipe Summary ................................................................................................................. E-2
E.2 Sub-header Summary ............................................................................................................ E-6
E.3 Header Summary ................................................................................................................... E-8
Appendix F HP Wet Flare model Review ........................................................................................ F-1
F.1 Review of HP Wet Flare Model .............................................................................................. F-2
Appendix G Calculations ..................................................................................................................G-1
G.1 Calculations ............................................................................................................................G-2
List of Tables
Table A.1 – Check on Area and Selected Orifice for Relief Devices in Vapour Service A-6
Table A.2 – Check on Area and Selected Orifice for Relief Devices in Liquid Service A-7
Table A.3 – Check on Blowdown Orifice Area A-9
Table B.1 – Comparison of Critical Devices B-8
Table C.1 – Relief Device Selection C-6
List of Figures
No table of figures entries found.
Summary
An independent verification exercise has been carried out on the West Harbor Expansion Project’s
new flare and blowdown systems by Atkins, at the Execute project stage, on behalf of the Pharaonic
Petroleum Company. The review covers the new facilities.
The review has been carried out in accordance with, and fulfilled the scope of; the Terms of
1
Reference and any exceptions are highlighted in the documentation. It should be noted that the
review is not yet complete and this is an interim report only. The report structure is based on the
headings used in the ToR.
Areas of non-conformance with current BP ETPs are noted in Section 4.2 for Project’s consideration.
In addition, where appropriate, a number of recommendations have been made throughout the report
and summarised in Section 3. There are a number of findings which will need further thought as to
how they should be addressed depending upon impact and given the current Project status.
Key findings are as follows:
Across all areas reviewed there was inadequate documentation detailing key decisions and
justification for the current design of the overpressure protection and disposal systems. Given
the advanced status of the design this should be addressed urgently and, if necessary, subject to
further review against the requirements given in the BP ETPs;
Of the 21 critical devices reviewed 5 were calculated by Atkins to be the same size, 13 were
undersized, 2 were oversized and for 1 device the current size is unknown and could not be
confirmed;
There is a concern that LOPA may have taken inappropriate credit for layers of protection in
arriving at IL ratings and there is a lack of transparency around why the LOPA (final) reported IL
ratings have been reduced in the SIL Verification Study. This is an area which should be given
further close attention.
1. Introduction
The industry has experienced an increase in incidents due to inappropriately designed or operated
relief and blowdown systems in the past few years. These systems are of critical importance in
maintaining safe and reliable operations and represent the last line of defence for a facility with
respect to personnel and public safety.
In order to identify and eliminate deficiencies in the design of the relief and blowdown systems and to
provide assurance on the adequacy of the proposed systems the Pharaonic Petroleum Company
(PhPC) have instructed Atkins to carry out an independent verification of the new flare and blowdown
system added as part of the West Harbor Expansion Project.
It should be noted that verification has been carried out only for:
the new facilities
the impact of the new facilities on overall issues of flare system capacity, radiation and dispersion
Verification of existing facilities has in general not been carried out.
This report summarises the verification exercise carried out on the blowdown, flare, relief and vent
systems between April and May 2013.
2. Glossary of Terms
Abbreviation Definition
CV Control Valve
EA Engineering Authority
HC Hydrocarbon
HP High Pressure
IL Integrity Level
KO Knock-out
LP Low Pressure
LT Low Temperature
RO Restriction Orifice
3. Recommendations
The following summarises the recommendations that have arisen throughout the report:
Recommendation 1 – Section 5.1.3
RO vendor should confirm that the Project’s required rates can be achieved through supplied orifice.
Recommendation 2 – Section 5.2.2.1
The potential paths for reverse flow through the Condensate Recirculation Pump, 0210-PB-001,
should be reviewed and 0210-PSV-021A/B sized accordingly.
Recommendation 3 – Section 5.2.2.1
The wetted area of the Glycol/HC Separator, 0210-VA-001, should be reviewed and the fire load
updated.
Recommendation 4 – Section 5.2.2.2
The orifice size of 0210-PSV-1005 should be increased from a D to an E.
Recommendation 5 – Section 5.2.2.3
The orifice size of 0210-PSV-1006 should be increased from an E to a G.
Recommendation 6 – Section 5.2.2.4
Project should review the build-up of condensate within the Ha’py slugcatcher and revisit fire relief
calculations.
Recommendation 7 – Section 5.2.2.6
Project should consider installing a restriction orifice in 0320-FCV-103 bypass line to restrict the flow
to no greater than that which can be passed by the control valve and can be handled by the installed
relief valves. Additionally, bypass should be locked closed to ensure it cannot be opened when the
control valve is in use.
Recommendation 8 – Section 5.2.2.7
The Cvs for 0420-PV-201 and 0420-PCV-202 should be confirmed, calculations revised and the valve
orifice size increased from a K to an L as necessary.
Recommendation 9 – Section 5.2.2.8
Calculations across letdown stations should be carried out based on the maximum operating pressure
for the high pressure system, this is typically the high pressure trip setting or PSV set pressure where
no trip exists.
Recommendation 10 – Section 5.2.2.8
Project should justify the use of a Cv of 3.192 for the manual bypass valve around 0420-PV-007A/B
or resort to a more typical valvue for a 1” manual globe valve.
Recommendation 11 – Section 5.2.2.8
Project should source the installed Cv of 0420-PV-007A/B and 0420-PV-1104 and update calculations
for 0420-PSV-1008A/B as required. These Cvs are safety critical items and should be documented
as such.
Recommendation 12 – Section 5.2.2.9
0600-PSV-1006A/B on the Nitrogen Distribution Header should be replaced with a G orifice valve.
or from prolonged flaring of wet streams, or if there is potential for blockage, what measures will be
taken to mitigate this.
Recommendation 50 – Section 6.6.2
Project should confirm that the potential for low temperatures within the flare system has been
addressed taking into account all potential modes of operation. The output from such a study should
be included within the flare and blowdown report. This equally applies to the existing cold flare header
where relocation of previous discharges to the wet flare header may adversely affect the expected
temperatures within this system, particularly as it is noted that the cold flare header from the KO drum
to flare is carbon steel.
Recommendation 51 – Section 7.2
A Safety Instrumented System summary (part of the Relief and Overpressure Protection Dossier, as
required by GP 44-70) should be prepared
Recommendation 52 – Section 7.2
The LOPA worksheets should be reviewed to establish that IL ratings have been arrived at taking
account of appropriate rule sets in the revision of GP 48-03 used as reference in the LOPA exercise.
Note also that the latest issue of GP 48-03, August 2012, has different guidance and rule sets for the
probability of failure of piping and vessels, as a function of the degree of overpressure on failure of the
protection, compared with those in the previous revision
Recommendation 53 – Section 7.2
BP GPs and all documents referenced in the LOPA report GL-WHUPZZ-SA-REP-0002_G1 LOPA
Report (Final) should have relevant revision/date noted.
Recommendation 54 – Section 7.2
Justification and an MOC audit trail should be provided in ENP-WHUPZZ-SA-REP-6652 REV B1 for
changes made to SIL ratings (all changes being reductions in IL rating) from the final LOPA report,
and for any subsequent changes arising from re-HAZOP/re-LOPA.
Recommendation 55 – Section 7.2
Check in the LOPA IL assessment that where credit is taken for trips as independent layers of
protection, they have separate output actions from the trip being assessed.
Recommendation 56 – Section 7.2
Revisit the layers of protections necessary to achieve the required risk reduction for 0230-LAHH-
1003, Wet Flare KO Drum.
Recommendation 57 – Section 7.3.3
Methodology used in depressuring calculations and simulations should be clearly detailed and basis
of all inputs to HYSYS defined.
Recommendation 58 – Section 7.3.3
Isentropic efficiency of 50% is too low for gas based systems and should be increased to 100% in
depressuring simulations.
Recommendation 59 – Section 7.3.3
It does not appear that minimum temperature blowdown has been considered, i.e. blowdown initiated
when system contents have cooled to minimum ambient temperature. This will give rise to the lowest
temperatures both upstream and downstream of the blowdown orifice. Depressuring scenarios for
this case should be run until atmospheric pressure is reached to ensure that lowest temperatures are
identified.
GP 44-70 6.6 Reverse flow does not Relief valves grossly undersized
appear to have been in the event of check valve
considered. failure.
GP44-70 7.2 High pressure system Actual relief loads may be higher
assumed to be at normal which may lead to overpressure.
operating pressure not
maximum possible pressure.
API 521 5.10.3 Flow through bypass not Potential overpressure of low
considered in relief system pressure system when either
design when the upstream both control valve and bypass
GP44-70 7.8 pressure exceeds the open, or bypass used instead of
downstream hydrotest control valve.
pressure. Bypasses have
been locked closed instead.
GP 44-70 9.4 A comprehensive Relief and It cannot be verified that the
Overpressure System relief and flare systems are
Dossier has not been adequately designed.
prepared. Furthermore it is essential in
ensuring that future
modifications do not jeopardise
the sizing/design basis of these
critical systems.
GP 44-80 10.2c CFD analysis should be KO Drum does not meet droplet
carried out for confirmation removal requirements, burning
of liquid separation efficiency liquid rain out from flare
of the flare KO drums and for
assessment of the impact of
the inlet diverter on
separation efficiency. Not
clear that rhoV2 values of
inlet nozzles/devices have
been confirmed acceptable
GP 44-80 10.2.d.2 Vacuum rating of the Cold Design inadequate for vacuum
and LP Flare KO Drums is conditions
GP 44-80 10.3f (current It is not apparent that relief No warning given of liquid relief
version) devices on liquid relief due to either relieving condition
service discharging to the or passing valve. Potential to
flare systems are fitted with overfill flare drum.
warning devices.
GP 44-80 11.2 / 11.5 It is noted from data sheets Insufficient purge, air drawn
that purge rates are to be back into flare stacks
calculated by the flare
package supplier.
Purge rate calculations
should be prepared for
burnback prevention and
prevention of air ingress
Note that no account can be
taken for flare seals in
reducing purge rates. These
should include calculation of
emergency purge rates
required for shrinkage due to
cooling / condensation in the
flare headers, GP 44-80,
11.2.f, and including any
coincident KO Drum pump-
out rates.
GP 44-80 11.5.c4 and Purge points are not No indication of loss of gas
11.5.l provided with low flow purge and no alternative supply.
alarms and fuel gas purges
are not backed by nitrogen.
It is not apparent that he
reliability of back-up gas
supply has been confirmed
as adequate
As can be seen from the above table, Atkins has calculated that the governing case is reverse flow
from the Ha’py Slugcatcher which was not considered by ENPPI. In addition the Atkins fire case is
greater than the ENPPI fire case. This is due to a combination of different latent heats, 535 kJ/kg
(ENPPI) versus 361 kJ/kg (Atkins), partly due to a differing methodology, and a different in the value
2 2
of wetted area used 8.8 m (ENPPI) versus 15.72 m (Atkins).
In calculating the reverse flow through the pumps we have assumed a flow area equivalent to an
orifice of 0.5 in diameter as it is a positive displacement pump.
The potential paths for reverse flow through the Condensate Recirculation Pump, 0210-PB-
001, should be reviewed and 0210-PSV-021A/B sized accordingly.
The wetted area of the Glycol/HC Separator, 0210-VA-001, should be reviewed and the fire load
updated.
5.2.2.2 0210-PSV-1005 Condensate Preheater 0210-HA-002A, Tubeside
0210-PSV-1005 protects the tubeside of the Condensate Preheater, 0210-HA-002A, from
overpressure. It is a 1D2 valve set at 17.5 barg.
Scenarios Identified Atkins Relief Load ENPPI Relief Load ENPPI Atkins
(kg/h) (kg/h) Orifice Orifice
Fire 830 524
Scenarios Identified Atkins Relief Load ENPPI Relief Load ENPPI Atkins
(kg/h) (kg/h) Orifice Orifice
Fire 6457 1090
E G
Tube Rupture 11,937 -
Table 5.5 – Relief Loads for Condensate Preheater Shellside
The ENPPI governing case for 0210-PSV-1006 is fire requiring a D orifice. The Atkins governing
case is also fire but requiring a G orifice.
As can be seen, there is a difference in fire load which is again attributable to a difference in latent
heats, 814 kJ/kg (ENPPI) versus 115 kJ/kg (Atkins), which is the API minimum recommended value.
Wetted areas were broadly similar.
Although tube rupture was considered by Atkins, as the shell test pressure exceeds the maximum
operating pressure of the tubeside, tube rupture does not need to be considered, although it should
be assured that the low pressure side is adequately protected.
The orifice size of 0210-PSV-1006 should be increased from an E to a G.
5.2.2.4 0210-PSV-1028A/B Condensate Stabiliser 0210-VE-001
0210-PSV-1028A/B protects the Condensate Stabiliser, 0210-VE-001, from overpressure. It is a 3K4
valve set at 9.2 barg.
Scenarios Identified Atkins Relief Load ENPPI Relief Load ENPPI Atkins
(kg/h) (kg/h) Orifice Orifice
Fire 5,817 12,453
Scenarios Identified Atkins Relief Load ENPPI Relief Load ENPPI Atkins
(kg/h) (kg/h) Orifice Orifice
Fire (HC only) 183,989 148,146
From the above table it can be seen that whilst the governing case by Atkins and ENPPI has been
identified as fire, the Atkins load is greater requiring a larger relief orifice. The reason for the
difference is assumed wetted area. Due to the length of the slugcatcher it has been assumed that
2
only that part within a fire area as defined by API 521 corresponding to an area of 232 m needs to be
considered. This is equivalent to a fire of diameter 17.2 m. Atkins have therefore assumed that a
length of 17.2 m will be subject to fire and in absence of physical details on the slugcatcher have
2
assumed that this section could be liquid full resulting in a wetted area of 400m . ENPPI have based
2
their calculations on a length of 24m and liquid level of 50% thus resulting in a wetted area of 311 m .
Whilst we consider our wetted area to be conservative and correct, the probability of accumulating
that much condensate within the system should be considered and this may result in the current
selected device being sufficient.
It is also noted that additional cases were considered such as fire under gas filled section and the
slugcatcher shut-in with continued injection of corrosion inhibitor.
Project should review the build-up of condensate within the Ha’py slugcatcher and revisit fire
relief calculations.
5.2.2.6 0320-PSV-1029A/B/C Gas/Gas Exchanger 0320-HA-001A/B Shellside
0320-PSV-1029A/B/C protect the Gas/Gas Exchanger, 0320-HA-001A/B, Shellside from
overpressure. They are 3K4 valves set at 85 and 89 barg with 2 on line.
Scenarios Identified Atkins Relief Load ENPPI Relief Load ENPPI Atkins
(kg/h) (kg/h) Orifice Orifice
External Fire - Vapour
34,424 29,366
Expansion
External Fire - Liquid
7,320 -
Vaporisation
Control Valve Failure 2K 2Q
(0320-FCV-103 8” bypass 802,304 -
valve)
Blocked Outlet 128,215 128,215
Table 5.8 – Relief Loads for Gas/Gas Exchanger Shellside
From the above table it can be seen that Atkins considers the governing case to be control valve
failure. Gas is fed under flow control to the LT Separator 0320-VA-001. A failure in this control
system could result in 0320-FCV-103 opening fully. Also, as the valve has a bypass this too could be
opened fully. In accordance with GP 44-70, as the maximum upstream pressure is less than the test
pressure of the vessel/exchangers, then the relief valve should be designed to pass the larger flow
between the control valve and bypass valve. In this case the bypass valve can pass considerably
more flow than the control valve and therefore becomes the governing case.
Project should consider installing a restriction orifice in 0320-FCV-103 bypass line to restrict
the flow to no greater than that which can be passed by the control valve and can be handled
by the installed relief valves. Additionally, bypass should be locked closed to ensure it cannot
be opened when the control valve is in use.
5.2.2.7 0420-PSV-801A/B HP Fuel Gas KO Drum 0420-VA-002
0420-PSV-801A/B protects the HP Fuel Gas KO Drum, 0420-VA-002, from overpressure. It is a 3K4
valve set at 40barg.
Scenarios Identified Atkins Relief Load ENPPI Relief Load ENPPI Atkins
(kg/h) (kg/h) Orifice Orifice
Fire - Liquid - 625
Fire – vapour expansion 1025 -
Failure of PV007A/B plus bypass is calculated to be the governing case. Atkins have calculated the
flow across PV007A/B as 3963 kg/hr per valve based on PAHH upstream at 78 barg. No vendor Cv
was available for this valve and the calculation has been based on a Cv of 3.07 as stated in the
2
ENPPI calculations . In addition the flow across the 1” manual bypass valve has been calculated to
be 12,932 kg/h based on a Cv of 10.6. ENPPI have calculated the flow across PV007A/B to be 2525
kg/hr per valve based on an upstream pressure of 72 barg, whilst flow through the bypass has been
calculated as 2400 kg/h based on a Cv of 3.192.
In accordance with GP 44-70, high pressure system should be assumed to be operating at maximum
possible pressure (e.g. high pressure trip setting), and therefore calculations should be based on an
upstream pressure of 78 barg.
Calculations across letdown stations should be carried out based on the maximum operating
pressure for the high pressure system, this is typically the high pressure trip setting or PSV
set pressure where no trip exists.
It is not clear where the Cv of 3.192 used to calculate the flow across the manual bypass valve
around PV007A/B has come from. Typically the Cvs of manual valves are significantly higher than
the same body size control valve.
Project should justify the use of a Cv of 3.192 for the manual bypass valve around 0420-PV-
007A/B or resort to a more typical value for a 1” manual globe valve.
Furthermore, it is noted that the Cv for PV007A/B and PV1004 has been calculated by ENPPI and are
not necessarily the installed Cvs. As the flow across these valves has a direct impact on relief device
sizing, these Cvs are safety critical and hence it is imperative that the actual installed Cv is sourced.
Project should source the installed Cv of 0420-PV-007A/B and 0420-PV-1104 and update
calculations for 0420-PSV-1008A/B as required. These Cvs are safety critical items and should
be documented as such.
5.2.2.9 0600-PSV-1006A/B Nitrogen Distribution Header
0600-PSV-1006A/B protects the Nitrogen Distribution Header from overpressure. It is a 1 ½ F2 valve
set at 10.6 barg.
Scenarios Identified Atkins Relief Load ENPPI Relief Load ENPPI Atkins
(kg/h) (kg/h) Orifice Orifice
Control valve failure (PCV-
2310 2000
1005A/B)
Blocked outlets 188 -
F G
Abnormal heat input HOLD – insufficient
data available to -
evaluste
Table 5.11 – Relief Loads for Nitrogen Distribution Header
Both the ENPPI and Atkins have calculated the governing case to be control valve failure of
PCV1005A/B. The derivation of the ENPPI load of 2000 kg/hr is unknown (no calculation provided)
but it is suspected that it has been calculated based on normal operating pressure upstream rather
than trip set pressure.
There will be an abnormal heat input case if the distribution system is shut-in whilst the Nitrogen back-
up heater, 0600-HM-001, remains operational. However no details on the heater dimensions are
available to evaluate this scenario.
0600-PSV-1006A/B on the Nitrogen Distribution Header should be replaced with a G orifice
valve.
Where control valve failure results in an ovepressure scenario it is imperative that vendor Cvs
are used in the relief device sizing calculations to ensure that the device is adequately sized.
Project should obtain Cvs for all such valves and ensure that they are reflected in the relief
calculations. These valves and associated Cvs should be documented in the Relief and
Overpressure System Dossier.
5.2.2.11 0850-PSV-1005 Water/HC Separator Condensate Outlet
0850-PSV-1005 protects the condensate train from overpressure. It is a 1 ½ G3 valve set at 17.5
barg.
Scenarios Identified Atkins Relief Load ENPPI Relief Load ENPPI Atkins
(kg/h) (kg/h) Orifice Orifice
Control valve failure (0850-
7567
FCV-002)
Gas Blowby (0850-FCV-
2818 2615
002)
Gas Blowby (0850-FCV- G P
135,941 (displaced
002) liquid)
Blocked outlets 3486 -
Table 5.13 – Relief Loads for Condensate Train
Whilst gas blowby is also the governing case for the sizing of this relief device, the valve is on a liquid
full system and as such Atkins has sized the valve for liquid displacement.
It should also be noted that if the downstream system is liquid full then piping could be subjected to
pressures greater than the design pressure in the event of gas blowby.
0850-PSV-1005 should be resized for liquid displacement in the event of gas blowby. In
accordance with GP 44-70 ISD principles should be applied in selecting design pressure and
corresponding set pressures for the downstream system and relief device.
5.2.2.12 0850-PSV-1023A/B Taurt Slugcatcher 0850-VQ-003
0850-PSV-1023A/B protects the Taurt Slugcatcher, 0850-VQ-001, from overpressure. It is a 4P6
valve set at 110 barg.
Scenarios Identified Atkins Relief Load ENPPI Relief Load ENPPI Atkins
(kg/h) (kg/h) Orifice Orifice
Fire - liquid 11,315 -
Fire – vapour expansion 1443 -
P 6T+R
Blocked Outlet 236,484 258,283
Inadvertent valve opening 9,200,054 -
Table 5.14 – Relief Loads for Taurt Slugcatcher
ENPPI have sized 0850-PSV-1023A/B on the basis of blocked outlet. However, as the maximum
sealine pressure is 144 barg, it is possible that inadvertent opening of 0850-SDV-001 after a
shutdown, without first depressuring to the flare, could lead to very high flowrates into the slugcatcher.
It is noted that the Taurt Slugcatcher has a design pressure of 144 barg and therefore cannot be
overpressured by this scenario, but the impact on downstream systems should be considered. If this
case can be protected against by an IPS, an N orifice would suffice for all other scenarios.
Inadvertent opening of 0850-SDV-001 without depressuring and the sealine at maximum
pressure of 144 barg will result in an extremely large load. Given that this load will exceed the
capacity of the flare system, an IPS will be required. Project should review existing
overpressure protection and confirm that it is sufficiently robust and reacts quickly enough to
protect the downstream systems.
Report No: 5119652/001/PR-REP-001/Rev 0 Page 30
Issue Date: July 2013
Pharaonic Petroleum Company
Independent Verification of WHX New Flare and Blowdown System -
As can be seen from the above table there is a large difference in the fire loads calculated. Atkins
has calculated the highest load is as a result of vapour expansion. This case was not considered by
ENPPI and they have instead sized it on the basis of liquid boil-off. Whilst Atkins considered water
and glycol as there is no condensate present in the stream, ENNPI would appear to have assumed
condensate. However it is noted that their wetted area is very high due to an assumption of a
particularly high level in the drum, this, coupled with a very low latent heat of 48 BTU/lb, lower than
the API recommended minimum, has resulted in a large relief load and an F orifice required.
Again, as can be seen from the above table there is a large difference in the fire loads calculated.
Atkins has calculated the highest load is as a result of vapour expansion. This case was not
considered by ENPPI and they have instead sized it on the basis of liquid boil-off. Whilst Atkins
considered water and glycol as there is no condensate present in the stream, ENNPI would appear to
have assumed condensate. However it is noted that their wetted area is higher due to an assumption
of a high level in the drum, this, coupled with a very low latent heat of 48 BTU/lb, lower than the API
recommended minimum, has resulted in a large relief load and an F orifice required.
6.2.2 Service
All valves are specified depending upon the service – safety for vapour relief, relief for liquid relief and
safety-relief for multi-phase relief. As little information was provided about the other relief scenarios
aside from the sizing case it was difficult to assess this criteria. However, as can be seen from Atkins
calculations for critical devices there are a number of valves which would have to operate for different
fluid phases. Whilst relief valves can adequately handle liquid, the reverse is not true and safety
valves will have to be derated when used for liquid service. For existing valves no information has
been provided on the type of service required.
PSVs 0320-PSV-1030A/C are on the shell side of heat exchanger 0320-HA-002A/B and have been
specified as safety valves, and 0320-PSV-1030B has been specified as safety relief. Despite being
sized for blockage, if a tube rupture occurred the valve would need to handle some 2 phase flow as
glycol is being injected upstream of the heat exchanger.
PSVs 0320-PSV-1030A/C should be specified as safety relief valves and that ethylene glycol is
will be present under some relieving conditions.
Project should review and confirm that all relief devices have been appropriately selected to
function adequately across all potential relief scenarios. Where safety valves are expected to
be used to relieve liquid under certain scenarios, the valve capacity should be reviewed and
confirmed as acceptable with derating factor applied.
The piping configuration for the inlet lines to 0210-PSV-1028A/B, 0210-PSV-1005, 0420-PSV-
1008A/B, 0600-PSV-1006A/B and 0850-PSV-1025 to ensure the pressure drop as a percentage
of set pressure is below the required project limits.
Confirm if the pilot operated valves require remote sensors and update datasheets
accordingly.
6.3.3 Winterisation
8 6
The minimum ambient design temperature is 5⁰C thus heat tracing for Winterisation is not expected .
Philosophy requires that heat tracing is provided on lines where stagnant flow may be conducive to
ice or hydrate formation. On reviewing the P+IDs it is not apparent that heat tracing has been applied
to any PSV inlet lines or critical instrument impulse lines.
Project should confirm that the potential for blockage of the PSV inlet lines and impulse lines
due to hydrate formation has been considered and appropriate measures are in place.
only. The possibility of liquid entrainment is particularly acute in lines downstream of relief valves so
the operation of such lines/valves should be carefully considered and the effects of liquid shock
loading included in stress analysis if required. It is important that all relief valves which may see liquid
or two phase relief are screened and not just those where these conditions exist as the governing
10
case. It is noted that the line list does not note those lines which could be subjected to two phase
flow, although, certainly in some cases, there is a note to reflect this on the P+ID.
It should be confirmed that the piping systems associated with those relief valves which may
see multi-phase relief are noted as such on the line list and subjected to screening and, if
required, full stress analysis.
6.6.2, and that this is reflected in the design temperatures of the flare KO Drums and stacks,
particularly as it is noted that the cold flare header from the KO drum to flare is carbon steel.
The LP and Cold Flare KO Drums are not noted on the relevant P+IDs as being designed for full or
half vacuum, as required by GP 44-80, 10.2.d.2.
Project to confirm vacuum rating of the Cold and LP Flare KO Drums, in line with GP 44-80,
10.2.d.2.
- The sub-headers slope to the headers does not always meet the 1 in 400 criteria;
- The headers slope to the knock-out drums does not always meet the 1 in 400 criteria;
Relief valve tailpipes enter the sub-headers from above;
Relief valve tailpipes enter the sub-headers at an angle of approximately 45°;
No pockets in line.
A comprehensive review of all critical relief device tailpipes, sub-headers and headers can be found in
Appendix E.
It should be noted that there are some instances where the slope is not stated on the isometric
drawing and where the isometric drawings are unavailable.
Project to confirm that HAZOP and LOPA will be carried out on, produced water and waste
water treatment, instrument air and nitrogen systems and the cold vent when re-designed to
cater for the required loads.
BP GPs and all documents referenced in the LOPA report GL-WHUPZZ-SA-REP-0002_G1
LOPA Report (Final) should have relevant revision/date noted.
The SIL verification report, ENP-WHUPZZ-SA-REP-6652 REV B1, has amended some IL ratings, but
without full documentation of the justification for change.
Justification and an MOC audit trail should be provided in ENP-WHUPZZ-SA-REP-6652 REV B1
for changes made to SIL ratings (all changes noted as being reductions in IL rating) from the
final LOPA report, and for any subsequent changes arising from re-HAZOP/re-LOPA.
For 0360-LALL-612A and 0360-LALL-602A (P) and (V), credit is taken for 0210-PAHH-041 and 0360-
PSV-812A/B in reducing the IL requirement. Credit for the PSV is based on its sizing for gas blowby,
but liquid relief at gas blowby volumetric rates will precede gas relief.
Project to confirm whether 0360-PSV-812A/B is sized for liquid relief under gas blowby
conditions and therefore if credit can be taken for it as a protection layer for 0360-LALL-612A
and 0360-LALL-602A (P) and (V).
Project to confirm whether 0210-PAHH-041 acts on different output devices compared with
0360-LALL-612A and 0360-LALL-602A (P) and (V), and therefore if credit can be taken for
PAHH-041 as a protection layer.
For 0360-LALL-612C and 0360-LALL-602C, (1), (2) and (3), credit is taken for 0850-PAHH-002 in
reducing the IL requirement. Credit for the PSV is based on its sizing for gas blowby, but liquid relief
at gas blowby volumetric rates will precede gas relief.
Project to confirm whether 0360-PSV-812A/B is sized for liquid relief under gas blowby
conditions and therefore if credit can be taken for it as a protection layer for 0360-LALL-612A
and 0360-LALL-602A (P) and (V).
It was noted that in assessing the IL rating for 0230-LAHH-1003, Wet Flare KO Drum, credit has been
taken for the slugcatcher high level trip in calculating the mitigated event likelihood. According to C&E
ENP-WHUPZZ-PR-CED-1085, Appendix A, both the flare KO drum and slugcatcher cause PSD, so
the slugcatcher trip is not an independent layer of protection. While slugcatcher overfill is not the
dominant cause in setting the IL rating, the credit taken for the slugcatcher trip should be reviewed.
This may also imply that a check should be made that appropriate credit for trips has been taken for
the other trips assessed in the LOPA, particularly for the LP Flare and Cold KO Drums.
Check in the LOPA IL assessment of trip loops, in particular the high level trips in the flare KO
drums, that where credit is taken for other trips as independent layers of protection, these
other trips do have separate inputs, logic and output actions from the trip being assessed,
and, if not, revise the LOPA accordingly, for example, credit wrongly taken for slugcatcher
high level trip as an independent layer of protection for the high level trip in the Wet Flare KO
Drum, and credit taken for 0210-PAHH-1012/1013 in closing upstream sources, as a layer of
protection in the LOPA for PAHH-0210HA002.
A recommendation in ENP-WHUPZZ-SA-REP-6652 REV B1, is to provide a separate high level alarm
for the Wet Flare KO Drum, since the required IL rating for 0230-LAHH-1003 cannot be achieved.
This cannot be considered as a separate protection layer since there is already credit taken for
operator response to the existing alarm 0230-LAH-1001 in the LOPA assessment.
Revisit the layers of protections necessary to achieve the required risk reduction for 0230-
LAHH-1003, Wet Flare KO Drum, since credit is taken twice for operator intervention, which
indicates a lack of understanding of the principles of LOPA and the requirements of GP 48-03.
It is noted that in the LOPA for 0210-LAHH-032, the output device of the trip is control valve FV-022.
While no credit has been taken for the trip if the control loop LIC-035 drives FV-022 open, if this valve
fails open/stuck, as a cause of rising level, then there will be no high level trip protection. Use of a
control valve as a shutdown valve is, in any case, not good practice.
Project to review feasibility of actuating a separate on/off valve, rather than FV-022 as the
output device of trip loop 0210-LAHH-032.
A number of assumptions are made in the LOPA report under an Assumptions heading and some
actions are contained under Summary of Recommendations for Action, and in the text in the
LOPA worksheets, for example for 0210-PAHH-1012-1014. It is noted that there appears to be no
relief protection associated with 0210-PAHH-1012-1014 and that this is alluded to in one of the LOPA
actions, action 3.
Project to confirm that assumptions made in the LOPA report under an Assumptions heading
are valid, and that the actions contained under Summary of Recommendations for Action, and
in the text in the LOPA worksheets, for example for 0210-PAHH-1012-1014, are being captured
and closed out in the project Action Tracking System.
In particular, project to confirm that relief or other protection will be provided on the
condensate pre-heaters and downstream glycol/HC separator for gas blowby/liquid relief, and
for a blocked outlet case, in support of 0210-PAHH-1012/1013 (PSVs sized for fire case).
7.3.2 Methodology
There is no detailed methodology given in any of the documents reviewed: Flare, Blowdown and Vent
12 13
Philosophy , Flare and Blowdown Basis of Design and Existing and New Depressuring Systems
14
Verification Report . Additionally neither HYSYS depressuring models nor depressuring calculations,
although requested, have been received for review.
However, based on the documents reviewed as noted, the following is inferred:
HYSYS depressuring module has been used to simulate blowdown;
For fire cases starting pressure is assumed to be design pressure (maximum settle-out pressure
for compressors) and maximum operating temperature coincident with maximum ambient
o
temperature of 40 C;
For adiabatic blowdown starting pressure is again assumed to be design pressure (maximum
settle-out pressure for compressors) and minimum operating temperature coincident with
o
minimum ambient temperature of 5 C. An isentropic efficiency of 50% is applied.
It does not appear that minimum temperature blowdown has been considered, i.e.
blowdown initiated when system contents have cooled to minimum ambient temperature.
This will give rise to the lowest temperatures both upstream and downstream of the
blowdown orifice. Depressuring scenarios for this case should be run until atmospheric
pressure is reached to ensure that lowest temperatures are identified.
There are discrepancies in different documents regarding final blowdown pressure 6.9
barg in Flare and Blowdown Basis of Design against 7 barg in Existing and New
Depressuring Systems Verification Report. Although this will not impact upon the
depressuring rates, there should be consistency.
Design basis of flare system should be adequately documented.
It is noted that the design intent to dispose of any liquid collecting at the base of the new flare stack,
including following blowdown, is to manually drain this to a portable container. This will not only
expose the operator to hazardous release of hydrocarbon but may also lead to exposure to high
levels of radiation on approach to the flare stack.
Re-design the drain arrangements for the new flare stack to avoid exposure of the operator to
hydrocarbons and potentially high levels of radiation. Confirm arrangements for draining of
the Cold and LP Flare stack risers and any required protections.
The fuel gas supply to the new flare is in carbon steel. There is no filtration on this fuel gas supply and
there is risk of restricted flow/blockage to pilots and the ignition system if there is debris / corrosion
product in this line.
Project to review the potential for restricted flow to flare pilots/ignition system due to debris in
the fuel gas supply piping, and replace in stainless steel, as necessary.
List of removable spools During the course of the review we did not come across any
removable spools.
A list of Removable spools should be included within the
Relief and Overpressure System Dossier if required to limit
relief loads or prevent overpressure scenarios.
Relief loads, calculations, and/or Calculations are presented as an appendix to the Existing and
2
assumptions New Safety Valves Verification Report . The basis for these
calculations is unclear.
All calculated loads should be included within the Relief and
Overpressure System Dossier with key assumptions
included as notes as necessary. Applicable calculation
document numbers should be included for reference. Refer
to GP44-70 A4.
Relief limiting control valves and There is no list that details which control valves, bypass valves
restriction orifices and restriction orifii control the relief load for a particular relief
device.
It is recommended that a list of control valves and ROs be
updated in line with A5 of GP44-70. This should include any
control valve bypasses. This should include assumptions
made in upstream and downstream conditions for relief load
evaluation, and should cross-reference the affected relief
device.
Restricted Cv control valves See above - Relief limiting control valves and restriction orifices
SIS No data provided.
It is recommended that those trips limiting relief load be
incorporated in the Relief and Overpressure System Dossier.
Data recorded should be in line with A8 GP44-70.
Process control loop segregation This does not appear to have been considered when evaluating
relief scenarios.
Fire areas, fire loads, and fire There is some data presented in Existing and New Depressuring
14
resistant insulation (fireproofing) Systems Verification Report .
Details of fire areas, loads etc should be incorporated within
the Relief and Overpressure System Dossier. Data recorded
should be in line with A10 GP44-70.
Flare system details, including These details are included within various documents.
flare header, knockout drum and Flare system details, including flare header, knockout drum
appurtenances, flare stack, flare and appurtenances, flare stack, flare tip, igniter system, etc,
tip, ignitor system, etc should be included within the Relief and Overpressure
System Dossier.
Header pressure profiles These details are included within the HP Blowdown Systems
4
Hydraulics Verification Report and an LP Flare and Blowdown
3
Systems Hydraulics Verification Report .
Maximum tailpipe and header These details are included within the HP Blowdown Systems
4
velocities Hydraulics Verification Report and an LP Flare and Blowdown
3
Systems Hydraulics Verification Report .
HP/LP interface schedule A list of HP/LP interfaces has been included within the Existing
2
and New Safety Valves Verification Report , however this does
not include all pertinent data.
It is recommended that an HP/LP interface schedule be
developed in line with A13 of GP44-70.
Size and type of disposal system Although mentioned in a number of reports it is not clearly stated.
used Relief and Overpressure System Dossier should clearly state
the Size and type of disposal system used.
Relief device inlet/outlet piping The outlet piping hydraulics are included within the HP Blowdown
Mechanical design basis of It is assumed that these details will be recorded in the piping
process piping and equipment stress analysis report.
It is recommended that a general statement regarding the
mechanical design basis of the flare headers be included
within the Flare Study Report in line with note 19, para 9.4
GP44-70.
Table 9.1 - Summary of Current Flare Documentation against GP44-70
10. References
1
PHPC-WHUPZZ-PM-TOR-001 ToR for the WHX New Flare and Blowdown System – Execute
Stage, Rev C01, October 2012.
2 th
ENP-WHUPZZ-PR-REP-1036 Existing/New Safety Valves Verification Report, Rev G7,12 March
2013.
3
ENP-WHUPZZ-PR-REP-1061 LP Flare and Blowdown System Hydraulics Verification Report, Rev
th
G1, 26 March 2013.
4
ENP-WHUPZZ-PR-REP-1060 HP Blowdown System Hydraulics Report, Rev D3
5
Overpressure Protection Systems, GP 44-70, BP Group Engineering Technical Practices, 24th
February 2010.
6
Line Sizing, Insulation and Heat Tracing Philosophy, ENP-WHUPZZ-PR-PHI-1017 Rev D3, 26th
March 2012.
7
Sizing, Selection, and Installation of Pressure-Relieving Devices in Refineries, Part 2 - Installation,
API Recommended Practice 520, 5th Edition, August 2003.
8
Process and Utilities Basis of Design, ENP-WHUPZZ-PR-BOD-1001 Rev G5, 19th September 2012
9
ENPPI Flarenet Model: ENP-WHUPZZ-PR-REP-1060_D2.fnw.
10 th
ENP-WHUPZZ-PI-LST-1086 Line List, Rev F1, 29 July 2012.
11
ENP-WHUPZZ-PR-PHI-1019 West Harbor Expansion Project Emergency Shutdown (ESD)
Philosophy, Rev D2, 12/9/12.
12 th
ENP-WHUPZZ-PR-PHI-1013 Flare, Blowdown and Vent Philosophy, Rev D4, 26 September 2012.
13 th
ENP-WHUPZZ-PR-BOD-1002 Flare and Blowdown Basis of Design, Rev G1, 27 October 2011.
14
ENP-WHUPZZ-PR-REP-1050 Existing and New Depressuring Systems Verification Report, Rev
th
G1, 7 June 2012.
15 th
ENP-WHUPZZ-PI-REP-3028-B1 Acoustic Induced Vibration Assessment Report, Rev B1 7 June
2012.
Appendix A
100% Area Checks
Table A.2 – Check on Area and Selected Orifice for Relief Devices in Liquid Service
FO Tag BDV Tag Flow (kg/h) ENPPI Size (mm) Size Atkins (mm) Discrepancy %
0190-FO-1006
0190-BDV-304 986.2 4.61 5.57 21
Appendix B
Critical Relief Device Evaluation
Relief Valve System ENPPI Sizing Required Selected Atkins Sizing Relief load Selected Comments
2 2
Case Relief load Orifice (in ) Case (kg/h) Orifice (in )
(kg/h)
Control Valve liquid and
Failure of 3,538 abnormal heat
0210-FV-035 input.
Blocked
53.5
vapour outlet
Blocked liquid
4,278
Outlet
Gas Blowby 3,315 Gas Blowby
4,025
(vapour)
Gas Blowby
(accelerated 275,229
liquid)
Liquid Overfill 19,452
Abnormal
193,196
heat input
300-PSV- Ha’py Slugcatcher External Fire – The PSV is
1024A/B 300-VQ-001 Liquid 29,346 undersized
(water+HC) based on the fire
External Fire case, where
Fire 148,146 L 183,989 M
– Liquid (HC) condensate only
External Fire – has been
12,695 considered.
Vapour
3
Blocked Outlet 0.01 m /h
0320-PSV- Hanover LT External Fire - The PSV is
707
1026 Separator (0320 Liquid adequately
VA 401) External Fire - sized.
Blocked 3355
134,565 M Vapour M
Outlet
Control Valve
128,599
Failure
Blocked Outlet 122,332
0320-PSV Gas/Gas External Fire - The PSV is
1029-A/B/C Exchanger Shell Blocked undersized for
128,215 K Vapour 34,424
Side (0320 HA Outlet full open bypass
Expansion
Relief Valve System ENPPI Sizing Required Selected Atkins Sizing Relief load Selected Comments
2 2
Case Relief load Orifice (in ) Case (kg/h) Orifice (in )
(kg/h)
001A/B) External Fire - around 0320-
Liquid 7,320 FCV-103
Vaporisation
Control Valve
Failure (0320-
802,304
Fire 29,366 J FCV-103 8”
bypass valve)
Blocked Outlet 128,215
0360-PSV-801 Onshore Gas Fire – vapour PSV is
949
AC/BC Compressor HP expansion oversized.
Suction Drum C Fire – liquid
Fire 13,515 F 697 D
(0360 VA 001C) case (H2O)
Fire – liquid
903
case (Glycol)
0360-PSV- Onshore Gas Blocked PSV adequately
Block 371,344 499,300
831- Compressor Discharge sized but ENPPI
AC/BC/CC Discharge C (0360 flowrate based
VA 001C) 2P 2P on normal flow
Fire 3,237 Fire 222,741 through
compressor plus
10%.
0360-PSV- Onshore Gas External Fire - PSV is
1000A/B Compressor HP Vapour 7808 oversized.
Discharge Drum C Expansion
(0360 VA 002C) External Fire -
Liquid
697
Fire 9367 F Vaporisation E
(H2O)
External Fire -
Liquid
903
Vaporisation
(Diesel)
Relief Valve System ENPPI Sizing Required Selected Atkins Sizing Relief load Selected Comments
2 2
Case Relief load Orifice (in ) Case (kg/h) Orifice (in )
(kg/h)
0390-PSV- Exhaust Glycol The PSV is
3 3
1003 Pump Blocked outlet 2.6 m /h D Blocked outlet 2 m /h D adequately
0390-PD-002D sized.
0390-PSV- Exhaust Glycol The PSV is
External Fire -
1040 Filter Fire 203 D 281 D adequately
Liquid
0390-CL-003D sized.
0390-PSV-605 Exhaust Glycol Unknown – no
External Fire -
Filter N/A N/A N/A 193 D data on existing
Liquid
0390-CL-601A valve available.
0420-PSV- HP Fuel Gas KO Fire (Vapour The PSV is
1,025
801A/B Drum Control valve filled vessel) undersized
30,000
420-VA-002 failure Control valve based on the
36,622
failure PV201 control valve
K Control valve L (PV201) failure
failure 33,897 case.
Fire 625 PCV202
Blocked
10,437
outlets
0420-PSV- Fuel Gas Start-up External Fire - The PSV is
179
1007 Heater vapour adequately
Fire 527 D D
420-HM-002 Abnormal Heat sized.
132
Input
0420-PSV- LP Fuel Gas KO External fire The PSV is
1008A/B Drum (vapour filled 277 undersized for
420-VA-001 Control Valve vessel) failure of
Failure (0420- 7,450 Control valve PV007A/B plus
PV-007) failure PV- bypass.
1,227
L 1004 plus FO- Q
1001
Control valve
Control Valve
failure
Failure (0420- 31,852 19,448
PV007A/B
PV-1004)
plus bypass
Relief Valve System ENPPI Sizing Required Selected Atkins Sizing Relief load Selected Comments
2 2
Case Relief load Orifice (in ) Case (kg/h) Orifice (in )
(kg/h)
Control valve
failure PV-
3,921
023A plus
bypass
Control valve
failure PV-
2,303
035B plus
Fire 1,574
bypass
Blocked
1,410
outlets
0600-PSV- Nitrogen Control valve The PSV is
2,310
1006 Distribution Header failure undersized
Control Valve Blocked based on the
2,000 F 188 G
Failure outlets control valve
Abnormal heat failure case.
HOLD
input
0850-PSV- Water / HC External pool The PSV is
1,286
002A/B Separator fire (max HC) undersized
0850-VA-001 Gas blowby External pool based on the
(0850-FCV- fire (max 1,881 gas blowby
20,596
001) Taurt water) case.
Slugcatcher CV failure
(0850-FCV- 193,800
001)
CV failure
J 14,241 Q
(0300-FV-001)
Gas blowby
(0850-FCV- 1,328,433
External pool
001) Taurt (liquid)
fire (max 504
Slugcatcher
water)
Gas blowby
(0850-FCV- 50,502
001) Taurt (vapour)
Slugcatcher
Relief Valve System ENPPI Sizing Required Selected Atkins Sizing Relief load Selected Comments
2 2
Case Relief load Orifice (in ) Case (kg/h) Orifice (in )
(kg/h)
Gas blowby
External pool (0300-FV-001)
2,531 116,047
fire (max HC) Ha’py
Slugcatcher
Total blocked
Gas blowby 10,249
outlets
(0300-FV-001)
13,568 Blocked
Ha’py
outlets 40
Slugcatcher
(vapour)
0850-PSV- Condensate Outlet Control Valve The PSV is
1005 of 0850FCV002 undersized
Water/Hydrocarbon 7,567 based on the
Fails Open:
Separator (0850 Liquid Flow Accelerated
VA 001) Control Valve Liquid Flow
0850FCV002 case.
Control Valve Fails Open: 135,941
4,190 G Accelerated P
Failure
Liquid Flow
Control Valve
0850FCV002
2,818
Fails Open:
Gas Blowby
Blocked Outlet 3486
850-PSV- Taurt Slugcatcher The PSV is
External Fire 11,315
1023A/B 850-VQ-001 undersized
External Fire – based on the
Blocked vapour 1443 inadvertent valve
258,283 P expansion 6T+Q
Discharge opening case.
Blocked Outlet 236,484
Inadvertent
9,200,054
valve opening
0850-PSV- Methanol Storage External Fire 2,016 The PSV is
1025 Tank, 0850-TC- Fire 2,010 H Control valve R undersized for all
3,345
003 failure cases with the
Relief Valve System ENPPI Sizing Required Selected Atkins Sizing Relief load Selected Comments
2 2
Case Relief load Orifice (in ) Case (kg/h) Orifice (in )
(kg/h)
Reverse Flow exception of
from Methanol reverse flow
6776
Injection - (methanol).
methanol
Reverse Flow
from
Methanol
312,807
Injection –
displaced
liquid
Reverse Flow
from Methanol
1709
Injection -
vapour
Table B.1 – Comparison of Critical Devices
Appendix C
Relief Device Selection
Pres T(°C)
barg T(°C) barg bar barg
(barg) min/max
0190-PSV-001 Conventional V 110.0 N/A N/A 133.1 272 6.82 3.3 10.12 3.0% Y
0210-PSV-012A Balance Bellows V 15.0 N/A N/A 18.15 218 7.16 2.38 9.54 64% N
0210-PSV-012B Balance Bellows V 15.0 N/A N/A 18.15 218 7.16 2.38 9.54 64% N
0210-PSV-021A Balance Bellows V 18.4 N/A N/A 22.264 216 7.33 0.3 7.63 41% Y
0210-PSV-021B Balance Bellows V 18.4 N/A N/A 22.264 216 7.33 0.3 7.63 41% Y
0210-PSV-032 Balance Bellows V 9.2 N/A N/A 11.132 140 7.16 1 8.16 89% N
0210-PSV-1004 Balance Bellows V 17.5 18.4 N/A 21.175 229 7.16 0.13 7.29 42% Y
0210-PSV-1005 Balance Bellows V 17.5 18.4 N/A 21.175 229 7.16 0.13 7.29 42% Y
0210-PSV-1006 Balance Bellows V 14.5 15.0 N/A 17.5329 218 7.16 0.85 8.01 55% N
0210-PSV-1007 Balance Bellows V 14.5 15.0 N/A 17.5329 218 7.16 0.87 8.03 55% N
0210-PSV-1028A Pilot V 9.2 9.2 N/A 11.132 298 7.33 0.56 7.89 86% Y
0210-PSV-1028B Pilot V 9.2 9.2 N/A 11.132 298 7.33 0.56 7.89 86% Y
0300-PSV-1024A Pilot V 110.0 110.0 N/A 133.1 286 6.33 9.2 15.53 14% Y
0300-PSV-1024B Pilot V 110.0 110.0 N/A 133.1 286 6.33 9.2 15.53 14% Y
Pilot Operated
V 100.0 N/A 93.5 12.15 14% Y
0320-PSV-1026 Modulating 85.0 55 7.9 4.25
0320-PSV-1027A Balance Bellows V 17.5 18.4 N/A 19.25 -65 7.4 2 9.4 54% N
0320-PSV-1027B Balance Bellows V 17.5 18.4 N/A 19.25 -65 7.4 2 9.4 54% N
0320-PSV-1029A Balance Bellows V 85.0 85.0 N/A 98.6 47 7.8 5.94 13.74 16% Y
0320-PSV-1029B Balance Bellows V 89.3 85.0 N/A 98.175 47 7.8 5.94 13.74 15% Y
PSV Tag Type Phase Device Device Design Upstream Conditions SUIMP Built- Total % Back Adequate
Set Conditions Back up Back pres pres (Y/N)
Pres Pres Back
(barg) Pres
Pres T(°C)
barg T(°C) barg bar barg
(barg) min/max
0320-PSV-1029C Balance Bellows V 85.0 85.0 N/A 98.6 47 7.8 5.94 13.74 16% Y
0320-PSV-1030A Balance Bellows V 85.0 85.0 N/A 98.6 47 7.8 5.97 13.77 16% Y
0320-PSV-1030B Balance Bellows V 89.3 85.0 N/A 103.53 47 7.8 5.97 13.77 15% Y
0320-PSV-1030C Balance Bellows V 85.0 85.0 N/A 98.6 47 7.8 5.97 13.77 16% Y
0320-PSV-1031A Balance Bellows V 85.0 85.0 N/A 93.5 47 7.87 2.05 9.92 12% Y
0320-PSV-1031B Balance Bellows V 89.3 85.0 N/A 103.53 47 7.87 2.05 9.92 11% Y
0320-PSV-1031C Balance Bellows V 85.0 85.0 N/A 93.5 47 7.87 2.05 9.92 12% Y
0320-PSV-1032A Balance Bellows V 85.0 85.0 N/A 98.6 47 7.91 2.05 9.96 12% Y
0320-PSV-1032B Balance Bellows V 89.3 85.0 N/A 103.53 47 7.91 2.05 9.96 11% Y
0320-PSV-1032C Balance Bellows V 85.0 85.0 N/A 98.6 47 7.91 2.05 9.96 12% Y
0320-PSV-109A Conventional V 110.0 N/A N/A 133.1 276 7.68 9.4 17.08 8.5% Y
0320-PSV-109B Conventional V 110.0 N/A N/A 133.1 276 7.68 9.4 17.08 8.5% Y
0320-PSV-209A Conventional V 110.0 N/A N/A 133.1 276 7.71 9.4 17.11 8.5% Y
0320-PSV-209B Conventional V 110.0 N/A N/A 133.1 276 7.71 9.4 17.11 8.5% Y
0320-PSV-309-1A Conventional V 110.0 N/A N/A 133.1 276 7.33 7.5 14.83 6.8% Y
0320-PSV-309-1B Conventional V 110.0 N/A N/A 133.1 276 7.4 7.37 14.77 6.7% Y
0320-PSV-309-2A Conventional V 110.0 N/A N/A 133.1 276 7.33 7.5 14.83 6.8% Y
0320-PSV-309-2B Conventional V 110.0 N/A N/A 133.1 276 7.4 7.5 14.9 6.8% Y
0360-PSV-1000A Conventional V 110.0 110 N/A 133.1 332 6.37 1.75 8.12 1.6% Y
0360-PSV-1000B Conventional V 110.0 110 N/A 133.1 332 6.37 1.75 8.12 1.6% Y
0360-PSV-1002A Conventional V 110.0 N/A N/A 133.1 332 6.37 1.75 8.12 1.6% Y
PSV Tag Type Phase Device Device Design Upstream Conditions SUIMP Built- Total % Back Adequate
Set Conditions Back up Back pres pres (Y/N)
Pres Pres Back
(barg) Pres
Pres T(°C)
barg T(°C) barg bar barg
(barg) min/max
0360-PSV-1002B Conventional V 110.0 N/A N/A 133.1 332 6.37 1.75 8.12 1.6% Y
0360-PSV-801A Conventional V 110.0 N/A N/A 133.1 332 6.85 2.9 9.75 2.6% Y
0360-PSV-801AC Conventional V 110.0 110 N/A 133.1 332 6.37 1.6 7.97 1.5% Y
0360-PSV-801AD Conventional V 110.0 N/A N/A 133.1 332 6.37 1.6 7.97 1.5% Y
0360-PSV-801B Conventional V 110.0 N/A N/A 133.1 332 6.85 2.9 9.75 2.6% Y
0360-PSV-801BC Conventional V 110.0 110 N/A 133.1 332 6.37 1.6 7.97 1.5% Y
0360-PSV-801BD Conventional V 110.0 N/A N/A 133.1 332 6.37 1.6 7.97 1.5% Y
0360-PSV-811A Pilot V 110.0 N/A N/A 121 104 6.85 6.37 13.22 12% Y
0360-PSV-811B Pilot V 110.0 N/A N/A 121 104 6.85 6.37 13.22 12% Y
Pilot Operated
V N/A N/A 20.24 10.7 58% Y
0360-PSV-812 Modulating 18.4 15 6.8 3.9
Pilot Operated
V 18.4 N/A 20.24 10.7 58% Y
0360-PSV-812A Modulating 18.4 15 6.8 3.9
0360-PSV-821A Conventional V 110.0 N/A N/A 133.1 332 6.85 2.1 8.95 1.9% Y
0360-PSV-821B Conventional V 110.0 N/A N/A 133.1 332 6.85 2.1 8.95 1.9% Y
0360-PSV-831A Pilot V 110.0 N/A N/A 121 104 6.85 5.7 12.55 11% Y
Pilot Operated
V 110.0 N/A 121 13.34 12% Y
0360-PSV-831AC Modulating 110.0 106 6.37 6.97
Pilot Operated
V N/A N/A 121 13.34 12% Y
0360-PSV-831AD Modulating 110.0 106 6.37 6.97
0360-PSV-831B Pilot V 110.0 N/A N/A 121 104 6.85 5.7 12.55 11% Y
Pilot Operated
V 110.0 N/A 127.05 13.34 12% Y
0360-PSV-831BC Modulating 115.5 106 6.37 6.97
Pilot Operated
V N/A N/A 127.05 13.34 12% Y
0360-PSV-831BD Modulating 115.5 106 6.37 6.97
PSV Tag Type Phase Device Device Design Upstream Conditions SUIMP Built- Total % Back Adequate
Set Conditions Back up Back pres pres (Y/N)
Pres Pres Back
(barg) Pres
Pres T(°C)
barg T(°C) barg bar barg
(barg) min/max
Pilot Operated
V 110.0 N/A 121 13.34 12% Y
0360-PSV-831CC Modulating 110.0 106 6.37 6.97
Pilot Operated
V N/A N/A 121 13.34 12% Y
0360-PSV-831CD Modulating 110.0 106 6.37 6.97
0390-PSV-1040 Conventional V 8 8.0 N/A 9.68 191 0.8 0.8 10.0% Y
0420-PSV-001A Conventional V 85.0 N/A N/A 102.85 129 1.64 0.4 2.04 0.5% Y
0420-PSV-001B Conventional V 85.0 N/A N/A 102.85 129 1.64 0.4 2.04 0.5% Y
0420-PSV-1007 Conventional V 85.0 85.0 N/A 102.85 130 6.42 1.8 8.22 2.1% Y
0420-PSV-1008A Pilot V 5.0 5.0 N/A 5.5 21 1.64 0.44 2.08 42% Y
0420-PSV-1008B Pilot V 5.0 5.0 N/A 5.5 21 1.64 0.44 2.08 42% Y
PSV Tag Type Phase Device Device Design Upstream Conditions SUIMP Built- Total % Back Adequate
Set Conditions Back up Back pres pres (Y/N)
Pres Pres Back
(barg) Pres
Pres T(°C)
barg T(°C) barg bar barg
(barg) min/max
0850-PSV-1005A Balance Bellows V 17.5 18.4 N/A 19.25 30 6.4 0.3 6.7 38% Y
0850-PSV-1005B Balance Bellows V 17.5 18.4 N/A 19.25 30 6.4 0.3 6.7 38% Y
Pilot Operated
V 110.0 N/A 121 15.45 14% Y
0850-PSV-1023A Modulating 110.0 40 6.4 9.05
Pilot Operated
V 110.0 N/A 121 15.45 14% Y
0850-PSV-1023B Modulating 110.0 40 6.4 9.05
0850-PSV-1025 Conventional V 3.5 3.5 N/A 4.235 115 0.21 0.35 0.56 10.0% Y
0420-PSV-1033A Conventional V 5 N/A N/A 6.05 134 0.16 0.2 0.36 4.0% Y
Appendix D
Inlet Line Verification
0360-PSV- Onshore Gas HP discharge 8’’ Interlocked Isometrics not Isometrics not
4 8 Y N
831CD Coolers (0360-HC-001D) Closed available available
Onshore Gas Compressor HP
1 1/2 3’’ Interlocked Isometrics not Isometrics not
0360-PSV-1002A Discharge Drum (0360-VA- 3 Y N
Open available available
002D)
1 1/2’’
Pig Receiving Trap (0190-VR- Interlocked Isometrics not Isometrics not
0190-PSV-001 1 1/2 1 1/2 N N
001) Open available available
10’’
Tuart Slug Catcher (0850-VQ- Horizontal
0850-PSV-1023A 4 10 Interlocked Y N N
001) section(s)
Open
10’’
Tuart Slug Catcher (0850-VQ- Horizontal
0850-PSV-1023B 4 10 Interlocked Y N N
001) section(s)
Closed
6” Locked Horizontal
0360-PSV-812 Unit 0360 (to 0210-HA-001A) 3 6 N N N
Open section(s)
6” Locked Horizontal
0360-PSV-812A Unit 0360 (to 0210-HA-001A) 3 6 N N N
Closed section(s)
Slopes directly
before PSV are
greater than
0320-PSV-309- Tube side of Gas/Gas 3’’ Interlocked Isometrics not
2 3 1:200, however Y N
1A Exchanger (0320-HA-003A/B) Closed available
isometrics for
upstream lines
missing
Slopes directly
before PSV are
greater than
0320-PSV-309- Tube side of Gas/Gas 3’’ Interlocked Isometrics not
2 3 1:200, however Y N
2A Exchanger (0320-HA-003A/B) Open available
isometrics for
upstream lines
missing
Shell Side of Gas/Gas 4’’ Locked Isometrics not Isometrics not
0320-PSV-1031A 3 4 Y N
Exchanger (0320-HA-003A/B) Open available available
Slopes directly
before PSV are
greater than
0320-PSV-309- Tube side of Gas/Gas 3’’ Interlocked Isometrics not
2 3 1:200, however Y N
1B Exchanger (0320-HA-003C/D) Open available
isometrics for
upstream lines
missing
Slopes directly
before PSV are
greater than
Shell Side of Gas/Gas 4’’ Locked Isometrics not
0320-PSV-1032A 3 4 1:200, however Y N
Exchanger (0320-HA-003C/D) Open available
isometrics for
upstream lines
missing
Slopes directly
before PSV are
greater than
Shell Side of Gas/Gas 4’’ Locked Isometrics not
0320-PSV-1032B 3 4 1:200, however Y N
Exchanger (0320-HA-003C/D) Open available
isometrics for
upstream lines
missing
Slopes directly
before PSV are
greater than
Shell Side of Gas/Gas 4’’ Locked Isometrics not
0320-PSV-1032C 3 4 1:200, however Y N
Exchanger (0320-HA-003C/D) Closed available
isometrics for
upstream lines
missing
Slopes ok (but
Isometrics not
Glycol/HC Separator (0210-VA- 1” Locked Isometrics not
0210-PSV-021A 1 2 available between N N
001) Open available
TP-575/576 &
Vessel)
Slopes ok (but
Isometrics not
Glycol/HC Separator (0210-VA- 1” Locked Isometrics not
0210-PSV-021B 1 2 available between N N
001) Closed available
TP-575/576 &
Vessel)
Exhaust Glycol Pump D (0390- 2” Locked Slope towards
0390-PSV-1003 1 2 Y N N
PD-002D) Open PSV
Slopes directly
before PSV are
greater than
1” Locked Isometrics not
0420-PSV-001A Fuel Gas Heater (0420-HM-001) 1 1 1/2 1:200, however Y N
Open available
isometrics for
upstream lines
missing
Slopes directly
before PSV are
greater than
1” Locked Isometrics not
0420-PSV-001B Fuel Gas Heater (0420-HM-001) 1 1 1/2 1:200, however Y N
Open available
isometrics for
upstream lines
missing
Fuel Gas Knock Out Drum
6” Locked Horizontal
0420-PSV-1008A (0420-VA-001) 3 6 Y N N
Open section(s)
Fuel Gas Knock Out Drum
6” Locked Horizontal
0420-PSV-1008B (0420-VA-001) 3 6 Y N N
Open section(s)
6” Locked
HP Fuel Gas Knock Out Drum Open Horizontal
0420-PSV-801A 3 6 Y N N
(0420-VA-002) Interlocked section(s)
Open
6” Locked
HP Fuel Gas Knock Out Drum Closed Horizontal
0420-PSV-801B 3 6 Y N N
(0420-VA-002) Interlocked section(s)
Closed
0360 Compressor
0360-BDV-1003 6 6 6” Locked Open Horizontal section(s) Y N N
Suction Header
0360-BDV-912C 0360-VA-002C Train C 8 8 8” Locked Open Horizontal section(s) N N N
Low temperature
0320-BDV-1001 Separator (0320-VA- 4 4 4” Locked Open Horizontal section(s) Y N N
401)
Glycol/HC Separator
0210-BDV-021 1 1 1” Locked Open Missing isometrics Y N Missing isometrics
(0210-VA-001)
HP Fuel KO Drum
0230-BDV-902 3 3 / Horizontal section(s) N N N
(0420-VA-002)
Set Rated
Existing/ Atkins Atkins Adequate
PSV Tag Type Equipment Pressure Phase Flow Comments
New ΔP (bar) % (Yes/No)
(barg) (kg/h)
Missing isometric for line
0420-410-FG-4"-1A3
0420 PSV 1008A/B Existing Pilot 0420-VA-001 5 V 8119 0.42 8.4% N
Tp346 to 0420-VA-001.
Rated Flow
Missing isometric for line
0420-410-FG-4"-1A3
0420 PSV 1008A/B Existing Pilot 0420-VA-001 5 V 8118 0.42 8.4% N
Tp346 to 0420-VA-001.
Required flow.
Only A valve done as B
0600 PSV 1006A/B New Conv. 0600HM001 10.6 V 2259 0.84 7.9% N
valve Isometric missing
0850 PSV 002A/B Existing Conv. 0850-VQ-001 Unable to assess as Isometric not available
Only A valve done as B
0850 PSV 1005A/B New B/B 0850-HA-002A 17.5 V 4190 0.415 2.4% Y valve. Isometric missing
for TP-591 to FCV-002
Isometric only up to TP-
0850 PSV 1023 Existing Conv. 0850-VQ-001 110 V 325302 3.97 3.6% N
060.
0850 PSV 1025 Existing Conv. 0850-TC-003 3.5 V 2013 0.276 7.9% N
Appendix E
Tail Pipe and Flare Header Summary
Angle of Entry to
Flange (in)
Insulation
Pockets
Size (in)
Material
Header
Note 1
Phase
Open
Line No. Description Slope Comments
Angle of Entry to
Flange (in)
Insulation
Pockets
Size (in)
Material
Header
Note 1
Phase
Open
Line No. Description Slope Comments
Not Sufficient -
0360-302-BD- 0360-PSV-801AC sections with Not Sufficient - sections with
None 6 3 FB Yes LTCS None LV 45 5.5 4.355
6"-1B3-V Tail pipe slope less than slope less than 1:400.
1:400
Not Sufficient -
0360-303-BD- 0360-PSV-801BC sections with Not Sufficient - sections with
None 6 3 FB Yes LTCS None LV 45 5.5 4.358
6"-1B3-V Tail pipe slope less than slope less than 1:400.
1:400
0360-305-BD- 0360-PSV-831AC Not Sufficient - Horizontal
Horizontal Section None 12 6 FB Yes LTCS None LV 45 4 4.352
12"-1B3-V Tail Pipe section.
0360-306-BD- 0360-PSV-831BC Not Sufficient - Horizontal
Horizontal Section None 12 6 FB Yes LTCS None LV 45 4 4.358
12"-1B3 Tail Pipe section.
0360-217-BD- 0360-PSV-831CC Section sloping Section sloping back towards
None 12 6 FB Yes LTCS None LV 45 5 4.361
12"-1B3 Tail Pipe back towards PSV PSV.
0360-309-BD- 0360-PSV-1000A Not Sufficient - Horizontal
Horizontal Section None 6 3 FB Yes LTCS None LV 45 5.5 4.363
6"-1B3-V Tail Pipe section.
Not Sufficient -
0360-310-BD- 0360-PSV-1000B sections with Not Sufficient - sections with
None 6 3 FB Yes LTCS None LV 45 5.5 4.365
6"-1B3-V Tail Pipe slope less than slope less than 1:400.
1:400
LP model
0390-400-BD- 0390-PSV-515 Tail Not Sufficient - Horizontal
Horizontal Section None 4 2 FB Yes CS None LV 45 not 2.951
4"-1A3-V Pipe section.
available
Angle of Entry to
Flange (in)
Insulation
Pockets
Size (in)
Material
Header
Note 1
Phase
Open
Line No. Description Slope Comments
Sloping back
0390-614-GY- 0390-PSV-1003 Tail
towards PSV None 2 2 FB Yes CS None L Relieves back into process
2"-1A3-V pipe
outlet
Cold Flare
0230-430-BD- 0420-PSV-801A Tail Not Sufficient - Horizontal
Horizontal Section None 8 4 FB Yes LTCS None LV 45 model not 2.821
8"-1B3-V Pipe section.
available
Cold Flare
0230-443-BD- 0420-PSV-801B Tail Not Sufficient - Horizontal
Horizontal Section None 8 4 FB Yes LTCS None LV 45 model not 3.005
8"-1B3-V Pipe section.
available
Not Sufficient - Not Sufficient - sections with
Cold Flare
0420-400-BD- 0420-PSV-1007 Tail sections with slope less than 1:400. Isometric
None 4 2 FB Yes LTCS None LV HOLD model not 12.879
4"-1B3-V pipe slope less than missing for 6"-FH-0012-01CS-
available
1:400 2PW
Cold Flare
0230-403-BD- 0420-PSV-1008A Not Sufficient - Horizontal
Horizontal Section None 6 4 FB Yes SS None LV 45 model not 3.301
1C1-V Tail pipe section.
available
Cold Flare
0230-404-BD- 0420-PSV-1008B Not Sufficient - Horizontal
Horizontal Section None 6 4 FB Yes SS None LV 45 model not 2.974
1C1-V Tail pipe section.
available
0600-203-UN- 0600-PSV-1006B
Atmospheric Vent
2"-1B3-F Tail Pipe
0600-204-UN- 0600-PSV-1006A
Atmospheric Vent
2"-1B3-F Tail Pipe
Angle of Entry to
Flange (in)
Insulation
Pockets
Size (in)
Material
Header
Note 1
Phase
Open
Line No. Description Slope Comments
Isometric Length
Angle of Entry to
Flarenet Length
(m) Note 1
Insulation
Pockets
Material
Header
Phase
(m)
Line No. Description Slope Comments
LP model
Isometric not available for 0230-003-BD-8"-
0230-407-BD-8"-1A3-V LP Sub Header Sufficient None CS None LV 45 not 138.773
A02-V
available
TP-261A
0300-007-BD-10"-A06- Horizontal section. Isometric only available
Wet Flare Sub header Horizontal section None CS None N/A HOLD not in 0.723
V up to TP-261A
flarenet
Isometric Length
Angle of Entry to
Flarenet Length
(m) Note 1
Insulation
Pockets
Material
Header
Phase
(m)
Line No. Description Slope Comments
0230-411-BD-20"-1C1- Not Sufficient - slope less than Not in Not Sufficient - slope less than 1:400.
Wet Flare Sub header None SS None LV 2.579
V 1:400 model Isometric only available to TP-045
Section near TP-046 slope is
Section near TP-046 slope is 1:1500. Other
1:1500. Other sections where
0230-437-BD-18”-1A3- sections where slope is <1:400 despite
Wet Flare Sub header slope is <1:400 despite being None CS/LTCS None LV 90 211.8 223.117
V being labelled as 1:400. Section with 1:625.
labelled as 1:400. Section with
. Isometric only available to TP-046
1:625.
Isometric Length
Flarenet Length
(m) Note 1
Insulation
Pockets
Material
(m)
Line No. Description Slope Comments
Appendix F
HP Wet Flare model Review
The model of the HP Wet Flare Header for the WHX Project does not reflect information from PSV sizing calculations or isometrics. The relief loads for all
new and existing PSVs were checked against calculation data (listed in Table 1 of Verification Report ENP-WHUPZZ-PR-REP-1036 Rev G6) and there were
many inconsistencies in relation to rated and required relief flowrates, set pressures and accumulation. However, no PSVs have been run in any of the flare
scenarios. There are also discrepancies between the isometrics (see Proforma 6.0) and P&IDs in terms of pipework routing, lengths and location of tie in
points.
It should be noted that the flarenet model is Rev D2, and the HP Blowdown System Hydraulic Verification Report of the same document number is Rev D3,
which could be the reason the data does not match. The flare model should be updated to provide an accurate model of the network in order to size headers
and sub headers correctly and evaluate the back pressures within the system.
Appendix G
Calculations
G.1 Calculations
The following calculations are included.
email: info@atkinsglobal.com
www.atkinsglobal.com