Professional Documents
Culture Documents
CHAPTER-1
INTRODUCTION
ABOUT SOBHA LIMITED
CHAPTER-2
INTRODUCTION OF THE PROJECT
SOBHA DREAM ACRES
(Sobha dream series project)
This is the area which includes the Outer Ring Road(ORR), Sarjapur and
Whitefield. Since 2000, this area has become the centre of the IT/ITES
business which is the main employers for young achievers, who are the core
market for Sobha Dream Acres.
This area is also showing signs that it will become another of Bangalore’s
entertainment and education hub with many malls and schools being planned
and built, which makes buying home here even more attractive.
Safety is very much important in site and hence safety training is so much
necessary for the workers who in construction.
General
An accident may occur in site due to the following reasons. They are:
Elimination
Substitution
Administration control
Personal protection control
Engineering control
Safety shoe
Knee guards
Safety mask
Safety glass
Helmets
Goggles
Aprons
CHAPTER-3
Precast method of construction
Precast also has lower lifetime costs than any other building solution. It is
possible due to consistent high quality of industrially produced products.
Precast minimizes the structural and facade maintenance. With precast,
logistics needs are minimal. Precast floors, walls, frames and foundations are
transported to a construction site ready- to-install. Logistics to building site is
arranged with just one delivery vehicle instead of several raw material
transfers back and forth.
Precast concrete suits well for any type of building like residential,
commercial, industrial, public to name a few. There is a suitable solution for
both indoor and outdoor precast production. The smart match can be found
for different kinds of building projects in terms of elements produced, factory
capacity and labour needs. Precast can be made into any shape or colour and
finished with several techniques. This together with longer span gives
architects and designers more freedom than ever. Precast is used within
exterior and interior walls, the precast concrete is affording the opportunity to
properly cure and be closely monitored by plant employees.
Advantages:
Entire concrete blocks are cured Curing is not done uniformly at sites.
uniformly for the required amount of
time.
Production is not hampered with Production is severely hampered.
weather delays.
Aesthetically pleasing appearance. Special aesthetic design is required.
1. Circulation system
2. Stationary system
CHAPTER-4
Production
1. Circulation system
In the circulation system, pallets are used for production of precast
elements. Pallets are defined as Mild steel table which moves from one
station to another station with the help of rollers. There are different
sections in the Circulation System such as reinforcement section,
shuttering section, cage fixing, plumbing and electrical works, quality
control checking etc.
Procedure:
Firstly, the pallets are cleaned to remove the traces of old concreting
and lubricating oil is applied on moulds.
After a fixed time, the pallet moves to next station where marking is
done. In the marking station, Robotic plotter marks the dimensions on
the pallet using paint.
Shuttering work is carried out by magnets.
2. Stationary system
The elements which are not able to be casted in circulation system are
casted in stationary system like sun shades, staircase etc. In this system
all the process of casting happens at a place hence the name stationary
system came.
CHAPTER-5
Erection
Erection is a process in which the precasted elements are lifted to their pre-
planned or pre decided place with the help of crane.
1. Equipments
Tower crane
4. Machineries
Hammer drills- 3kg and 5kg
Impact wrinch
Welding machine
Hydraulic jacks
Chipping machine- 5kg and 10kg
1. Walls
a) WA walls
The Thickness of WA walls is 200mm.
These walls are used as main walls.
b) WB walls
The Thickness of WB walls is 160mm.
These walls are used as main walls.
c) WC walls
The Thickness of WC walls is 100mm.
These walls are used as main walls.
d) WD walls
The Thickness of WD walls is 250mm.
These walls are used as retaining walls.
e) WE walls
The Thickness of WE walls is 300mm.
These walls are used as wall columns.
2. Columns
a) CA columns
The thickness of CA columns is 300mm.
These are used in tower area.
b) CB columns
The thickness of CB columns is 350mm.
These are used in podium.
3. Beams
a) BA beams
The breadth of these beam is 300mm.
These are used in tower area.
b) BB beams
The breadth of these beams is 750mm.
These are used in podium.
4. Slabs
a) HA slabs
These are used in tower areas.
The height of lattice girder is 55mm.
b) HB slabs
These are provided at the non-tower areas.
The height of lattice girder in lower basements area is 128mm.
The height of lattice girder is in upper basements area is 168mm.
5.4 FOUNDATION
Foundation is the substructure of the building. Which transfers the load
from superstructure to the ground.
Footing which are provided under each column independently are called
as isolated footing. They are usually square, rectangular or circular in
section. Footing is laid on PCC. Before laying PCC termite control is done
to restrict the termites to damage the footing. These footing are most
economical when compared to other kind of footing. These kind of footing
are provided where the soil bearing capacity is generally high. Isolated
footing comprise of a thick slab which may be flat or stepped or sloped. It
is most commonly used footings for reinforced cement concrete column
because it is simple and most economical.
over large are, the footings are overlapped each other instead of
providing each footing on each column all columns are placed in
common footing. A raft foundation is a solid reinforced concrete slab
covering entire are beneath the structure and supporting all the
columns. Such foundation due to its own rigidity minimizes differential
settlements.
b) Earth excavation :-
It is a process of excavating a trench on the earth for the footing
purpose. The size of the trench should bigger in both the sides than the
footing size. Excavation of soil is done up to the required depth. For
isolated footing, the depth to should be one and half times the width of
the foundation. For the hard soils, when the depth of excavation is less
than 1.5m the sides of the trench do not need any external support. If
the soil is loose or the excavation is deeper, some sort of sharing is
required to support the sides from falling.
c) Soil compaction :-
Soil compaction is the process where a mechanical pressure is used to
compress the soil mass for the purpose of increasing the strength.
f) Reinforcement :-
Concrete is good in resisting compression but it is very weak in
resisting tension. Hence, reinforcement is provided in the concrete
wherever tensile stress is expected. The best reinforcement is steel,
since tensile strength of steel is quite high and the bond between steel
and concrete is good. As the elastic modulus of steel is high, for the
same extension the force resisted by steel is high compared to
concrete.
The method and sequence of installing wall panels are outlined as follows:-
1. Precast walls are manufactured and will require the use of a crane to
lift the precast walls off from the delivery truck and into the correct
spots for installation.
2. Walls are lifted one after the other with the help of the cranes.
3. The places where and all the walls need to be installed are initially
fixed with the dowel rods having size of 20mm.
4. Precast walls will be having inbuilt holes called as dowel tube made at
the time of manufacturing itself. So, the walls are lifted and it is fixed
on to the dowel rods through the dowel tubes present below the base of
the walls.
5. The dowel tubes of the precast walls are joined onto the dowel rods.
Likewise, all the walls are installed throughout the flat.
There are single looped and double looped shear loops. In retaining
walls single looped joints are used and in areas where there is more
shear loads like lift areas double looped joints are used. Loop joint has
220mm long wire bent in the form of a loop during the production
process only. 100mm length is exposed out and 20-25mm of
overlapping is maintained between the adjacent loops. A 12mm
diameter steel inserted between the loops of adjacent walls which is
called a shear key.
Profile joint:
Profile joint has groves of size 80*210mm and depth of 20mm each
wall consists of 5 numbers of such grooves. Profile joints are provided
where the shear force is considerable.
Plain joint:
Plain joints are provided where there is negligible shear force. Usually
provided between non-load bearing wall which are of 100mm
After fixing these walls to its position, a push and pull prope is attached to the
wall for providing supports. There will be two push and pull prope on each
wall for giving supports.
6. The materials used in preparing are 1bag of GP2N and water. 1bag of
GP2N will be containing 25kg of cement.
7. Water is added to the cement, GP2N in the ratio 1:4 which is mixed by
using a grouting machine called as Putzmeister.
1. The tops of the precast walls are made into L shaped for the slab to fit
on it correctly.
2. Slabs to be installed in typical floors will be having thickness of 60mm
reinforced with Lattice Girder.
3. We erect these precast slabs with the help of cranes on to the top of the
wall support.
4. Based on the top surface clearance, the level of the slab is determined.
5. After slab has been erected completely, we have to focus on the 90mm
conventional slab by binding the seismic rods alternatively.
6. Reinforcement is provided to the conventional slab as per the design
specified by the designers –
i. Providing edge bars or bottom bars at edges.
ii. Seismic bars from walls are bent on the slabs alternatively and
tightened with Lattice Girder.
7. Up stand bars having 8mm thickness are provided in the area of 50mm
down at the bathroom. We have to make the surface equal by using
these up stand reinforcement.
8. Crank bars are provided in the area of bathroom
9. And for the balcony. 10mm connecting rods and u-bars are provided
because of its contiliver property. These 10mm rods are connected with
the 8mm crank bars.
10.All the slab reinforcement are tightened to the precast slab with the
help of Lattice Grid.
11. A layer of concrete is poured and surface clearance is taken after the
curing of the cement.
12.Simultaneously all the works such as pouring cement after
reinforcement, erections will be taking place at the same time.
13.After complete curing, for the erection of next floor slab a red color is
marked which indicates the point where the wall needs to be fixed and
even the dimensions of the wall will be also marked together.
14.Then a blue color mark is made for safeguarding the electrical pipes.
15.And the stairs side of the slab edges included corbel supports for
installation of staircase.
CHAPTER-6
Basement
The floor of a building which is partly or entirely below ground level. Used
for parking of vehicles and other purposes. In this apartment we can find two
types of basement in each wing. They are:-
1) Lower Basement
2) Upper Basement
Compaction of soil:-
Soil compaction is defined as the method of mechanically increasing the
density of soil in construction. This is a significant part of the building
process.
In this process compacting the soil layer by layer, the each layer thickness is
minimum 100mm. after compacting of required height, test the soil density
by the method of dynamic cone penetration test (DCP)
Dynamic cone penetration test has been successfully utilized for estimating
the strength of soils and the thickness and location of subsurface soil layer.
The Dynamic cone penetration used consists of 16mm steel rod, to which a
tempered steel cone with a 20mm base diameter and a 60 point angle
attached. The DCP is driven into the soil by the 8kg hammer with a dropping
height of 575mm.
Manufacture sand with proper water content and give surface clearance . The
completion of GSB layer. Have to lay the polyethylene sheet on GSB
surface.
Low density polyethylene sheet has a big role in offering plastic protection. It
is used to control the water drops from Plain cement concrete to the granular
sub base layer . Then pour the plain cement concrete on LDP sheet.
Vacuum dewatering using vacuum pump and suction mat top curves
filter pads
Flooring and troweling of the concrete pavement using Trimix flooring
machine.
CHAPTER-7
Finishing Works
7.1 Snagging
Snagging does not have an agreed meaning and is not a contractual term. It is
a slang expression widely used in the construction industry to define the
process of inspection necessary to compile a list of minor defects or
omissions in building works for the contractor to rectify.Generally snagging
refers to a process that takes place a fortnight or so prior to practical
completion when an area is considered complete and offered ready for
inspection. Snagging is common term throughout construction.
Snagging inspections need to be done after there has been a proper clean. The
area should be cleaned throughout and should be fully accessible. The spaces
should be clear of any tools or materials. There should also be full, permanent
lighting to ensure that everything can be easily inspected, systems such as hot
water, alarms, ventilation or under floor heating should all be checked to be
in good working order.
A snagging list is prepared and issued by the company Sobha itself, typically
to the engineers. The company, Sobha has its own procedure in snagging
process. In this snagging list, we can find various stages from beginning to
the end of the process. The stages which are been included in the snag list are
as follows –
1. Snagging 1
2. Snagging 2
3. Snagging 3
4. Snagging 4
The precast walls will be erected by the erection department. After the
completion of erection, clearance is taken from the erectors for pursuing the
next process. Hence, after taking clearance from the erectors, we need to get
through into the faults and incomplete work in the flat. The whole task is
divided into each department in each different processes. The work which is
to be performed in this stage is as follows-
Bore packing
Bore packing is one of the preparatory works for water proofing. This is to be
ensured in plumbing and electrical penetrations. For example, bore packing
will be done for plumbing lines that are crossing the RCC members in toilets.
Bore packing is the process of fixing plumbing pipes in RCC members (slabs
or beams or RCC walls) in their cut outs/core cuts.
Initially, clearance is taken from the erectors. The core cutting location is
marked first on the floor considering the tile layout. Then the core cutting is
done with diameter slightly higher than the plumbing pipe. For better
bonding, side face of the core cutting and plumbing pipe should be
roughened. From the bottom shuttering is done for holding the bore packing
material. Then the plumbing pipe is positioned properly in vertical manner
and the pipe fixing is done by aligning it. After this, the another process
called grouting is to be performed. In grouting, the material is filled into the
gaps found all around the pipe. Here, the aggregate mixture, water and
ceragrout is used as the filling material. The grouting mixture consists of 1
part off grovels and 3 parts of ceralex. All these processes are take place
simultaneously. After grouting, we leave that up to two hours for the water
proofing work. Also GP2 cement is used for flooring. In each and every step,
the designers specifications is been followed strictly. After the completion of
bore packing, we remove the shutters which is used to cover the packing and
then surface is cleaned. This ends the process of bore packing.
While there are many products, including joint compound and spackle, that
can be used to patch or smooth out different types of walls. Wall putty is
particularly useful on plaster or concrete walls. Wall putty can fill in small
cracks and holes and adding a couple thin layers over the wall improve its
appearance and help paint adhere better.
Once erection has been completed, there will be definitely gaps and joints
between the walls. So, the gaps between these walls should be filled. Hence,
meshes are used to avoid crack formed due to the insufficient gap filling
between the walls. On the interior walls, it is often applied in corners since
the walls seldom is entirely connected which give a risk for shrink and
movement cracks which the mesh lowers. Mesh work is for vertical joints of
walls, corners and floors of toilets.
The wire mesh is fixed to the connecting parts bet. The wall and the beam,
panel and the column and door hole and the ring beam. We should make
smooth and straighten the steel wire mesh before attaching. The mesh used is
having a width of 15cm which is placed at corners in right angle of in L shape
with equal length of 7.5cm at each of the walls. The cement paste and the
professional mortor is used as primer. Then we plaster and make pack it
down hard in layers and make sure that there is no cavity.
When the gap is filled with mesh, we should clean the surface of the wall.
Then the putty works starts. If the undulation or minor, it will be filled and
leveled with putty itself. For major undulation on the wall surface, plaster
work is provided.
Give the putty to dry, then smooth it out by sanding over it lightly with fine
sandpaper. And the patched areas are then coated with a primer. Only a one
coat of primer is applied on to the wall. And the level is checked, if any low
areas are found, then it is leveled by applying a coat of primer. After the
completion of putty works, the electrical holes entirely in the flat. Finally
passages and electrical boxes are prepared using springs or threads.
Plumbing
Surface is made free from oil, grease or any other particles. Cement mortar is
prepared in the ratio 1:3. And then the proofing material cerolex is added
with cement mortar. After mixing the cement mortar is splattered over the
surface
To ensure the waterproofing works were done correctly with no leakages, the
company runs out tests to rule out any water leakages. Once the company has
completed the waterproofing works in the designated area, our team ensures
the area is leak-free by conducting a pond test after the standard curing
period.
A pond test is carried by sealing up all drainage exists in the area and
flooding the entire area by filling up water completely. The test is carried out
for 24 hours. By doing so, we apply a layer of pressure on the internal layer
without exceeding the hydrostatic head of the external layer to test the
integrity of the water repellant barrier. Any significant water level reduction
over the testing period will signify a leak in one of the cervices. When that
happens, then steps are taken to detect such leakages. The leakages can be
stopped by patching or in rare cases where the leak cannot be identified, the
entire process is repeated once again.
Screeding
After taking clearance from the electrical department, we need to evaluate the
surface of the base. Firstly, the bull mark is fixed by the erections department.
Depending on this mark, the length of the screeding floor is taken as per
mentioned in the planning.
But before the start of screeding, the floor cleaning and surface preparation is
carried out. The surface is cleaned up thoroughly to remove dust, dirt or any
loose other particles. Bull marking is made by using dumpy level and
scale(level staff). If any chipping work is to be done before the flooring, then
it is finished off first. Then based on the bull mark mentioned, we leave the
height of 0.5cm from that mark for laying the tiles. From there the complete
screeding work is carried out.
Tiling
Once the screeding work is completed, we need to clean the floor from dust,
dirt and other solid particles. This ensures that the tiled surface will be in a
level. First we need to identify the bull mark made by the erector. Then going
1m below from the bull mark we should place the tiles. A centre line is
marked by using string of wire. Dividing the lobby into two halves and even
along the opening also. This mark will help us to give a clear picture for
laying the tiles.
In this flooring, tile dimension for the hall and rooms used is
600mm×600mm. And the vertical tiles are provided to the edges of the floor.
When we get a wall where a standard tile will not fit, then it is marked and
cuts are made with the help of a tile cutter. The space between every tile is
2mm, which is compulsory so that uniform distance is maintained between
the tiles.
Tiling from main hall to the balcony is done below at a 35mm depth and
20mm depth from the main hall to the bathroom floor respectively. When all
the tiles are finished laying, we allow the tiles to dry before grouting. Then
we cover the tile with air bubble sheets to avoid dust and other particles being
entering onto the tiled floor.
Wall tiling
Wall tiles can be installed over drywall and plaster, but in wet areas, they
should be installed over cement board. We make sure that the surface is free
from dust or any other particles. We begin the tile layout by finding the
center of the wall, then we use a split level to create interesting vertical and
horizontal layout lines. Then adjust the layout lines as needed for the best
appearance along with the layout lines, spaces for grout joints will be also
included. Preparing the adhesive used is fixal. Then we apply the adhesive to
the wall with a notched trowel, holding the trowel at about 45 degrees so the
furrows of adhesive are uniform in height. Then the installation of wall tiles
begins.
The thickness of the tiles is 8mm and its dimension is 300mm×300mm. the
tiles are placed and pressed firmly to embed them into the adhesive and 2mm
space is left between each and every tile so as to maintain uniformity. Finally,
after completion of fixing all the tiles it is left to get dried. In the next stage,
grouting material is added.
In this stage, clearance is taken for incorporating frames for the doors
and the windows.
The opening of the door in the erected wall will be having an extra one
inch for the frame to fit.
Cement is applied about an inch so that frames can be installed to the
wall.
Based on requirements and the measurements mentioned in the design
a layer is filled with cement.
After the cement has cured, frames are fixed to the wall.
Once, the frames of doors and windows are installed, there will be gaps
between the frames and the wall.
In this construction, we can witness both front architrave and back
architrave. Architrave is used to cover up the frames where horizontal
head casing extends across the tops of the vertical side casings where
the elements join.
Soundafoam is used as ideal gap filler. It is a sealant offering superior
adhesion to concrete and the frames.
And a second coat of primer is applied onto the walls.
Electric lines are drawn for the sockets and outlets, then the wires are
drawn through the passages
The gap that is been left between the tiles are filled with recommended
grouting material.
Finally the sanitary fittings such as commodes, taps, showers, basin,
sinks and the necessary accessories are installed.
After the quality checking is been completed clearance is taken. This
ends the processes of snagging 2.
Almost all the works will be completed in the previous stage only,
if any task is pending then it is finished off.
Electrical switched are installed at the specified points.
Paint is applied to the walls. If any undulations are found means it
is cleared while painting only.
Sanding papers are used to remove material from surfaces and to
make the walls smoother.
Measurements of ceiling and the ceiling to the wall is taken for each
room and the main hall and then ceiling is installed.
If they found any minor dots and damages, there itself it is rectified.
Replacing of the damages is done.
Totally, the flat will be completed with all the pending works.
Clearance is taken after the quality checking is completed.
Conclusion
In this internship, I have learned a lot about the prevent scenario in the
field of Civil Engineering System. I have gained sufficient knowledge
about the technology used by the company.
CHANDAN L