Professional Documents
Culture Documents
A INTERNSHIP REPORT ON
“BUILDING CONSTRUCTION”
Submitted to Visvesvaraya Technological University in partial fulfillment of
the requirement for the award of Bachelor of Engineering degree in Civil
Engineering.
Submitted by:
Ankith .T.D
[4JN15CV011]
APRIL 2019
ACKNOWLEDGEMENT
SL NO PARTICULARS PAGE NO
1 INTRODUCTION 4
2 SITE PROFILE 5
3 SITE LAYOUT 6
4 PROJECT MANAGEMENT 7
5 PLANNING 7
6 SITE APPROVAL PROCESS 10
Introduction
SOBHA Ltd. is one of the largest and only backward integrated
real estate players in the country. Since inception they have strived for
bench mark quality, customer centric approach, robust engineering, in-
house research, and compromising business ethics, timeless values and
transperancy in all spheres of business conduct, which has made them
India`s most admired builder and most liked real estate brand on social
media.
Vision : Transform the way people percieve ‘Quality’
Mission : No Shortcuts to ‘Quality’
Philosophy : Passion at Work
Site Profile
Name of the Project : SOBHA Arena
Site Layout
Dept. of Civil Engineering, JNNCE, Shivamogga. 6
Building Construction
PROJECT
PROJECT MANAGEMENT:
Project management is the application of knowledge, skills, tools, and
techniques to project activities to meet the project requirements. Project
Management Processes for a Project, defines the five Process Groups:
Initiating
Planning
Executing
Monitoring
Controlling, and Closing.
PLANNING:
Construction planning is a fundamental and challenging activity in the
management and execution of construction projects. Estimation of the
required resources and durations for individual tasks, and the
identification of any interactions among the different work tasks. A good
construction plan is the basis for developing the budget and the schedule
for work. Developing the construction plan is a critical task in the
management of construction, even if the plan is not written or otherwise
formally recorded. In addition to these technical aspects of construction
planning, it may also be necessary to make organizational decisions
about the relationships between project participants and even which
organizations to include in a project
There are planning engineers in Sobha Arena to look after the planned
and scheduled activities at site. Scheduling of the project based on the
drawings in coordination with the project team, using primavera is the
main role of planning engineers.
Daily sight visit to check the progress at site and inform to block in
charge and project head about progress and delay of any particular
activity and plan for the same.
Tracking of activities will be done weekly basis and highlight the
critical activities at sight and inform to the project head.
Preparation of internal schedule to complete the critical activities.
They prepare the progress report with respect to the tracking on the
weekly basis.
Preparation of purchase request and work request for all the items
as per PR policy.
Planning engineers prepare the concrete schedule along with
projects and send the same to purchase department to get the
concrete as per the given schedule. Physical checking of labour
strength with respect to security labour entry.
Preparation of monthly schedule and tracking the same on daily
basis and weekly and timely reporting in case of disparity in
aspects of time schedule.
Along with cost auditors,external agency does bill checking and
verifying the quantity at site and follow up with all departments to
get the resources on time.
Mostly they prepare the critical issues with the consultation of
project heads on a weekly basis.
Site approval process is the important to be carried out before start of the
project. Each and every approval needed for the project should be
authorized correctly by the suitable department in order to run the
project smoothly without any restrictions. Following are the
corresponding departments that give approval for this project.
DEVELOPMENT
BBMP/BDA(BANGALORE DEVELOPMENT AUTHORITY)
BOARD
Itfocuses on the processes that are used to help ensure the timely
completion of the project.
SobhaArena is following the time management activities to finish
the project at scheduled time. Sequential activities are carried out to
identifying and documenting relationships among the project activities.
Control schedule is carried out to monitoring the status of the project to
update project progress and managing changes to the schedule baseline.
Milestone schedule is prepared for this project in detail. Project is
in progress as per schedule with delay of some days.
ESTIMATION:
Estimation is a technique of calculating or computing
the various quantities and the expected expenditure to be incurred in a
particular project.Estimate give an idea of the cost of the work and hence
its feasibility can be determined whether the project could be taken up
with in the funds available or not. Estimate gives an idea of time
required for the completion of the work. Estimate is also required to
control the expenditure during the execution of work.
Estimation and costing as per Sobha Arena are as follows,
Preliminary estimation
This estimation includes staff salary, mobilisation, site operating
expenses, safety, marking masons, shifting and cleaning charges, curing
M&E estimation
This estimation includes plumbing &sanitary works, electrical works,
fire protection works, HVAC works, lifts, infrastructure development.
PQS
Stores In-charge
1)Planning Manager
Planning
Execution team Engineer
2) Costing Manager
Costing
Engineer
1) Senior engineer
2) Engineer
3) Technical supervisor
(shuttering)
4) Technical
supervisor(reinforceme
nt)
Bill provision
Preparation(engineer/supervisor)
Estimation department
Certification by QAD
Finance department
Payment of bills
Day 2
07.07.2018
1. Excavation of block 1
Usage of safety nets
Maintenance of slope and landing levels
Barricades 1m away from excavated areas
Day 3
09.07.2018
1. Block 1 Excavation
Leveling and Compaction
Anti-Termites Treatment
Day 4
10.07.2018
1. Block 1 Foundation Plan
2 different sizes of lift used in every block
Space for car wash drain water
2. Safety
Usage of Elevated electric lines used for construction tools and
machinery
Usage of male and female sockets
3. Estimation work assigned by Mr. Govind
GI Rhombus Mesh Used quantity calculation for block 3
Note: GI Rhombus Mesh is being used at the places where a RCC
and a Block work come in contact. They are calculated in running
meters.Width of GI Rhombus is 20cm.
Day 5
11.07.2018
1. Sobha Arena Entrance Gate
Naming Board made of glass fiber reinforced concrete board
Underground Storm Water Drain in the entrance
2. Slab Drawings
One-way slab
Two-way slab
3. Shuttering types
Conventional (Basement to Ground Floor)
Aluminum Form Work Shuttering (From 1st Floor)
5. Advantages of S-Form
Highly adaptable to meet our design requirements
Easy Installation and Removing
Easy Reuse for identical floors
Quick completion (7 days)
Day 6
12.07.2018
1. Visit to Block 3-B2
Capital columns - Used for resisting punching shear
Corbels - For supporting beams and architectural purposes
Block works are done for hand rails in the parking (Hollow blocks
were used)
2. Note:Types of Blocks
1. Hollow Blocks
2. Solid Blocks
3. Blocks are supplied by Sobha Concrete Product Division (SCPD)
4. Reconciliation for Rafts in Block 1
Measurements were checked for quantity surveying
5. Bull Marking for Block 3
Flat No. 6174, 6173
Note: 6 denotes wing number
17 (Next 2 digits) denotes floor number
4(the last digit) denotes flat number
Day 7
13.07.2018
1. Fixing of Wooden Frames for Doors and Windows
Flat No. 6041
PU foams are used for fixing the door frames
Door frames are supplied by SOBHA interior ltd.
After the frames are fixed it`s being covered by papers to avoid
damage
2. Horizontal Bars
3. Master Rings
4. Stirrups
5. Chair Reinforcement
3. Calculation
1. Bar Volume in metric tones
Weight of 1m Bar = D2/162 (in kg)
2. Cutting length in meters(For Cost Cutting)
Day 8
14.07.2018
1. BBS calculation for Wing 9 Columns
Different diameter of bars were used in a single column
Hence volume is calculated for each diameter rods
Day 9
16.07.2018
1. Observation of Materials used in Construction and their Testing
Procedure
Cement
Concrete
Bricks
Aggregates
Bitumen Sheet
2. Read SOBHA TECHNOLOGICAL MANUAL and got to know
about the standards and procedures followed specifically in SOBHA
Day 10
17.07.2018
1. Plumbing Visit to Block 2
2. Types of Pipes Used
1. PVC (For Waste Water)
2. UPVC (For Domestic Water)
3. CPVC (For Drinking and Hot Water)
4. GI (For Fire Pipes)
Day 11
18.07.2018
1. Shuttering for Block 3 Podium
Materials used for shuttering
Scaffolding
Base plate
U-Jack
Standards and Ledgers
Primary runner
Secondary runner
Swivel clamp
Marking on PCC
Column marking using Marking Chord Roller with the help of site
surveyor
Reinforcement for Raft and Column
Day 12
19.07.2018
I. Dewatering in UG sump area block 3 and 4
II. Leveling of adjacent areas of UG sump
III. Slab reinforcement for block 3 podium area.
IV. Ledge wall construction in 6044
V. Plumbing pipes are observed in toilets
VI. Cold and Hot water pipes provisions are made for shower and
wash basins
Day 13
20.07.2018
I. Slab dimension measurements of block 9 for quantity surveying
assigned by Mr. Dinesh
II. Concrete volume calculation for above mentioned slab area
III. Observations of foam tape which is used for arresting the slurry
leakages in concreting areas
IV. Concreting for Rafts in Block 3 podium area
Day 14
21.07.2018
I. Inspection of Block 3 and reporting current works(for all flats)
II. Observation of works in Wing 8 and Wing 9
III. Observation of Podium area columns(No. of lifts completed)
Day 15
23.07.2018
I. Plumbing procedures explained by Mr. Senthil Kumar
II. Types of Pumping systems
Gravitational system
Hydropneumatic system
Day 16
24.07.2018
I. Study of Ramp detailing drawing for block 3
II. Visit to Sewage Treatment plant
Note : Capacity of STP=600KLD
III. Visit to Club House(Indoor gym, Multi-Purpose hall, Multi-Sports
hall, Steam and Sauna, etc)
Day 17
25.07.2018
I. Visit to SOBHA Forest
View Project
Accompanied by Mr. Anoop
Observed:
Hydropneumatic pumps
Pressure valves (Hammer and Butterfly valves)
Booster pumps in the terrace (3 rung systems)
Swimming pool pumping room
Fire Pump Room
Organic Waste Converter
Sewage Treatment Plant
Hardness Test
Day 18
26.07.2018
I. Quality Team – Under Mr. Govindasamy
II. Visited Quality control lab
III. Observed:
Bulking of sand Test
Sieve Test
Cube test
Consistency Test
Slump test at the site
Day 19
27.07.2018
I. Visit to SOBHA Dream Acres
II. Visited the precast plant
III. Observed:
Different types of precast structures
Precast moulds
Conveyor systems
Dept. of Civil Engineering, JNNCE, Shivamogga. 47
Building Construction
Day 20
28.07.2018
I. Quality Team – Under Mr. Govindasamy
II. Common Area Inspection (Block 4)
Observed:
Reinforcement of Stairs
Day 21
30.07.2018
I. Water Proofing
II. Areas – Wet Area and Dry Area
Procedure:
Screeding
Primer
2 coats of Saniflex (in 8 hours interval)
I. Tiling Work
II. Grooves used - 8mm and 10mm
III. Laying of tiles on the walls is called dadooing
IV. Laying of tiles on the floor is called floating
V. Quantity Surveying
Percentage of block works finished in B1 and B2 of block 3
No. of hollow and solid blocks piled up in each floor
I. Visited store
Listing of materials available in store and application of those
materials.
Conclusion
During this one month we as under graduate students were able to
learn many new technologies and materials, and we assure that, this
experience will pave a way for our career growth. We are thankful to all
the engineers, supervisors and labors who has helped to gain valuable
information.