You are on page 1of 2

CPP-SV

PROCESS EMERGENCY SHUTDOWN LOGIC


DIAGRAM/ HIERARCHY

THIS DOCUMENT HAS BEEN HANDOVERED FROM AKER SOLUTIONS TO PTSC M&C AFTER
DETAILED DESIGN

DETAIL ENGINEERING CONSULTANT COMPANY COMPANY PROJECT NO.

D4 29.10.19 RE-ISSUED FOR CONSTRUCTION APP/ NTT NCH DNL SAO VANG (SV) CENTRAL PROCESSING PLATFORM
D3 05.09.19 RE-ISSUED FOR CONSTRUCTION APP NCH DNL PROCESS EMERGENCY SHUTDOWN LOGIC DIAGRAM/ HIERARCHY
D2 11.04.19 RE-ISSUED FOR CONSTRUCTION APP NCH DNL
D1 25.10.18 APPROVED FOR CONSTRUCTION YZU TPH TR PROJECT TITLE:
05-1_EPC
C1 13.02.18 ISSUED FOR APPROVAL YZU TPH TR CONTRACTOR DETAIL ENGINEERING
COPYRIGHT © B1 25.08.17 ISSUED FOR REVIEW WYS / YZU TPH TR SAO VANG AND DAI NGUYET DEVELOPMENT PROJECT
THIS DRAWING REMAINS THE PROPERTY OF IGP AND MAY NOT BE COPIED IN ANY WAY - - A1 06.07.17 ISSUED FOR INTER-DISCIPLINE CHECK WYS / YZU TPH - - - SCALE DRAWING NO. SHEET REV
EXCEPT FOR FULLFILING THE SPECIFIC PURPOSE FOR WHICH IT IS ISSUED.
BY CHK'D APPR CONTRACTOR COMPANY A1
DRAWING NUMBER REFERENCE DRAWINGS REV DATE DESCRIPTION
DETAIL ENGINEERING CONSULTANT APP APP N.T.S 05-1_EPC-GE-AEI-P-XR-00001 1 OF 2 D4
D:\Dai Nguyet WHP Detailed Engineering\SV DD\SHUTDOWN HIERARCHY\D4\[05-1_EPC-GE-AEI-P-XR-00001_Rev D4_Process Emergency Shutdown Logic Diagram, Hierarchy-issue.xlsx]Content
Activation of APS 
P.B. (via F&G)

LEVEL 4
ABANDONMENT

F&G Isolate UPSs after  Sewage  NOTE 15


Isolate EDG closing 
Hydraulic  30min delay PAPA Alarm
air inlet valves Treatment 
Reservoir LSTLL  Except NavAids (via F&G)
(via F&G) Pkg

Permissive
(WHCP), or HP  (via F&G)
NOTE 12 NOTE 4 NOTE 4 NOTE 12                                   

Subsurface  DRILLING RIG Gas in the Gas in the TR Pressurization  GTC  DRILLING RIG Fire/Gas  Fire in the Fire in the Fire in the Fire in the Smoke in the
Fire in the Fire in the  Fire in the  Gas in the  Gas  in the ESD P.B. FIELD ESD Smoke  in the
Shutdown PB ESD P.B. or PROCESS or  TECH BLDG P.B in CCR or  Enclosure  Confirmed in TU   TECH BLDG TECH BLDG LQ LQ TECH BLDG
WELL BAY PROCESS AREA  UTILITIES AREA UTILITIES AREA  LQ HVAC Intakes CCR P.B. LQ HVAC Intakes
(NOTE 13) Confirmed Fire WELL BAY HVAC Intakes Dining Room Fire Gas Riser Zone Switchrooms (excl. SwRm) Switchroom (exclud SwRm) HVAC Intakes

LEVEL 3
ESD

Deluge Required Trip GTG  Trip GTG, Tech Trip GTG, LQ Trip GTG,  Trip elec feeder, F&G Dampers


Trip  Start  SV ESD  Trip  Trip TEG  Trip GTC (fast Signal to  Inhibit EDG  Isolate Electrical  Trip Tech Bldg Trip LQ
Zone, and  Bldg HVAC & Initiate TR  Release Fire  Release Fire  Start Firewater Isolate the 
Trip Heating  Helifuel  Firewater Blowdown Signal to Seawater Regeneration  stop with  GPA BK‐TNG  Starting for Equipment in the  HVAC & HVAC &
Foam is manually  Selected  HVAC & Close Pressurisation Suppressant Suppressant Pump Required
Medium  Pkg Pump Drillling Rig System System blowdown) Platform Emerg SwRm Fire Zone Close Dampers Close Dampers
Subsurface  initiated Equipment Close Dampers Dampers after delay after delay Fire Zone
Shutdown NOTE 18                                   
NOTE 2,11 NOTE 1 NOTE 3 NOTE 3 NOTE 5                                    NOTE 6                                   
NOTE 7    NOTE 9 NOTE 8                 
Trip all SV Well Trip 
SCSSV (after PWV/  Both 
PMV) GTGs
NOTE 13 NOTE 20 NOTE 19
NOTE 17                                   
HP Flare / LP Flare  Export Gas/  Dead‐Bus Both lean TEG 
Hydraulic LP  HP Separator /  TEG Contactor  Condensate  Instrument Air 
PSD P.B. Condensate  Condensate  Both Export Gas  MP Separator Fuel Gas System   HP Gas Outlet Cooler 
Supply PSTLL Knockout Drums  Test Separator Integral Scrubber  Preheater Inlet  HP Fuel Gas PSTLL 400V EDG  pumps are not 
at CCR Stabilizer PSTHH Pipeline PSTHH/  Compressor USD PSTHH LSTHH/ PSTHH (Seawater) PSTHH PSTLL
LSTHH LSTHH/ PSTHH LSAHH PSTHH Switchboard running
PSTLL
2oo3
LEVEL 2 2oo3 2oo3 2oo3
PSD

Shutdown all  Send PSD status Stop all Cool‐down Stop  Trip Heating 


Close SV Well Blowdown Gas  Trip TEG 
Close all Process  Close the  PSD Signal to  Signal to THIEN  Switch running  Hydrocarbon  GTC Medium into 
PMV & PWV  Hydrocarbon  Compressor Regeneration  Open BDVs
SDV's / XSV's RISER SDVs WHP‐DN UNG GTG to Diesel Fuel  Process Chemical  (with remaining  Cooldown 
Valves Process Facilities (by Solar) System
(BK‐TNG) Injection Fuel Gas) Mode
NOTE 16

Heating  Gas in GTG Fire in GTG 


Fire in GTC  Gas in GTC Medium  GTG Stack  Stop GTG 
Stop GTC  Air Intake Enclosure
Process Unit  Enclosure Air Intake sustained  TSTHH 
Pushbutton in CCR (from Solar F&G) (from Solar F&G) Pushbutton in CCR
Shutdown Initiators (from Solar F&G) (from Solar F&G) FSTLL / TSTHH 

LEVEL 1
USD NOTE 10

GTC fast‐stop  Close Fuel Gas &  ABBREVIATIONS:


Release water  Close Fuel Gas  GTG fast‐stop  Release water 
Trip Process Unit  Lockout with  Stop with cool  Diesel SDVs for 
Close Process Mist Spray ESD SDV's for GTC Lockout Mist Spray Stop GTG ACCU AIR COOLED CONDENSING UNIT
Motors via MCC  Blowdown down GTG
Unit  SDV's (by Solar) (by SDS) (by Solar) (by Solar)
IRP Relays (by Solar) (by SDS) AHU AIR HANDLING UNIT
APS ABANDON PLATFORM SHUTDOWN
CAP CRITICAL ACTION PANEL
NOTES: CCR CENTRAL CONTROL ROOM
1.  Utilities Area non‐certified equipment, and high risk processes such as air compressors are trippped. GTG is tripped and HVAC run 50% load on EDG. CPP‐SV CENTRAL PROCESSING PLATFORM ‐ SAO VANG TU THIEN UNG
2.  Blowdown is immediate, apart from Fuel Gas system blowdown which is delayed for one minute to allow GTG switchover to diesel. (refer to Note 11) EDG EMERGENCY DIESEL GENERATOR XSV ON/ OFF SAFETY VALVE
3.  F&G Dampers isolate the initiated fire zone, AHU & ACCU and GTG are tripped  F&G FIRE AND GAS SYSTEM WHP‐DN DAI NGUYET WELLHEAD PLATFORM
4.  When gas is detected in the HVAC intakes, GTG is tripped and all non‐certified electrical equipment is manually isolated (Refer to 05‐1_EPC‐GE‐PTC‐Z‐DN‐00008, Technical Note‐New Power Isolation Philosophy in Technical Building & LQ). GPA GENERAL PLATFORM ALARM WHCP WELLHEAD CONTROL PANEL
5.  When the upper deck HVAC intakes are shut‐in and the below cellar deck TR intake is gas‐free, the TR pressization fan is manually started.  GTC GAS TURBINE COMPRESSION 2oo3 TWO OUT OF THREE VOTING
6.  GTG trip to remove the power and fire suppressant release is automatic, delayed 60 seconds (hold for code), with manual isolate selector and immediate release selector at switchroom entrance  GTG GAS TURBINE GENERATION
7.  Only if the fire is detected in the Emergency Switchroom is the EDG inhibited from starting HMI HUMAN MACHINE INTERFACE
8.  The two electrical feeders from the Normal & Emergency Switchboards to the LQ switchboard are isolated automatically HVAC HEATING, VENTILATING AND AIR CONDITIONING SYSTEM
9.  Electrical plant within the Fire Zone is tripped. IOM INSTRUCTION OPERATING MANUAL
10.  The GTG is tripped by Solar F&G activation, loss of HM flow for 180s, HM outlet TSTHH for 180s, and any stack TSTHH. LQ LIVING QUARTER
11.  Fuel Gas 45‐SDV‐020 & 025 remain open to supply GTG for one minute after ESD PAPA PREPARE TO ABANDON PLATFORM ALARM
12. SV ESD signal shall not be repeated back to Drilling Rig in the event of ESD from Drilling Rig. PB PUSH BUTTON
13. Well closing starts by sending signal to close choke (via PCS) and signal to close PWV (via SDS) at same time, followed by signal to close PMV, with SCSSV last. PMV PRODUCTION MASTER VALVE
14. Deleted. PWV PRODUCTION WING VALVE
15. Sewage Package is not tripped by any cause. Will stop when power is cut, following Abandon.  SDS SHUTDOWN SYSTEM OR SAFETY INSTRUMENTATED SYSTEM
16. Heating Medium trip to 'cool down' keeps HM pumps running, and trim cooler fans. It does put dampers in bypass and trips the electrical HM heaters.  This avoids cascade trip of GTGs on low HM flow.  TEG TRIETHYLENE GLYCOL
17. Trip of both Heating Medium Circulation Pumps will cause cascade trip of both GTGs on low HM flow.  TR TECHNICAL ROOM

18.  CPP‐SV ICSS (Fire & Gas) will automatically send an alarm signal to the TU platform (BK‐TNG) control system in the event  of confirmed fire or gas in the TU riser location of CPP‐SV (FZ‐4B); SDV SHUTDOWN VALVE


       • The BK‐TNG platform control system will then show an alarm event alerting the BK‐TNG operator to the alarm, but the BK‐TNG control system takes no action to close the ESDV of BK‐TNG platform.  SCSSV SURFACE‐CONTROLLED SUBSURFACE SAFETY VALVE
       • The BK‐TNG platform control room operator  shall have three (3) minutes to telephone CPP‐SV control room to verify the alarm authenticity. UCP UNIT CONTROL PANEL
          + If the event is genuine, the BK‐TNG control room operator shall close the ESDV (on BK‐TNG) immediately thereafter. The CPP‐SV ESDVs will automatically close within eighteen (18) seconds of the alarm. UPS UNINTERUPTABLE POWER SUPPLY
          + If the event is not genuine as confirmed by the SV/DN Operator the CPP‐SV Operator shall cancel the alarm and the BK‐TNG control room operator shall take no further action. 
          + If the BK‐TNG control room operator fails to  contact  CPP‐SV within the three (3) minutes time frame to confirm leakage status, then the ESDV (on BK‐TNG) shall automatically close. 
       Ref: 05‐1_EPC‐GE‐SOG‐S‐TN‐00004_Assessment of Need for Executive TU Shutdown

19. If both lean TEG pumps are not running for more than 15 minutes, then PSD will be initiated on CPP‐SV.
20. Time delay (15 minutes ‐ adjustable) to be provided. The time delay gives operator enough response time to choke down production and safely control CPP‐SV to avoid PSD.

COMPANY
THIS DOCUMENT HAS BEEN HANDOVERED FROM AKER SOLUTIONS TO PTSC M&C AFTER DETAILED DESIGN SAO VANG (SV) CENTRAL PROCESSING PLATFORM COMPANY PROJECT
NO.
PROCESS EMERGENCY SHUTDOWN LOGIC DIAGRAM/ HIERARCHY

PROJECT TITLE:
CONTRACTOR DETAIL ENGINEERING
05-1_EPC
COPYRIGHT © SAO VANG AND DAI NGUYET DEVELOPMENT PROJECT
THIS DRAWING REMAINS THE PROPERTY OF IGP AND MAY NOT BE COPIED IN ANY - - SCALE DRAWING NO. SHEET REV
WAY EXCEPT FOR FULLFILING THE SPECIFIC PURPOSE FOR WHICH IT IS ISSUED.
A1
DRAWING NUMBER REFERENCE DRAWINGS N.T.S 05-1_EPC-GE-AEI-P-XR-00001 2 OF 2 D4
D:\Dai Nguyet WHP Detailed Engineering\SV DD\SHUTDOWN HIERARCHY\D4\[05-1_EPC-GE-AEI-P-XR-00001_Rev D4_Process Emergency Shutdown Logic Diagram, Hierarchy-issue.xlsx]Content

You might also like