Capital Cost For E-101

Area = 19.5402 m2

Purchased Equipment Cost,

From Table A.1,

Equipmen Equipment K1 K2 K3 Capacity Min Max


t type Description Units size Size
Heat Floating 4.8306 -0.8509 0.3187 Area, m2 10 100
exchanger head

log 10 C0p ¿ K 1 + K 2 log 10 A+ K 3( log 10 A)2

2
¿ 4.8306−0.8509( log 10 29.71302)+ 0.3187( log10 29.71302)

¿4.2687

¿ $18565.74

From table A.3, Identification number: 2,

From figure A.18, Material factor, FM : 1.4

From table A.4, B1 = 1.63; B2 = 1.66

¯¿
Pinlet = 1799.820 kPa × 0.01 1 kPa ¿

¿ 17.9982 ¯¿

From table A.2, C1 = 0.03881, C2 = -0.11272, C3 = 0.08183

log 10 F p ¿ C 1+C 2 log 10 P+C 3 (log 10 P)2

¿ 0.03881−0.11272 ( log 10 17.9982 ) +0.08183 (log 10 17.9982)2

¿ 0.02625

¿ 1.0623

Bare module cost, CBM


0 0
CBM = C p F BM =C p ( B 1+ B2 F M F P )

¿ 18565.74 [1.63+1.66 ( 1.4 )( 1.0623 ) ]

¿ $ 76096.98

∴ ,C BM =C 1=$ 76096.98

CEPCI (2001) = 394

CEPCI (2015) = 560

I2
C 2=C1 ( )
I1

¿ $ 76096.98¿ )

¿ $ 108158.1446