-COMPUTATION OF PROJECT DURATION

-Table from Department Order No. 71, Series of 2013, ANNEX B - b - 2


Reinforced Concrete, Type 1
Interpolated Values
Length 2994.50 4491.75 5989.00 *
Reference/Given Amount 50,000,000.00 75,000,000.00 100,000,000.00
Reference Duration 659 988.50 1318
Duration Reduction Factor 0.2 0.160 0.12
Estimated Duration 146.80 173.16 183.16 **
"Say" 147 174.00 184

* Assumed Equivalent Length without Steel Sheet Pile 174 < 184
Project Cost = 65,000,000.00 ∴ use 174 days
** Computations from Department Order No. 71, Series of 2013, ANNEX A
Calendar Days = [(given reference amount X reference duration per ln.m.)/estimated
amount per ln.m.] X Duration Reduction Factor
+ (duration of mob./demob. on the given reference amount)
Mob./Demob. Duration for P5 Million up to P50 Million - 15 c.d.