• PROFILE
31 years of professional experience Industrial Plants, Ports sector (maritime and fluvial),
with projects of multimodal port terminals , Oil &Gas – Biodiesel, Wastewater Plant and
CSP-PV projects.
• EDUCATION
Lan gua ges SPARCS N4 (The Industry Standard Terminal Operating System)
English
PRIMAVERA PROJECT PLANNER (with specialization in EPPM -
Spanish Enterprise Project Portfolio Management).
Portuguese
REDMINE: Redmine is a flexible project management web application.
French That uses the framework Ruby no Rails, is cross-platform and cross-
Arabic database.
Redmine is open source and released under the terms of the GNU
General Public License v2 (GPL).
• COURSES
PROFESSIONAL EXPERIENCE
Direction of port projects (maritime - Fluvial) and business development from Mexico to
Peru, including the Caribbean
Director of maritime and fluvial port projects, besides business development in this area in
LATAM, leading important projects for the company and attention of its global clients such
as APM Terminals, COSCO, DP World, YILPORT.
Development and assurance of engineering for dredging and special structures in coastal
protection, superstructures in docks and breakwaters
Project management for electro-mechanical and civil works, with special focus on insulation
and fireproofing in equipment and structures to terminal port.
• KSA (King Abdullah Economic KAEC project in City)
Page 2 of 6
LUIS ENRIQUE ROMERO RODRÍGUEZ,
CONSTRUCTION PROJECT MANAGER
Working on the project and leading the engineering studies and designs of the Terminal and
photovoltaic development project of 10 MW to supply power to the port and nearby
community.
Also, coordination and engineering of purchase for a 15MW PV plant for port concession
Caribbean
Coordination of different disciplines, oceanographic and river studies.
Hiring local and foreign Engineering Cost analysis and preparation of CAPEX and OPEX.
Construction Project Manager EPC Contract for Port of hydrocarbons (naphtha and crude) April
2014 - September 2014
Functions:
- Manage project completely under control minimum technical and administrative
actions (reports, budget meetings, coordination, etc.)
- Attendance at department meetings and team meetings also performance-related
position such as: technical review, etc.
- Port development multipurpose large scale in the Bay of Cartagena.
- specializing in the handling and storage of crude oil and its derivatives infrastructure
- Sea Grant approved environmental license and construction license
- Port facility and industrial park in the area of 110 hectares.
- Natural Depth maneuvering area of 19 meters.
Page 3 of 6
LUIS ENRIQUE ROMERO RODRÍGUEZ,
CONSTRUCTION PROJECT MANAGER
Construction Project Manager LNG marine terminal and Ammonia- Urea 2009 – 2011
Functions:
Coordinate the activities of contractors performing C / S / in the work fronts • Supervise
subcontractors works and facilities
• Ensures contractor personnel are trained and knowledgeable of specifications and work
procedures, the material is being used to ensure maximum efficiency, and that the work
performed is in accordance with specified quality requirements
• Monitor daily field activities of the Contractor to conform with the design documents,
specifications, standards and codes
Page 4 of 6
LUIS ENRIQUE ROMERO RODRÍGUEZ,
CONSTRUCTION PROJECT MANAGER
• Assess the workforce against progress achievements. Keep the cash program and cost
control of C / S / in fronts.
• Assist contractor consultations resolutions through RFI (request for information)
• Assist Contractor in the execution of their quality program - inspection, testing and
maintenance of records
• Ensure compliance with the contractor project safety program and plays an active role in
the development of the safety culture on the project
• Review the safety analysis tasks and work permits. Attend safety meetings work.
• Track changes in scope or influence, ensuring that all scope changes are documented
quickly and appropriately, and change orders are approved prior to execution of the work
• Participate in weekly progress review meetings
• Ensure that the contractor keeps existing as-built drawings
• Check the equipment erection and supervise lifting operations
• Assist quantity surveyors in measurement of progress of work.
• Coordinate and assist contractors Configuration and installation of temporary facilities
contractor
• Take responsibility for the following functions: - Earthworks, including excavation,
dewatering , backfilling and compacting - Including pile driving tests - Layout and stroke
foundation or formwork , reinforcement , integrates and anchor bolts, concrete placement
and curing , and waterproofing application - Construction of structural elements -
Construction of roads and paving surface - Installation of underground piping including
coating and wrapping, hydrotesting , wells, basins, valve boxes , hydrants and stand pipes
capture - Structural steel and precast concrete and erection, ladders and platform installation
- Construction and housing in camps, erection and finishing work - Review and approval of
plans for installation / inspection proof C / S and method statements
Capture, a network of water treatment and conduction of 100 km of 700 mm HDPE pipe.
Construction of 104 km of runway with 10 mt road in selected local materials for transport
and placement of pipes, with demining work. Construction of interim Lobito port for
containers, which would bring the materials that would be to deliver the water pipelines
project from Sud-Africa; Works performed: Construction of dam on reinforced concrete
wall attached to a reef docking structures additional dam construction Quay wall built solid
concrete block and protege by tetra acropods.
Construction of ports: The KPPA (Kuwait Ports Public Authority) supervision request to
expand the Port of Shuaiba industrial complex within the project part of Equate OLK PII,
this port would serve as material storage area for industrial project construction for all
companies involved. Work done in partnership with the Dow Chemical.
The project involves the construction of a pier about 291 m attached to the east side of the
central pier petrochemical plant, through the funding of 11 drawers and stuffing you
backfill. The dock will be aligned with the current docking DOW plant and will involve
dredging of 1.1 million cubic meters and filling with quarry material.
Page 5 of 6
LUIS ENRIQUE ROMERO RODRÍGUEZ,
CONSTRUCTION PROJECT MANAGER
Senior Construction Manager and Technical to LNG Punta Europa marine Terminal 2002 – 2006
• DRAGADOS CONSTRUCCIONES
Construction Manager 1995 - 2002
1. CONSTRUCTION PORT OF JAMAICA
CONSTRUCTION OF PORTS JAMAICA MONITORING CONSTRUCTION PROJECT FIRST PHASE WITH
THE URBAN DEVELOPMENT CORPORATION CAYMANAS AREA IN KINGSTON TRANSSHIPMENT
PORT IN JV WITH JAMAICAN GLEANER
Supervision for the modernization of a security system to meet U.S. and international
certification for security for the port of transshipment.
Development of methodology for analysis, evaluation and treatment of risks under ISPS
Code protection to ships and port facilities
Significant Data: More than 500 facilities evaluated and improved
Monitoring construction project first phase with the Urban Development Corporation
Caymanas area in Kingston transshipment port in JV with Jamaican Gleaner
2. GOVERNMENT PUBLIC WORKS (COLOMBIA) 1991 – 1995
Modernizations: Other projects include the modernization of the port in Cartagena Bavaria
for Bavaria Beer Company that also proposals for consortia renewals Propilco Petco and
Olefins for the port of Cartagena.
The project consists of enabling and improving the outer harbor of the Port of Petaca and
the construction of the new breakwater west of the basin and creating a new dock.
Action is completed, once executed the work of demolition and Poniente old dam, with the
dredging of the dock area to the height demolished -13.5 m. Since there are also problems in
the basin depth 9 think appropriate dredging the entire area up to elevation -16.5 m.