You are on page 1of 4

BASF Construction Chemicals Egypt, Business Park A, Building A1, Cairo Festival City, Ring Road, New Cairo,

Egypt
Phone +202 2 5980800, Fax +202 2 5980801

Standard method for making and curing cubes


made from pre-bagged grouts and polymer
modified mortars
General
This guideline hopes to cover some of these points
The method described below is based on practical and set out what is believed to be a reasonable
experience of making and curing mortar and grout method, easily reproduced on site or in the laboratory,
cubes in the laboratory and on site. BASF offers the and able to provide consistent results.
methods stated in good faith and endeavours to
ensure that any advice given is accurate, however, the Cube size
method, although using ASTM C-109 and C-942 as a
guideline, should not be construed as relating to any Detailed below are some of the various cube sizes
International standard. found in grout and repair specifications used
worldwide.
The method statement relates to BASF products only.
Other materials falling into the above categories may BS 1881 Methods for testing concrete 100mm
be mixed successfully using this method, but BASF BS 4551 Methods for testing mortars 100 or 70.7mm
cannot be held responsible for failures caused by not BS 4550 Methods for testing cement 100 or 70.7mm
following manufacturer’s recommendations or stated BS 6319 Methods for testing resin 40mm
procedures. compositions
ASTM C-109 Compressive strength of grouts 50mm

Philosophy Cube size used is to an extent irrelevant. The main


points to consider are:
The basic philosophy behind testing should be to
assess the material quality following a standard I. The correct type and quality of testing equipment
procedure. The results of these tests should, initially, must be specified and maintained at a fit for use
be used to determine the suitability of the product for level. (Planeness, levelness, quality of internal
use, and later to check the consistency of the supply. surfaces, cleanliness etc.)
Tests may also be carried out to check the quality of
the product being used in a critical area. This type of II. The testing should be comparative throughout.
testing, however, should be more a check on the Cubes of 40, 50 and 70mm will give similar results
mixing quality rather than the product itself. however, there may be a big difference between 50
and 100mm cubes, which could amount to 4 - 5
The manufacture and testing of cubes made from N/mm².
grout or polymer modified cementitious mortars can
pose many problems to the Engineer. The materials III. The testing should be carried out by trained
are based on cement, and yet there may be conflicting personnel and procedures should be followed
requirements as to how to do the 3 'C's (cast, cure and strictly and under supervision.
crush). Maybe, because the material is cementitious
in nature, and all technicians and Engineers know BS
1881, it is often easy to treat these types of product as
"concrete". However, this does not take into account
the type of products or the product's reaction to
different curing regimes. With so many Standards,
different cube sizes and various curing methods, it is
possible for the Engineer to become confused.
A Private Company Incorporated with limited liability
). . . . (
in the Egypt Paid Up Share Capital EGP 6,000,000.
Commercial Registration No. 52538
+ :
+ :
www.master-builders-solutions.basf.com.eg
.
BASF Construction Chemicals Egypt, Business Park A, Building A1, Cairo Festival City, Ring Road, New Cairo, Egypt
Phone +202 2 5980800, Fax +202 2 5980801

Tempreature between either pair of opposite internal faces based


on the average of four measurements should be the
The temperature of the air in the vicinity of the nominal size ± 0.15mm.
mixing slab, the dry materials, molds, base plates,
and mixing bowl, shall be maintained between 23 The joint between the mould sections and the bottom
°C ± 3°C. plate should be watertight. The mould's internal and
The temperature of the mixing water, moist closet external surfaces and joints should be kept clean from
or moist room, and water in the storage tank shall build up of cement and loose rust by wire brushing, or
be set at 23 °C ± 2°C. other suitable technique, and lightly oiled with a
proprietary mould release agent.

Summary Note: Mould oil should not be allowed to pool in the


mould and any excess oil should removed prior to use.
Normal site testing should only be carried out to check The correct application can be checked by wiping a
the consistency of supply using some or all of the tests dry finger across the mould surface. If the mould oil is
employed to confirm initial acceptance, unless other ridged either side of the finger mark an excess of oil is
testing regimes have been agreed. present. If the finger is still oil free then insufficient oil
is on the surface. New moulds should have the
Only trained technicians should be used for the travelling grease removed before use.
preparation and testing of materials, as without doubt,
the majority of product failures come from poor curing All fasteners should be tightened using the correct
and testing technique. tools such that the mould sections are rigid and will not
loosen under compaction or movement. Avoid over
Curing should be properly employed to ensure tightening that can distort the sections.
cementitious materials gain their full potential strength.
Any other technique is open to variation unless fully Where the cubes are made from products that have
controlled and monitored. partial or complete expansion or are to be restrained
in application, the moulds shall be provided with a
Making and curing cubes made from covering plate which shall be firmly fixed ensure that
the top of the grout is not allowed to expand freely.
cementitious grouts and normal
weight / light weight repair mortars Cleaning equipment
• Wire brush
General • Rags or similar cleaning materials
• 25mm paintbrush
The method described below, if carried out by trained • Mould release oil
staff, should ensure consistency of manufacture and • Dust pan and brush
hence consistency of results. • Spanners or hexagonal screw keys
• Scrapers
Equipment • Rubber hammer
• Screwdriver
Cube moulds
Steel float for levelling
The cube moulds should be precision moulds, Absorbent cloth or heavy duty tissue to wrap the
specifically designed as cube moulds, made from cubes after stripping
metal with matched parts marked with unique Heavy gauge polythene bags and 50mm wide
numbers or characters on the opposite sides of the plastic packing tape
top flange to facilitate correct assembly. Permanent marker pens and self adhesive labels
The internal faces of the moulds shall be machined. Small scoop for filling
All angles will be at right angles (90°) to adjacent
faces. The depth of the mould and the distance

A Private Company Incorporated with limited liability


). . . . (
in the Egypt Paid Up Share Capital EGP 6,000,000.
Commercial Registration No. 52538
+ :
+ :
www.master-builders-solutions.basf.com.eg
.
BASF Construction Chemicals Egypt, Business Park A, Building A1, Cairo Festival City, Ring Road, New Cairo, Egypt
Phone +202 2 5980800, Fax +202 2 5980801

Procedure - The tamping pressure shall be just sufficient


to ensure uniform filling of the molds. The 4
Prepare an area to manufacture and store the cubes. rounds of tamping (32 strokes) of the mortar
The area should be dry and the cubes should be shall be completed in one cube before going
made on a flat, solid base free from vibration and the to the next. When the tamping of the first layer
effects of weather. The area should be shaded and if in all of the cube compartments is completed,
possible inside an enclosed room. fill the compartments with the remaining
mortar and then tamp as specified for the first
Ensure that the moulds are clean and ready for use, layer. During tamping of the second layer,
and all equipment required to complete the task is at bring in the mortar forced out onto the tops of
hand. (i.e. rags, plastic bags, heavy duty cloth etc.) the molds after each round of tamping by
means of the gloved fingers and the tamper
Scoop a quantity of the mortar or grout and half fill upon completion of each round and before
each of the moulds to be cast. Ensure that a starting the next round of tamping.
representative sample is taken. This is particularly
important for grout products.
B- Fluid
-Apply a thin coating of release agent to the interior
faces of the mold and non-absorptive base plates - Fill the Gout on 2 layers ,
-Seal the surfaces where the halves of the mold join - Fill each mold in the set halfway. Puddle each
by applying a coating of light cup grease such as with a gloved finger five times to release
petrolatum entrapped air.
-Effect a watertight seal by applying the liquefied - Fill the mold and puddle again. Bring the
sealant at the outside contact lines between the mold excess grout to the center and finish the
and its base plate surface by cutting off the excess with the
-Mechanically mix in accordance with the procedure straight edge of a trowel held vertically and
given in Practice C 305. drawn across the top of the mold with a
-Place the Grout into cubes based on the following sawing motion.
consecuitances - After 24 hours carefully strip the cubes from
the moulds. Set the mould sections aside in
A- Flowable (Mortar) groups for easy cleaning and re-assembly.
Examine the cubes for any defects. Reject
- Fill the Gout on 2 layers , any that do not look normal (e.g. have an
- Place a layer of mortar about 25 mm excess of surface voids or are not complete)
(approximately one half of the depth of the and inform the Laboratory Supervisor or
mold) in all of the cube compartments. Engineer. Mark on the surface of each cube
- Tamp the mortar in each cube compartment with the permanent marker, its' full
32 times (in about 10 sec) in 4 rounds, each identification and the age for test. Do not
round to be at right angles to the other and scratch details onto the cube.
consisting of eight adjoining strokes over the
surface of the specimen,

A Private Company Incorporated with limited liability


). . . . (
in the Egypt Paid Up Share Capital EGP 6,000,000.
Commercial Registration No. 52538
+ :
+ :
www.master-builders-solutions.basf.com.eg
.
BASF Construction Chemicals Egypt, Business Park A, Building A1, Cairo Festival City, Ring Road, New Cairo, Egypt
Phone +202 2 5980800, Fax +202 2 5980801

Immediately wrap each set of cubes in the heavy For reference cubes should be crushed within the
duty tissue or absorbent cloth pre - soaked in following time limits after casting.
water and seal inside the polythene bag. Fold
over the open end and seal it with packing tape, 1 day ±½h
such that a water tight and air tight seal is formed. 3 days ±1h
Repeat the identification marks on a self-adhesive 7 days ±3h
label for sticking on the polythene bag. Store the 28 days ± 12 h
bag containing the cubes carefully ,ensuring that it
has no punctures and cannot be punctured, away The cubes should be crushed in accordance with BS
from sunlight or other operations until ready for 1881, Part 116 ASTM C109 or DIN standards using a
testing. compression test machine with ranges suitable for the
maximum strength and cube size of the material under
- Place the cover plate over the mold (three- test.
gang), taking care that the grout or loose
grains of sand do not prevent seating of the Apply the load to specimen faces that were in contact
plate. with the true plane surfaces of the mold.
- Place a mass of 7 kg (or 15 lb) on each cover
plate or fix the cover plates to the molds with The maximum permissible range between specimens
C-clamps, finger tightened. from the same mortar batch, at the same test age is
8.7 % of the average when three cubes represent a
Grout and normal weight cubes may alternatively be test age and 7.6 % when two cubes represent a test
stored directly in water until ready for test. Follow the age
identification procedures as above prior to immersion.
Ensure the marking medium is water proof. It is
recommended that if the cubes need to be transported
to a testing house, they are wrapped as described
above for the journey.

Clean up

Carefully clean the mould sections with the wire brush


and lightly oil the sections before re-assembly. Ensure
all joints and internal faces are clean and there are no
steps between pieces. Ensure all fasteners are
tightened correctly and the corresponding matching
sections are in their proper position.
Stack the moulds in a covered area away from the
influence of weather, dirt and other operations.
Periodically check the internal faces and joints
dimensions for excessive wear. Do not join non-
matched sections,

Cube crushing
The cubes should be transported to the testing house
if this is not at the site of the cube manufacture, at
least 1 day prior to the crushing time. Grout cubes and
normal weight mortar cubes should be stripped from
the paper and plastic wrapping and stored in water
until ready for crushing.

A Private Company Incorporated with limited liability


). . . . (
in the Egypt Paid Up Share Capital EGP 6,000,000.
Commercial Registration No. 52538
+ :
+ :
www.master-builders-solutions.basf.com.eg
.

You might also like