JSA - Painting For Pipe
JSA - Painting For Pipe
RAM 1. Identify the “worst case credible” Scenarios and Potential Consequences, under the
prevailing conditions.
2. Estimate the Severity of each Potential Consequence, in the four consequence categories –
People, Assets, Environment, and Reputation (PAER), as applicable.
3. Estimate the Likelihood, from past experience (including the incident in question), by
asking the question: ‘How often has a hazard release resulted in a Consequence similar to
the one that we are considering (worst case credible consequence)? The approach is one of
applying history to predict the future. The estimate of Likelihood is based on the Likelihood
of the particular consequence under consideration, not on the Likelihood of the hazard being
released or incident occurring.
4. Estimate the Risk Rating. For each potential Consequence determine the Risk Rating for
each of the applicable PAER categories. The colors (Light Blue, Dark Blue, Yellow or Red)
represent increasing level of risk. The rating that falls in the area with the higher level of risk
(e.g. yellow vs. light blue) should become your risk rating.
Light Blue/Low: Manage for continuous improvement, although Businesses may set lower
priority for Further Risk reduction.
Yellow/High: Identify and implement controls and recovery measures to reduce Risk to
ALARP
Red/Serious: Identify and implement Controls and Recovery Measures to reduce the Risk to
ALARP and provide a documented demonstration of ALARP by a Bow Tie or equivalent
methodology.
JOB HAZARD ANALYSIS WORKSHEET Title: Painting for pipe
hoodLikeli
Severity
RatingRisk
when the task step is
sequence they performed
are carried out.
Allowed only trained and qualified workers to assign jobs.
Unskilled and un trained Explain the work sequence clearly by job supervisor.
personnel starting the job, Ensure it the entire worker attend the TBM before start work.
Work Condition Defective Tools, Always using mandatory PPE and Job specific PPE if required.
& General Improper storage of tools Ensure slow movement of workers.
and spare parts Ensured by work supervisor workers follows the proper procedure.
C 2 Lo Supervisor
Bad housekeeping Don’t allowed defective and homemade tools / equipment’s. w
1 Horse play & loitering, Don’t allow any kind of Malpractices and Horseplay in the site.
unsafe acts Smoking is strictly prohibited in the work place use designated smoking shelter.
Smoking in the work place All the tools and equipment’s must be properly stored.
Slip, trip and fall Employees are not allowed to leave their job site without informing the job supervisor.
2 Should be competent, & having all documents (Local Driving licence, operator
licences)
Collision / Hit Maintain road speed limit when using access roads, 20 Kmp/h.
Mobilization of Environmental Do not use mobile phones while operating any equipment.
Equipments and Fire Ensure that equipment is inspected, Color coded & provided with back reverse alarm, B 3 Lo Supervisor /Insulator
Materials (Paint) Eye contact lighting, mirrors, fire extinguisher, seat belts…etc. w
Unauthorized entry Banks man should accompany the equipment during movement.
Materials must keep on designated area.
Fire Extinguisher must be provided and assign qualified fire watcher.
Provide shades to avoid direct sun exposure.
Variation and Signage been providing for Material and equipment’s.
JOB HAZARD ANALYSIS WORKSHEET Title: Painting for pipe
Fire/Explosion Storage Shall Be in Good Ventilated & Shade Location to Avoid Sun Exposure.
3 Paint storage Improper Storage Provide proper fire extinguishers nearby work area/Equipment. C 2 Me
No conflicting activities. d
Remove all flammable materials from nearby area
Do not obstruct the access.
Store the materials as per standard.
Tripping/slipping/ Falling
4 Cleaning Limit the person in the area.
hazard
surfaces Use proper PPEs. C 2 Me
Flying particles
Ensure no water spills over electrical equipment’s. d
Electrocution
Protect nearby electrical equipment from water contact.
Provide proper shielding around the painting area to avoid spreading of paint particle
Keep the MSDS in site
Use appropriate PPEs as per MSDS Use respirators while handling spray painting.
Chemical in contact with
Never kept the paint tins open when not in use
body
5 Mixing of paint/ Use tray for the storage and mixing of paint. C 2 Me
Environmental hazards
and Painting Proper ventilation shall be providing in storage and mixing area. d
Fire/Explosion
Ensure no chemical spills
Whipping of Painting hose
Store the chemicals as per MSDS & Follow all the safety precautions as per MSDS
Remove all flammable materials from nearby area
Ensure the air compressor hose connections are properly connected and using whip
checks and pins
Provide proper fire extinguishers nearby.
Provide eye washer in case of emergency.
Working at Incompetent workers, Ensure that all personnel attend the work at height training.
Height/on the Hit by Falling Object, Should use inspected full body harness if work above 1.8 mtrs of height.100% Tie off.
JOB HAZARD ANALYSIS WORKSHEET Title: Painting for pipe
7 Equipment damage or permanent PPE is to be used only when no other control can reduce or eliminate the hazards /risk;
C 2 Lo Supervisor /Insulator
deafness Make sure all workers are issued with wear the recommended PPE as required for the w
safety on worksite and specific to the activities and tasks.
Trainer workers in the correct use maintenance& storage of PPE
Carry out basic housekeeping regularly keeping access ways and work clear off
materials, tools, and debris.
Slips, Trips, and fall can Wear appropriate foot wear
Leaving the cause cuts abrasions, breaks, Make sure cable & other equipment don not cause of trips hazard.
8 work area/house strains, sprains and back Barricade or restrict areas where the hazard cannot be eliminated. Supervisor/Insulator
B 3 Me
keeping injury to workers and Make sure that the work area left clean and tidy. d
others. Never leave ladders or tools and equipment unattended in case of unauthorized use or
an unexpected change in weather.
Always check to make sure all ladders step and ramps are stable before descending.
Make sure site entry and exits are secured.
Provide safe means of lowering tools, plant, materials and debris to make sure they are
not carried while descending ladders, steps and ramps.
Make sure scaffold is secure against unauthorized entry.
All Paint Chemical Waste Shall Be Removed and Disposed as Per Procedures