You are on page 1of 22

(St) Prodi Unit Type Dev.

Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

Method Statement for Drying Operations


IQ022-00-2001-SI-0029

00 Issued for Approval Engineering A. Tareq A. Al-Maliki 14/02/2018

Prepared Checked Approved Date


Rev. Description
(name & initials) (name & initials) (name & initials) DD/MM/YYYY

DOCUMENT REVISIONS
This document is the property of SICIM spa who will safeguard its rights according to the civil and penal provisions of the law.

DOCUMENT REVISION HISTORY SHEET

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 1 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

Rev. REVISION DATE ISSUED UPDATE / AMENDMENT DETAILS


DESCRIPTION

00 Issued for Approval 14/02/2019 First issue

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 2 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

Table of contents

1 Introduction..................................................................................................................................................... 4

1.1 Definitions/Abbreviations 4

1.2 Reference 4

1.3 Summary……………………………………………………………………………………………………………5

2 Scope of work 5

2.1 Mobilization of Personnel and Equipment 5

2.2 Rig-up of Equipment 6

2.3 Drying 6

2.5 Rig-down of equipment 7

2.5 Demobilization 7

3. Dryness Criteria 8

3.1. Initial drying with dry air……………………………………………………………………………………………..8


3.2. Final air drying with air dryer……………………………………………………………………………………...8

3.3. Soak test……………………………………………………………………………………………………………8


4. Appendix…………………………………………………………………………………………………………………..9

4.1. Execution Schedule………………………………………………………………………………………… ...9

4.2. Equipment Certificate…………………………………………………………………………………….…..10

4.3 Risk Assessment…………………………………………………………………………………………….16

4.4 Daily Report ……………………………………………………………………….……………………......22

4.5 soak test Report…………………………………………………………………………………………….23

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 3 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

1 Introduction

The purpose of this document is to establish a detailed method statement for drying operations that Dr.
Concrete Building Material (hereinafter referred to as Subcontractor) will carry out in accordance with Sicim’s
(hereinafter referred to as Contractor) project requirements and specifications.

1.1 Definitions/Abbreviations
Company ENI BV
Contractor Sicim Iraq
Subcontractor Dr. Concrete Building Material Co.
DGS Degassing Station
SOW Scope of Work

1.2 Reference

03526.PLI.MEC.SDS Hydrocarbon Pipelines Pre-Commissioning (Company specification)


IQ022-00-2001-SI-029-0 SOW for Trunk Lines TK-01, 02, 03 & 04 Drying Operation

1.3 Summary

The scope of work includes the application of super dry air blowing technique on the newly installed Multiphase
Interconnecting Trunk Lines (total of four lines: 20” x 2 nos., 26” x 2 nos.).

The Multiphase Trunk Lines interconnect the oil manifolds headers of nearest DGS’s. The DGS’s interested by
the works are:

- Hammar Mishrif New DGS (DGS North)

- Hammar existing DGS

- Zubair Mishrif existing DGS

- Zubair existing DGS

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 4 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

The Trunk Lines and DGS scheme is per following:

Figure 1: Overall Connection Scheme between the entire plants

Dr. Concrete Building Material as subcontractor scope of work do include the following:
- Mobilization of equipment and personnel
- Rig-up of equipment
- Drying operations
- Rig-down of equipment
- Demobilization of personnel and equipment

2 Scope of work
Drying operation for the Trunk line TK-01, Trunk lineTK-02, Trunk line TK-03, Trunk line TK04..

2.1 Mobilization of Personnel and Equipment


Subcontractor will mobilize all of equipment and personnel needed to work site, 48 hours prior to start of
activities. Please find be the list of personnel to be mobilized to site:
- 1 X Supervisor
- 2 X Operator
- 2 X Technician
- 3 X Driver
All of the communication with regards to the activities will be maintained with supervisor.

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 5 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

For the equipment list, below the list of major equipment list (equipment certification can be found in the
appendix)
- 2 X Diesel Operated Air Compressor (1000 CFM)
- 1 X Pneumatic Air Dryer
- Manifold, hoses fittings and Gauges (adequate quantity)
- 1 X Dew point meter
- 2 X Trailer
- 1 X Crane
- 1 X Pickup
- 1 X Light tower
- 1 X office Cabin and Toilet

2.2 Rig-up of Equipment


Equipment rig-up will commence after mobilization and offloading of all equipment at work site, below
equipment set-up diagram:

Please refer to appendix for equipment certificates, equipment certificates will include the pressure gauges and
hoses certificates as well.
For the receiver side, there are no connections are needed except the following:
- Pressure gauge
- Dew point measurement sampling connection

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 6 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

2.3 Drying
Once residual dewatering and swabbing operations have been completed and approved, drying operations will
be carried out. Each pipeline will be dried using dry air.

When the dew point of the air at the pipeline end is 5°C lower than ambient temperature and does not fluctuate
by more than 3 °C whilst replacing the content of the line by dry air, drying can be accepted.

Air introduced into the pipeline during dry air drying shall have a dew point of at least 15 °C below the final dew
point of the pipeline (i.e., 20 °C below the ambient temperature).

The pipeline dew point is to be monitored at both ends to ensure the required dew point is achieved throughout
the pipeline. For final acceptance, the specified dew point in the pipeline is to be maintained for a minimum
period of 48 hours (soak test). All opening during this period will remain closed.

Following the minimum 48 hours hold period and if the Contractor requirements are fulfilled, final acceptance
will be obtained through signing the Drying Report by Contractor to terminate the drying operation.

The pipeline shall then be pressurized using super dry air to 1.5 barg and maintained at this pressure until start
of commissioning.

Below the expected drying time for each pipeline:

Expected
Length
Support Type diameter Volume drying
meters
time (hrs)
Trunk Line TK-01 4760 26" 1,404 40

Trunk Line TK-02 11946 20" 2072 70

Trunk Line TK-03 7580 26" 2236 45

Trunk Line TK-04 11946 20" 2072 94

2.4 Rig-down of equipment

When drying operation is complete, shall be disconnect and remove the pipeline drying equipment and
cap all open pipe ends. Equipment typically must be disconnected from power sources, decoupled from
pressurized systems, disassembled and moved off the rig floor or even off location.

2.5 Demobilization
Demobilization shall start after completion the all activities. A letter shall be submitted to the contractor
on completion of activity for the approval .DCBM shall carefully manage demobilization plans. DCBM
will assign the skilled workforce for demobilization requisite plant, equipment and materials on
completion.

Demobilization Including the compressor, air dryer, truck, manpower, instrument, crane, Removal, and
site clean-up , monitoring caravan, WC and other facilities on the site.

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 7 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

3 Dryness Criteria

For natural gas pipelines, the generally accepted moisture limit is a dew point of –

4°F (-20°C). The sequence of air drying activities


 Initial drying with dry air
 Final drying with dry air
 Soak test
3.1 Initial drying with dry air

Initial drying will be done with dry air compressor. The facilitating evaporation into the
dry air stream. The pipeline dries from the launch end and gradually progresses in a
front down the pipeline.

The executer must make sure pressure at receiver side is just above the atmospheric
pressure throughout the drying, by this lower the pressure more water vapour the air
can absorb and the quicker the pipeline will dry.
In addition to measuring the outlet dew point, the appearance of dust gives strong visual
indication that the line is beginning to dry.
3.2 Final drying with dry air

If further reductions in the dew point required, it can be achieved by simply continuing to blow air
through the line until the desired dew point is achieved.
3.3 Soak test

After reaching desired dew point, all the opening to the pipeline should be closed for minimum of
48 hours at a pressure of 0.5 bar above the ambient pressure at all point along the pipeline.
After 48 hours of soak test pipeline dew point shall be monitored at both ends to ensure the
required dew point is achieved throughout the pipeline. During starting and finishing time dew
point, ambient temperature and pipe temperature must be checked and recorded.
On acceptance, the pipeline drying campaign is complete. The pipeline shall then be nitrogen
purged and packed with nitrogen at pressure 2 bar. This positive pressure shall be maintained
until start of commissioning.

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 8 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

4 Execution Schedule

Air drying Instruments, materials and equipment’s required to undertake the test shall include oil- free
compressors with dryer, instrumentation recorders, all essential equipment.

Drying materials manifolds shall incorporate end enclosures, by-pass pipe work and valves for
Continuous drying activity.
All equipment’s shall be inspected to ensure that it meets all safety requirements. All calibration certificates of
pressure gauges, dew point meter shall be available at the point of use.

Below the expected drying time for each pipeline:

Appendix 01

Location Responsible Start date Complete date


Trunk Line TK-02 Adnan Abbas Oday 25/02/2019 03/03/2019
Trunk Line TK-04 Adnan Abbas Oday 04/03/2019 12/03/2019
Trunk LineTK-03 Adnan Abbas Oday 13/03/2019 20/03/2019
Trunk Line TK-01 Adnan Abbas Oday 21/03/2019 30/03/2019

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 9 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

3.1. Equipment Certificate

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 10 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

3.2. Risk Assessment

Project Name Zubair Oil Field Development Project Location:

Work Activity Preparation of Air Drying during Pre-commissioning Activity Date:


Proce
Severi Likelih Risk
No Job Steps Potential Hazards Harm Control Measures ty ood Level
dure
No.

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 12 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

Project Name Zubair Oil Field Development Project Location:


 Unauthorized work  Obtain valid operation permit approved by commissioning/operation
Unskilled and untrained authorized personnel
personnel starting the job  Allow only trained and qualified workers to assign jobs.
leading to incident /  Operatives shall receive Commissioning/operation Safety Induction.
accident.  Emergency Response Procedure shall be discussed with the crew.
 Emergency situations  Employees are not allowed to leave their job site without informing the
 Asphyxiation hazards job supervisor.
 High noise areas  Equipment  Explain the work sequence clearly by job supervisor.
 Unauthorized tampering or damage  Ensure all assign crew participated and attend group TBM.
Preparation triggering any field control
1.  Personal Injury  Always use mandatory PPE and Job specific PPE if required. 2 B 2B
works panels, devices, sensors  Smoking is strictly prohibited in the work place use designated
and fire alarm system and smoking shelter.
removing of LOTO without  Ear protection required on high noise areas exceeding 85 db noise
approval. level.
 Failure to identify correct  Never remove LOTO, touch or tamper any energized field control
isolations. panels, devices, sensors or triggering device for fire alarm system
 Release of N2 gas, Parts of unless approved by commissioning authorized person.
system untested, over  Barricade system to be leak tested and provide signage on work area
pressurise system.

DCBM shall describe the policies and practices for managing risk and a summary of the risk analysis results. Risk management shall be addressed in the PEP. The
preliminary shall summarize the key project risks. Key risks or “critical risks” are those estimated to have the most impact on cost and schedule and could include
project, technical, internal, external, and other sub-categories.

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 13 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

Site
Mobilization,
line checking
and installation
 Site speed limit of 20 KPH shall be observed at all times.
of barricade
 Equipment Failure  Ensure pre-use inspection of vehicle and equipment’s conducted prior
and signage,
 Traffic Hazard to use.
Connection of  Vehicular Accident  Only authorized drivers shall be allowed to drive the vehicle. Site traffic
temporary hose  Collision with vehicle,
 Personal Injury regulation shall be adhered at all times.
2. equipment and personnel  Verify system lines to be leak tested on P and ID drawings 2 C 2C
 Damage to
 Wrong system  System line should be marked up for easy identification.
Property
identification  Defective and home-made tool shall not be used on site.
 Hand Injuries  Wear proper PPE for the task
 Slip and trips  Ensure access and work area free from obstructions
 Material Fall  Vehicle shall be parked at dedicated parking area only.
 Obstruction

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 14 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 15 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

 Should be obtain Permit and need to add all relevant information


(Drawings, Connection Joint, Mark up P&ID).
 Tool box meeting for all personals involved in the activity should be
conducted, discussion include hazards and precaution for particular
activity.
 Allowed only competent and qualified worker to do the activity.
 Should be barricade the area properly and Provide signages atleast 5mtr
surrounded.
 Notification Protocol shall be followed and confirmed prior to start flushing,
blowing.
 Noise – Ear Impact,  Should be wear proper PPE – Ear Plug, duct Mask, Face Shield etc…..
 Should be maintain safe distance between equipments like Air
Flying Objects, Hit,
Compressor 3mtr – Manifold 3 Mtr – Pipe 3 Mtr approx.
Injury, Failure of
 Personnal  Should be Maintain Safe Distance at Air Blowing/Venting Area.
Piping, cause by
Injury  Proper support at Blowing point to reduce thrust effect.
Air Drying using over pressure,
3  Property  Proper communication between team members. 2 C 2C
Air Compressor Improper
Damaged  Warning Signages and Information of the hazard to neighbor using
bolting/gasket at
megaphone and whistle.
Flange joint area  Inspection of Equipments, Tools, Connection of hoses and Provide
 Equipment Failure
inspection Sticker and Apporved TPI certification for Manifold, Guages
and Hoses.
 Provide PSV to avoid over pressuring.
 Shuold be provide whiplash arrestor for both end of the connected hoses.
 Should be provide Shield or vent to prevent
 All the temporary connectionn should be pressure rated and Inspected for
damage/defects prior to use.
 Notify all personal working within the vicinity of air blowing.
 Should be wear earplug when start the blowing out.
 Double Check the each re bolting point.
 Watch man to be organized for access control.
 Proper Ergonomics.
 Should be inspect the Equipment and Color Coded by competent Person.

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 16 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

 Site inductions for personnel.


 Inadequate Access &  Follow site Safety rules & regulation.
 Maintain speed limits. Reverse with a banks man.
Egress
 Ensure vehicles are serviced. Ensure loads are secure.
 Insufficient turning
 Heavy items to be lifted by two or more persons. Personnel to be trained in
circle.
‘Manual Handling.
 Movement of
 Personnel trained in the correct selection and use of hand tools.
vehicles in and out of  Site Supervisor to check rig up and routing of hoses.
site  Hoses to be rigged up away from access points and above head height
 Manual handling of where possible.
heavy equipment  Harness to be worn by personnel working at height1.8m
items.  Suitable scaffolding/ladders to be provided.
 Incorrect lifting of  All hosing to be used is of suitable pressure rating and carries appropriate
equipment items. certification.
 Inadequate pressure  Supervisor and Client representative to check equipment rig up.
Assess work rating or is damaged.  Check test certificates for all pipe work.
area Access  Over pressurise or  Personnal  Check unit, sling and crane Lifting Certification.
and Weather rupture hosing. injury Property  Attach guide rope during lift.
 Rig up hosing onto Damage  Do not lift over personnel or sensitive equipment. Use trained banks man
condition
wrong injection point  Equipment during lifting operation. Slings to be attached by a qualified person.
4 Rig up and onto an adjacent Damage  Plan and schedule vehicle movements. If required liase with local personnel. 2 C 2C
Equipment  Environmental  Valve checklist checked and signed by Authorize Person Double block and
system.
and  Fall of unit from  Effect bleeds where possible. Secondary vent paths identified and aligned.
Alignment of  Personnel  System walked and alignment checked by Authorized Person Pre ops
height o
system and  Failure of slings or involved with checklist completed and signed. OPP connection as close as possible to
Isolation attachments operation. injection point.
 System incorrectly  Make sure all access ladders, steps and ramps are safe and secure.
 Make sure edge protection and handrails are in place and secure where
isolated.
 System internal required.
 Immediately cease work in hazardous weather conditions such as:
valves closed.
o Thunderstorms and strong winds that may cause loss of
 Public (pedestrians /
balance;
others) o Rain is causing a slippery work surface;
 Hit by falling objects o Excessive glare is being emitted from work surfaces and/or
 Slips, trips and falls
poor lighting affects visibility;
 Lighting  Remove any items that may obstruct the work activity; and
 Eye injury  Check for any items that may cause slips, trips and falls and remove or
secure them as required
METHOD STATEMENT FOR DRYING OPERATIONS Sheet 17 of 25
(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 18 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

 Wrong system  Verify system and lines on approved P and ID


 System line and equipment not included on the purging must be
identification
 Damage to other isolated by valves or positive blinds and follow LOTO procedures
 Ensure hose connection and fittings tight and secured with whiplash
equipment and pipes
 Hose dislodge from arrestor
 Check hose and fittings for any defects
connection
 Ensure all pressure gauge and relief valves properly calibrated and
 Rupture of hose
 Over pressurization inspected.
 Only authorized person to enter the test area.
resulting to rupture of
 Always use mandatory PPE and Job specific PPE if required.
Opening of pipes and equipment’s  Defective and home-made tool shall not be used on site.
 Asphyxiation hazards from  Close supervision and monitoring at all times
5 valve and  Personal Injury
Nitrogen purged lines or  Provide proper communication means . 3 C 3C
purging of  Damage to
equipment  Emergency Contact Numbers available on work area
nitrogen to gas Property
 Unauthorized entry on leak  Ear protection required on high noise areas exceeding 85 db noise
line test area level
 Hand Injuries  Ensure access and work area free from obstructions
 Lack of supervision and  Ensure all personnel attend work at height training.
monitoring  Use full body harness above 1.8 meters of height.
 Lack of communication  Always hook above the shoulders.
 Emergency situations  100% TIE-OFF at all times whenever required.
 High noise areas  All tools and materials should be tied and secured.
 Slip and trips  Ensure close supervision by supervisor
 Fall from heights  Work only in green tag scaffolding and approved steel structure
 Falling objects platforms
 Never work alone on elevated areas, maintain buddy-buddy system

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 19 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

 Un necessary materials and scrap materials must be removed from


 Hand injury  Personal Injury elevated areas
Completion of  Slip and trips  Damage to  Materials that could easily fall or slip on gratings to be place inside
6 work and house  Falling objects Property secured containers. 2 B 2B
keeping  Waste accumulation  Wear proper PPE for the task given.
 Environmental
 Conduct housekeeping and proper material segregation.
effect  Dispose waste on proper waste disposal area.

Prepared by: Subcontractor Name Position Signature

SICIM
Reviewed by: Name Position Signature
Department/SI
SICIM
Approved by: Name Position Signature
HSE Department

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 20 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

3.3. Daily report


PIPELINE DRYING REPORT

Test Package No.


Pipeline No.
Pipeline Size (inch)
Location

Ambient Dew Point at


S/N Time Remarks
Temp. °C Pipeline End °C

Remarks.

SUBCONTRACTOR CONTRACTOR COMPANY

NAME

SIGNATURE

DATE

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 22 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

ZUBAIR OIL FIELD DEVELOPMENT


PROJECT
SICIM CONTRACT ID:IQ022-2001-SI-029-0
Dr.Concrete Building Material
PIPELINE SWABBING AND DRYING RECORD
TEST PACK No TEST SECTION TEST SECTION
WALL
PIPE SIZE : THICKNESS :

PIG TYPES :

RECEIVING AVERAGE WEIGHT


DATE PIG TYPE LAUNCHING TIME DEW POINT REMARKS
TIME PRESSURE LAUNCHING TIME RECEIVING TIME

REMARKS : ACCEPTABLE □ NOT ACCEPTABLE □


DCBM SICIM Eni Iraq BV ZFOD

NAME

SIGNATURE

DATE

Annex-01 Pipeline Swabbing and drying Record

Annex - 02 Soak Test Record

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 24 of 25


(St) Prodi Unit Type Dev. Serial Rev

(2) IQ22 00 2001 SI 029 0


Contact N°:
IQ022-00-2001-SI-029-0
Document ID:
SICIM DOCUMENT
Method Statement for Drying Operations
TITLE:

IRAQ - ZUBAR OIL FIELD DEVELOPMENT PROJECT – MULTIPHASE PIPELINES BETWEEN DGS

ZUBAIR OIL FIELD DEVELOPMENT PROJECT


CONTRACT ID:IQ022-2001-SI-029-0

Dr.Concrete Building Material


Soak Test Record

Test Pack no.: Line No.:


Test Limit: From: To : Date :
From Chainage: To Chainage :
Section Length: Pipeline Section no.:
Diameter: Thickness:
Dew point Reading
Ambient temperature Remarks
Date Time Pipe temperature measured from
Launcher Receiver measured from
thermocouples.
Thermocouples.
TP(Launcher TP2(Receiver side) TP TP
side) 1 2

REMARKS : ACCEPTABLE □ NOT ACCEPTABLE □


Remarks :

DCBM SICIM Eni Iraq ZFOD


BV

Name

Signature

Date

METHOD STATEMENT FOR DRYING OPERATIONS Sheet 25 of 25

You might also like