PROJECT: 2x40 MW NMDC Power Plant Contractor: Sms Engineering Services PO NO: 3000005119 Rev 1
PROJECT: 2x40 MW NMDC Power Plant Contractor: Sms Engineering Services PO NO: 3000005119 Rev 1
Quantity
Task Line Description UOM Ordered Unit Price
ENC01 1 corner Link fixing & welding Number 8 2939.8
APH BY PASS DUCT - pre-assembly, erection , Metric
ENC01 2 testing, touch-up painting Tonne 4 12230
APH to ID FAN duct - pre-assembly, erection , Metric
ENC01 3 testing, touch-up painting Tonne 10 12230
APH to wind box duct - pre-assembly, erection , Metric
ENC01 4 testing, touch-up painting Tonne 3 6585
Boiler to eco duct - pre-assembly, erection , testing, Metric
ENC01 5 touch-up painting Tonne 12 12230
COG DUCT -Erecetion, alignment & welding - back Metric
ENC01 6 chipping, In root E- 6010 to be used Tonne 35 13171
CONVECTION BANK HOPPER - pre-assembly, Metric
ENC01 7 erection , testing, touch-up painting Tonne 10 12230
Convection bank casing - erection, alignment & Metric
ENC01 8 welding Tonne 4.6 14111
ENC01 9 ECO coil scallop plate fixing Metre 40 587.97
FD FAN to APH duct - pre-assembly, erection , Metric
ENC01 10 testing, touch-up painting Tonne 8 12230
Metric
ENC01 11 FD Fan - erection, alignment and commsissioining Tonne 11 14111
Guillotine dampers - pre-assembly, erection , Metric
ENC01 12 testing, touch-up painting Tonne 12.2 12230
ENC01 13 Hydraulic Test Lot 1 141113
NON integral Piping - pre-assembly, erection , Metric
ENC01 14 testing, touch-up painting Tonne 11 39512
ID FAN to CHIMNEY DUCT - pre-assembly, erection , Metric
ENC01 15 testing, touch-up painting Tonne 22 12230
Metric
ENC01 16 ID Fan - erection, alignment and commsissioining Tonne 32 14111
ENC01 17 Joint repair Number 30 4076.61
Liquidation of punch point - Points related to Boiler
ENC01 18 #3 Lot 1 211670
Penthouse
structure
Gas duct vent & Purging piping
Description weight
50 NB pipe 1675.52
150 NB Pipe 741.95
150 NB Pipe 1117.71
50 sov 528
80 sov 792
1 ball 316.8
2 ball 237.6
150 NB GV 484
3 ball 237.6
support 2200
25 Nb 219.7
25 NB SOV 442.8
8993.68
SR.NO Description QTY Mt. Rate amount
1 BFP DISCHARGE 10.379 27200 282308.8
2 BFP SUCTION 1.608 27200 43737.6
3 Mainsteam & TG INLET 9.967 28800 287049.6
4 PROCESS CONTROL STATION 3.023 27200 82225.6
5 BLEED & EXTRACTION LINE 9.521 27200 258971.2
Total amount 954292.8