Professional Documents
Culture Documents
CHAPTER I: INTRODUCTION
1.1 BACKGROUND AND RATIONALE OF THE EIA STUDY REPORT
1.2 OBJECTIVE
1.3 SPECIFIC OBJECTIVE OF THE PROJECT
1.4 OBJECTIVE OF THE STUDY
1.5 SCOPE OF THE STUDY
1.6 METHODOLOGY
This Environmental Impact Assessment project requires skills and knowledge about
engineering. The core team was made up of the following persons.
OBJECTIVE
The objectives of this EIA study for road re-blocking is;
- To assess the environment costs and benefits of the proposed project to the local
government of Goa.
- To prevent traffic, specifically in Numeriano D. Rodriguez Ave. Corner Bagumbayan
Grande Street, Goa, Camarines Sur
- To prevent the overflowing of water.
METHODOLOGY
In this part the methodology of the project will be discussed. The methodology used in
the study consisted of the following.
i) A site inspection and survey in the project to provide information about the
project.
ii) Discussion or interview with the project in charge or project engineer.
iii) Interview some of the respondents.
iv) Assessment of the project documents.
v) Traffic count in the area.
vi) Assessment of the impacts of the project.
vii) Proposal of the possible measures to minimize negative impacts.
CHAPTER I
PROJECT DESCRIPTION
SITE OWNERSHIP
The site is covered by the Mayor, Honorable Marcel Pan of Municipality of Goa.
It is the National Highway that the government owned land. The location is capable for the said
project
.
TRAFFIC COUNT
Traffic count in the area was conducted for three days including Monday, Friday,
and Saturday during 6:00am until 6:00 pm. The count was categorized in different type of
vehicle including motorcycle, tricycle, jeep, bus, truck, and SUV/PUV.
CHAPTER III
STUDY AREA
Baseline Information and Environmental Settings
The proposed project (Road Re-blocking) site lies in the intersection along Brgy. Matacla
Goa, Camarines Sur near at Partido College. Goa is bounded by the Municipality of Tinambac
west, Municipalities of Tinambac and Lagonoy on the north, and by Municipalities of San Jose
and Lagonoy on the east thus better road is much needed to accommodate all transportation
vehicle for various Municipalities. It has a total land area about 3.99 % of the total province land
area characterized as level to gently rolling and sloping. The majority sloping area was placed
along Tinambac and Lagonoy north. On the other hand, San Jose and Lagonoy west was
characterized as level to gently rolling.
The elevation of the municipality is almost 92.55% low to very low with a mean
elevation from 0–100 meters above sea level. Hence, low elevation is about 5.72% ranging from
100–300 meters above sea level as well as 1.73% with moderately high elevation ranging from
300–500 meters above sea level.
The rainfall distribution in the municipality is greatly influenced by the air streams,
tropical cyclone (Intertropical Convergence Zone). The rainfall season occurs from June to
December with high rainfall intensity of 285.06mm to 474.22m and less rainfall intensity of
245.30mm to 224.06m from January to the month May which at the same time is the onset of
effective rainfall with 75% probability and it would terminate in February of the following year
which consequently during this period the mountainous areas receive higher intensity of rainfall.
But the trend of monthly rainfall is unimodal (having one peak) and the maximum rain period is
from October to December. On the other hand, the monthly average rainfall varies from
125.86mm to 594.56mm with a mean annual rainfall of 298.54mm.
Waste Management
Municipal implement segregation of any solid waste generated by the residents and
contracted a companies to handle their solid waste including woods, textile and metal.
Waste Water Disposal
Liquid waste in the area is mostly managed by the Local Government Unit of the
municipality of Goa, Camarines Sur.
CHAPTER IV
ENVIRONENTAL IMPACTS AND MIIGATION
MEASURES DESCRIPTION OF THE EXISTING AND ANTICIPATED IMPACTS
ANTICIPATED IMPACTS:
The impacts of the proposed project on the environmental elements are both positive and
negative. The magnitude of each impact is described in terms of being significant, minor or
permanent, short-term or long term, specific (localized) or widespread, reversible or irreversible.
Most of the impacts have been addressed in the proactive design of the project and other
mitigations can only be guaranteed through active and responsible management committed to the
propositions of the environmental management plan.
PREDICTED IMPACTS
Environmental impacts are caused by environmental aspects and can have a
direct Impact on the environment, contribute indirectly to a larger
environmental change, or be cumulative.
IMPACTS OF DURING CONSTRUCTION PHASES
NEGATIVE OR ADVERSE IMPACT
LAND ENVIRONMENT
Change of existing profile pattern of the land
Loss of agricultural land due land acquisition for residential development
Generation of solid waste in the form of construction spoils
SOCIAL ENVIRONMENT
Sanitation and health hazards due to inflow of construction of labor
Improved economic activities and trade in the region
WATER ENVIRONMENT
Ambient air quality will be monitored within the plant and in the vicinity as
directed by Orissa Pollution Control Board. The parameters will include SPM,
RPM, SO2 and NO2. The report will be submitted to Orissa Pollution Control
Board. The sampling and analysis of air pollutants will be done as per the norms
suggested by Central Pollution Control Board (Emission Regulations Part-III) and
also the Bureau of Indian Standards IS-5182.
STACK EMISSIONS
NOISE MONITORING
Noise monitoring will be carried out inside the units near the high noise
generating areas once in a month. Ambient noise monitoring just outside the plant
limit will be conducted monthly. Noise levels monitored will include Leq day &
night, Lmax, and Lmin.
QUALITY ASSURANCE
A quality assurance plan should be developed which will include all references
methods for monitoring, relevant analytical techniques, calibration of equipment,
standard of reagents, collection and presentation of results etc. All monitoring
activities will be reviewed to find out the implementation of all the required
norms. Periodic environmental audit may be arranged to make quality assurance a
success.
Periodic monitoring of the health of the workers will be carried out as required by
Factories Act. For safety, mock drill of the concerned employees for handling the
emergency situation will be carried out, as a part of On-Site Emergency Plan. Air
Quality at the work place will be measured intermittently.
IMPROVEMENT OF EMP
ACTIVITY PHASES OF EMP
This table show the activity life cycle of environmental management plan the first phase
is the pre-feasibility second the feasibility of the stud , the design , the establishment or the
construction phase, the implementation or operation and the closure .
CHAPTER VI
PUBLIC CONULTATION
PUBLIC PARTICIPATION
Public participation may be defined as the involvement of individuals and groups that
are positively or negatively affected by a proposed intervention (e.g. a project, a programme, a
plan, a policy) subject to a decision-making process or are interested in it. Levels of participation
in impact assessment vary, from passive participation or information reception (a unidirectional
form of participation), to participation through consultation (such as public hearings and open-
houses), to interactive participation (such as workshops, negotiation, mediation and even co-
management). Different levels of public participation may be relevant to the different phases of
an impact assessment process, from initial community analysis and notice of the proposed
intervention, to approval decision making, to monitoring and follow-up.
OBJECTIVES OF PUBLIC PARTICIPATION
Public participation is essential for good governance and may empower local
communities. Impact assessment is multi-purposive, aiming specifically to:
Invite the affected and interested public into the decision-making process to foster
justice, equity and collaboration;
Inform and educate the stakeholders (which includes the proponent, public,
decision-maker(s) and the regulator) on the planned intervention and its
consequences;
Gather data and information from the public about their human (including
cultural, social, economic and political dimensions) and biophysical environment,
as well as about the relations (including those related to traditional and local
knowledge) they have with their environment;
Questionnaires
Detailed questionnaires on the project were administered among the neighbours and other
stakeholders within the vicinity of the project. Form the analysis; few are opposed to the
project. They are proposing various mitigation measures to be implemented and their
recommendations have been captured in the EMP. Sample questionnaires have been
attached to the study report