You are on page 1of 3

PROJECT QUALITY PLAN (PQP) SUBMITTAL CHECKLIST

Contract No. : PQP Ref. :


Contractor : PQP Ver. :
Consultant : PQP Date :

Contract Title : Reviewed By :

Project Manager Review Date :


Review (By
Available Adequate
Item & No. Description / Requirement Remarks Consultant/Cl
Y/N Y/N
ient)
A1 PQP Index

A2 PQP Revision status

A3 PQP Approval Signatures

A4 PQP Distribution List. Distribution shall be as per the


CONTRACT.
A
PQP

A5 PQP scope

A6 Details of CONTRACTOR’s procedure for preparing,


reviewing, approving, revising and re-issuing the PQP during
the CONTRACT

B1 Details on how the CONTRACTOR’s Corporate Quality


Management System shall be applied and implemented in the
B
QMS

project, as applicable.

C1 Detailed Contract Scope of Work.


Scope of

C
Works

C2 Contract Program of Works (Schedule).

D1 Identification of all main work activities and sub-activities to


be controlled by the PQP.
Main activities &
sub-contracted

D2 Identification of activities that will be carried out by sub-


activities

D
contractors. State details of sub-contractors Quality
Management System and how it will be monitored and
controlled by the main CONTRACTOR.

E1 Organizational Chart specific to the CONTRACT identifying


functions and job title of all management and staff down to
Organizational structure

foreman level.

E E2 Schedule of responsibilities for all key functions utilized in the


project as shown in the organization chart including
responsibilities of the Management Representative and
QA/QC personnel.

F1 List of QMS Procedures & Manuals


QMS Documents applicable to this contract

F2 List of Drawings and Shop Drawings

F3 List of Method Statements (MS)

F4 List of Work Instructions (WI)

F5 List of Inspection & Test Plans (ITP) or Quality Control


F Plans (QCP)

F6 List of Forms and Formats with unique numbers

F7 Sub-Contractor Procedures, MS, WI, ITP, QCP, Drawings,


Forms, etc. In case no sub-contractors are required on this
contract, this should be indicated in the PQP (see D2 above).

G1 Internal Audit Procedure


Audit Plans (Int. &

G2 Internal / external Audit Plans


G
Ext.)

G3 External Audit Schedule of Sub-contractors

1 of 3
PROJECT QUALITY PLAN (PQP) SUBMITTAL CHECKLIST
Contract No. : PQP Ref. :
Contractor : PQP Ver. :
Consultant : PQP Date :

Contract Title : Reviewed By :

Project Manager Review Date :


Review (By
Available Adequate
Item & No. Description / Requirement Remarks Consultant/Cl
Y/N Y/N
ient)
Where the services of a Third Party Certification is required
by the CONTRACT, the Project Quality Plan shall include :
Inspection (TPI)
Third Party

H H1 Details of the services that will provided by TPI.

H2 List and details of the TPI Certification Authority.

I1 A project specific Document Control Procedure shall be


prepared to control the issue, distribution, change, review,
location, and/or withdrawal of all documentation, drawings,
Document Control

procedures, submittals, correspondences, etc., that are related


I to the project.
I2 Document Control Procedure detailing the preparation of
Test Pack and As-built Documentation Dossier towards
handover.

J1 A documented procedure for Control of Non-Conforming


Products establishing that product/s (goods or services) that
Non-Conforming

does not conform to requirements stipulated in the


Products

J CONTRACT is identified and controlled to prevent its


unintended use or delivery.

K1 A documented procedure for Corrective Actions shall be


established by the CONTRACTOR.
Corrective
Actions

L1 A documented procedure for Preventive Actions


establishing system to identify and plan actions to eliminate
Preventive
Actions

L the cause of potential nonconformities and to prevent their


occurrence.
M1 A documented procedure for Record Control shall be
established by the CONTRACTOR and his sub-contractors to
Record Control

define the controls required for the identification, storage,


M protection, retrieval, retention time, and disposition of records.

N1 A documented procedure or system shall be identified in the


PQP with regards to Inspection, Measuring and Test
Inspection &
Measuring

N Equipment

O1 Material, sub-contractors and suppliers shall be selected from


ADDC's approved vendors list (as per ADDC contract
Procurement Control

documents), and where not detailed, from the contractor's own


approved vendors list.
O
O2 Procurement schedule for all important contract materials
showing all critical dates such as submittal, approval, order
and site expected dates. Dates will be based on program of
works.

2 of 3
PROJECT QUALITY PLAN (PQP) SUBMITTAL CHECKLIST
Contract No. : PQP Ref. :
Contractor : PQP Ver. :
Consultant : PQP Date :

Contract Title : Reviewed By :

Project Manager Review Date :


Review (By
Available Adequate
Item & No. Description / Requirement Remarks Consultant/Cl
Y/N Y/N
ient)
P1 Materials submittal schedule

P2 Drawings submittal schedule


Submittals &
Approvals

P P3 Procurement schedule

P4 Approved Subcontractors schedule (as applicable)

Q1 Procedure or system for progress monitoring and reporting


including but not limited to MS, WI, procedures, drawings,
Progress &
Reporting

Q material procurement, construction, commissioning, etc.

R1 A procedure, system or statement is required so that Client


shall have the right to inspect at all times all tools,
instruments, materials, staging, equipment, templates, work
technique, etc., used or to be used in the performance of the
R
Client

WORKS. This shall include pre-inspection meetings.

R2 A statement from the contractor ensuring his adherence to


Client projects, quality and HSE procedures.

S1 Quality Improvement program or Lessons Learned system /


procedure to improve existing practices must be implemented
Lessons Learned

as an integrated part of the contract. Format for Lessons


S Learned and relevant action plan to be provided in the PQP
and results be reported as part of the close-out report.

T1 HSE Plan prepared and submitted by Contractor.


T
HSE

Quality policy and QMS certificate (copies) for :


ISO 9001:2000 Policy &

U1 Contractor
Certificate

U
U2 Sub-contractor (if applicable)

Shaded items denote deficiencies and improvements that are required to the submitted PQP to render it acceptable and in line with Client quality requirements.

Acceptable Improve Not Acceptable


PQP Status :

3 of 3

You might also like