Activity ID Activity Name Original Start Finish J July 2010 A S O N D J F
Duration 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1
160 21-Jun-10 28-Dec-10 28-Dec-10, Cleopatra Jungle
Cleopatra Jungle
Startup Phase 0

Construction Phase 160 21-Jun-10 28-Dec-10 28-Dec-10, Construction Phase

Zone.No 1 116 21-Jun-10 02-Nov-10 02-Nov-10, Zone.No 1


Villa Number D10 104 03-Jul-10 31-Oct-10 31-Oct-10, Villa Number D10
A10540 Start Villa construction 0 03-Jul-10 Start Villa construction
A10550 finish Villa construction 0 31-Oct-10 finish Villa construction
Villa Number B11 102 23-Jun-10 19-Oct-10 19-Oct-10, Villa Number B11
A10940 Start Villa construction 0 23-Jun-10 Start Villa construction
A10950 finish Villa construction 0 19-Oct-10 finish Villa construction
Villa Number B12 103 21-Jun-10 18-Oct-10 18-Oct-10, Villa Number B12
A11340 Start Villa construction 0 21-Jun-10 Start Villa construction
A11350 finish Villa construction 0 18-Oct-10 finish Villa construction
Villa Number B13 108 27-Jun-10 30-Oct-10 30-Oct-10, Villa Number B13
A11740 Start Villa construction 0 27-Jun-10 Start Villa construction
A11750 finish Villa construction 0 30-Oct-10 finish Villa construction
Villa Number B14 116 21-Jun-10 02-Nov-10 02-Nov-10, Villa Number B14
A12140 Start Villa construction 0 21-Jun-10 Start Villa construction
A12150 finish Villa construction 0 02-Nov-10 finish Villa construction
Zone.No 2 125 21-Jun-10 13-Nov-10 13-Nov-10, Zone.No 2
Villa Number D89 116 21-Jun-10 02-Nov-10 02-Nov-10, Villa Number D89
A13340 Start Villa construction 0 21-Jun-10 Start Villa construction
A13350 finish Villa construction 0 02-Nov-10 finish Villa construction
Villa Number D90 72 08-Jul-10 29-Sep-10 29-Sep-10, Villa Number D90
A13740 Start Villa construction 0 08-Jul-10 Start Villa construction
A13750 finish Villa construction 0 29-Sep-10 finish Villa construction
Villa Number D91 102 10-Jul-10 04-Nov-10 04-Nov-10, Villa Number D91

TASK filter: start and finish dates. Date Revision Checked Approved
Remaining Level of Effort Milestone
Actual Work Summary Page 1 of 3
Remaining Work
Critical Remaining Work  
  Dr.Ibrahim mahfouz
Cleopatra Jungle
Activity ID Activity Name Original Start Finish J July 2010 A S O N D J F
Duration 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1
A14140 Start Villa construction 0 10-Jul-10 Start Villa construction
A14150 finish Villa construction 0 04-Nov-10 finish Villa construction
Villa Number A92 102 11-Jul-10 06-Nov-10 06-Nov-10, Villa Number A92
A14540 Start Villa construction 0 11-Jul-10 Start Villa construction
A14550 finish Villa construction 0 06-Nov-10 finish Villa construction
Villa Number F93 102 12-Jul-10 07-Nov-10 07-Nov-10, Villa Number F93
A14940 Start Villa construction 0 12-Jul-10 Start Villa construction
A14950 finish Villa construction 0 07-Nov-10 finish Villa construction
Villa Number F94 102 13-Jul-10 08-Nov-10 08-Nov-10, Villa Number F94
A15340 Start Villa construction 0 13-Jul-10 Start Villa construction
A15350 finish Villa construction 0 08-Nov-10 finish Villa construction
Villa Number A95 102 12-Jul-10 07-Nov-10 07-Nov-10, Villa Number A95
A15740 Start Villa construction 0 12-Jul-10 Start Villa construction
A15750 finish Villa construction 0 07-Nov-10 finish Villa construction
Villa Number A96 102 18-Jul-10 13-Nov-10 13-Nov-10, Villa Number A96
A16140 Start Villa construction 0 18-Jul-10 Start Villa construction
A16150 finish Villa construction 0 13-Nov-10 finish Villa construction
Villa Number A97 102 17-Jul-10 11-Nov-10 11-Nov-10, Villa Number A97
A16540 Start Villa construction 0 17-Jul-10 Start Villa construction
A16550 finish Villa construction 0 11-Nov-10 finish Villa construction
Zone.No 3 105 10-Aug-10 14-Dec-10 14-Dec-10, Zone.No 3
Villa Number D9 100 11-Aug-10 09-Dec-10 09-Dec-10, Villa Number D
A10230 Start Villa construction 0 11-Aug-10 Start Villa construction
A10240 finish Villa construction 0 09-Dec-10 finish Villa construction
Villa Number B102 100 10-Aug-10 08-Dec-10 08-Dec-10, Villa Number B
A12540 Start Villa construction 0 10-Aug-10 Start Villa construction
A12550 finish Villa construction 0 08-Dec-10 finish Villa construction
Villa Number B107 100 10-Aug-10 08-Dec-10 08-Dec-10, Villa Number B

TASK filter: start and finish dates. Date Revision Checked Approved
Remaining Level of Effort Milestone
Actual Work Summary Page 2 of 3
Remaining Work
Critical Remaining Work  
  Dr.Ibrahim mahfouz
Cleopatra Jungle
Activity ID Activity Name Original Start Finish J July 2010 A S O N D J F
Duration 2 0 1 1 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 1
A12940 Start Villa construction 0 10-Aug-10 Start Villa construction
A12950 finish Villa construction 0 08-Dec-10 finish Villa construction
Villa Number E08 102 14-Aug-10 14-Dec-10 14-Dec-10, Villa Number E
A16940 Start Villa construction 0 14-Aug-10 Start Villa construction
A16950 finish Villa construction 0 14-Dec-10 finish Villa construction
Villa Number B106 102 12-Aug-10 13-Dec-10 13-Dec-10, Villa Number B
A18540 Start Villa construction 0 12-Aug-10 Start Villa construction
A18550 finish Villa construction 0 13-Dec-10 finish Villa construction
Villa Number B105 102 12-Aug-10 13-Dec-10 13-Dec-10, Villa Number B
A18940 Start Villa construction 0 12-Aug-10 Start Villa construction
A18950 finish Villa construction 0 13-Dec-10 finish Villa construction
Zone.No 4 (Hold) 110 18-Aug-10 28-Dec-10 28-Dec-10, Zone.No
Villa Number A55 110 18-Aug-10 28-Dec-10 28-Dec-10, Villa Number A
A17340 Start Villa construction 0 18-Aug-10 Start Villa construction
A17350 finish Villa construction 0 28-Dec-10 finish Villa construction
Villa Number A86 110 18-Aug-10 28-Dec-10 28-Dec-10, Villa Number A
A17740 Start Villa construction 0 18-Aug-10 Start Villa construction
A17750 finish Villa construction 0 28-Dec-10 finish Villa construction
Villa Number A87 110 18-Aug-10 28-Dec-10 28-Dec-10, Villa Number A
A18140 Start Villa construction 0 18-Aug-10 Start Villa construction
A18150 finish Villa construction 0 28-Dec-10 finish Villa construction

Closing phase 0

TASK filter: start and finish dates. Date Revision Checked Approved
Remaining Level of Effort Milestone
Actual Work Summary Page 3 of 3