Professional Documents
Culture Documents
BC PDF
BC PDF
BITUMINOUS CONCRETE
1.1 General
1.1.1 Purpose / aim of the Method Statement submission:
As per the contract drawings and technical specification Clause No: 512, BOQ item
No.4.05.
1.3 Surveys
BC will be laid after completion of necessary survey checks on DBM surface by
supervision staff.
1.4 Utilities
All identified utilities like electrical poles, telephone cables etc.; will be relocated before
starting of the embankment works.
Traffic will be diverted on another carriageway by providing traffic signs and safety
measures. Moreover necessary extra manpower and display boards will be placed to
regulating the flow of traffic with out causing any congestion or stagnation so that no
mitigation arises.
1.6 Access
Land access will be provided with the temporary diversions where necessary.
Material Testing
Removal of unwanted material from Tack coat treated surface (if any)
Transiting BC Mix
Compaction
a) The layer on which the BC will be laid will be prepared, shaped and conditioned
to the specified lines, grades and cross sections in accordance with the working
drawings.
b) The surface on which BC layer is being laid will be swept clean free from dust
foreign matter by using mechanical broom and air compressor.
c) The mix will be transported from the HMP to the site and will be spread by means
of self-propelled sensor paver with suitable screeds, capable of spreading,
tamping and finishing the mix to a specified grade, line and cross section.
1. The mix once tipped into the self propelled sensor paver will be spread and
tamped to the correct lines, grades and cross sections.
2. The mix will be laid manually in restricted locations and in narrow widths where
available paver cannot be operated.
3. The temperature of the mix at the time of laying shall be in the range of 1200C –
1600C.
4. Longitudinal joints and edges will be constructed true to the delineating line
parallel to the centerline of the road.
5. All joints will be cut vertical to the full thickness of the previously laid mix and the
surface painted with hot bitumen prior to placing fresh material.
6. Paving will be done up to the full width i.e.: 8.75 m in a single operation. However
longitudinal and transverse joints shall be offset by at least 250 mm from those in
lower courses and the joint on the top most layers shall not be allowed to fall in
the wheel track.
1.10 Compaction:
Material inspection and testing shall be carried out in accordance with Tech.
Specifications. The frequency of testing may be reduced (to the satisfaction of the
Engineer) if the test results are found to be a consistent value. Notice inspection should
given to the Engineer by the site – in – charge on a standard request for inspection (RFI)
sheet.
After laying and compaction, the site Engineer will check the BC surface levels.
Pre-Batch
Material
Mixed Material
Placed Material
Compacted Material