Professional Documents
Culture Documents
AGP-GPS-ANOGP-Z02-0001
Revision Philosophy
All documents for approval will be issued at A01 as required.
If the document is for information, it will also be issued as A01.
All revisions re-Issued for approval will be issued as A02, with subsequent A03, A04, etc as
required.
Documents approved for Construction will be issued at C01, C02, and C03 respectively.
Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03 etc.
Previous revision highlighting to be removed at subsequent issues
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the
affected areas and by the use of a triangle containing the revision status.
Revision History
Table of Contents
1 PROJECT INTRODUCTION ......................................................................................... 5
2 SCOPE..................................................................................................................... 6
3 DEFINITIONS ........................................................................................................... 6
4 ABBREVIATIONS ...................................................................................................... 6
5 REFERENCE DOCUMENTS ......................................................................................... 6
5.1 Project Documents and Specifications ............................................................................ 7
5.2 Codes and Standards ...................................................................................................... 7
5.3 Exclusions ....................................................................................................................... 8
5.4 Order of Precedence....................................................................................................... 8
6 DESIGN AND LAYOUT .............................................................................................. 8
6.1 Overall Field Layout ........................................................................................................ 8
6.2 General........................................................................................................................... 8
6.3 Key Considerations ......................................................................................................... 9
6.4 Basis of Layout .............................................................................................................. 10
6.5 Separation of Facilities.................................................................................................. 10
6.6 Safety and Work Environment ...................................................................................... 11
6.7 Pipe Routing ................................................................................................................. 11
6.8 Valves ........................................................................................................................... 18
6.9 Vents, Drains and Sample Connections ......................................................................... 21
7 EQUIPMENT PIPING............................................................................................... 23
7.1 General......................................................................................................................... 23
7.2 Pumps, Compressors and Turbines ............................................................................... 24
7.3 Diesel Engine ................................................................................................................ 27
7.4 Heaters ......................................................................................................................... 27
7.5 Vessels and Towers....................................................................................................... 28
7.6 Storage Tanks ............................................................................................................... 29
7.7 Custody Meters ............................................................................................................ 31
7.8 Launcher and Receiver Stations .................................................................................... 31
7.9 LPG Storage and Piping ................................................................................................. 31
7.10 Heat Transfer Equipment .............................................................................................. 33
7.11 Additional Requirements Related to Piping System ....................................................... 35
7.12 Fittings ......................................................................................................................... 38
1 PROJECT INTRODUCTION
The ANOH reservoir comprise Assa North, located in JV Block OML 21 operated by SPDC, but also
extend into JV OML 53 Block where they are called Ohaji South operated by SEPLAT. As a
combination, the reservoir are jointly known as ANOH. These gas fields situate in Imo State, about
25Km South West of Owerri, and 70Km North-West of Port Harcourt, geographically defined
within coordinates Easting 475,000 – 490,000m and Northing 140,000 – 160,000m.
ANOH Midstream Gas Processing Plant Project is one of seven (7) critical projects identified by
Federal Government of Nigeria for supply of gas to the domestic market by Q4 2019, a project has
been active since 2004 under the stewardship of the OML 21 JV consisting of Shell Petroleum
Development Company (SPDC) and National Petroleum Investment Management Services
(NAPIMS). In October 2016, Federal Government of Nigeria, through NAPIMS, separated ANOH
development into Upstream and Mid-Stream where a 600 MMscfd Midstream gas plant would be
developed by SEPLAT whilst Upstream consisting of Wells and reservoir management would
remain with SPDC. Subsequently, that proposal was altered for SEPLAT to develop 300mmscfd
Midstream whilst SPDC would continue to manage Upstream and develop a 300mmscfd plant in
parallel.
Accordingly, the ANOH Gas Processing Company Limited (AGPC) has been formed to develop and
manage the Midstream business with the following ownership:
AGPC Midstream gas processing facilities will be jointly owned 50/50 as an IJV between Nigerian
Gas Pipeline and Transportation Company (NGPTC a division of the NNPC) and AGPC. The IJV will
wholly own the project and upon completion, own and operate the gas processing plant complete
with utilities, living quarters and infrastructure. Early Upstream scope, to be delivered by Shell
Petroleum Development Company (SPDC) on behalf of a consortium of orders in which SEPLAT has
20% share, consists of drilling six (6) gas production Wells on behalf of ANOH Operating Unit, four
(4) Wells in reservoir H1000 and two (2) Wells in reservoir H4000. Each well will be connected by
individual flow line to a central Upstream Facility also operated by SPDC to two Midstream Gas
Plants, one 300MMscf/d operated by AGPC and the other 300MMscf/d operated by SPDC.
Stabilized Gas-liquids will spike to existing crude evacuation systems pipelining to Bonny and Brass
Terminals for export, with an option for local refining, under present consideration by several Third
Parties. Produced LPG’s will be sold from the plant from evacuation by road tanker loaded from
the (included) Plant LPG depot. In this initial phase, AGPC will develop 300 MMscfd processing
Block receiving wet gas from OML 53 JV NAG development.
2 SCOPE
The scope of this document is to provide a basis for Piping engineering of plant process and / or
utility piping and components, for onshore oil and /or gas production facilities and to maintain
consistency throughout execution of the project.
3 DEFINITIONS
Company : ANOH Gas Processing Company (AGPC)
Contractor : Global Process Systems LLC
Project : ANOH Gas Plant Project (AGPP)
Vendor / Supplier : Firm or Company to whom purchase order is issued to
Manufacturer : Supply the Goods
4 ABBREVIATIONS
TOS : Top of steel
API : American Petroleum Institute
ASME : American society of Mechanical Engineers
NPS : Nominal Pipe size
P&ID : Piping and Instrumentation Diagram
ISO : International Organization for Standardization
GRE : Glass Reinforced Epoxy
5 REFERENCE DOCUMENTS
The following sub sections provides the list of codes and standards, which relate to the piping
systems. The latest edition as of 1st Jun-2019 including addenda and supplements of the
applicable piping codes and standards are to be considered at the time of contract award as part
of this specification.
5.3 Exclusions
· All instrument control piping downstream of the last piping block valve
· Sanitary piping systems
· Gas Transmission & Distribution Piping Systems (ASME B31.8)
· Pipeline Transportation Systems for Liquids and Slurries (ASME B31.4)
· Glass Reinforced Epoxy piping (GRE)
6.2 General
The design of all systems shall be in accordance with the Codes, standards and specifications listed
in section 5.
Onsite design conditions shall be in accordance with the ASME B31.3 except where the
requirements of this specification are more stringent.
The separation distances between critical facilities are based on the below considerations: -
· Safety of personnel
· Protection of Environment
· Minimization of consequences from fire, explosion, toxic pressure
The layout shall be basis for the implementation of the loss prevention philosophy which shall
address the following:
· Land available for facilities as shown in the Company’s drawing as part of the data issued by
company
· Prevailing wind direction
· Escape, evacuation and abandonment
· Operation and maintenance access
· The relative location of equipment / modules in order to meet process system and
· Operational requirements.
· Location and impact of non-process facilities (like Accommodation, Substation
· building, control room etc.)
· Expandability
· Pipe run optimization
· Underground system network
· Handling and laydown areas
· TIE IN Interfaces
· Modularization of process facilities and utilities considering location of roads and approach
· of modules from harbor / road.
· The Module size is based on the limitations mitigated by the transportation regulations of
· the country of origin (plant location).
· Drainage facilities of storm and rain water.
· Future requirements
Separation distance between modules and utilities has been maintained to aid containment of
hazard and avoid cascade effects.
Adequate separation distances between sections of a unit are estimated considering the probable
maintenance and access needs and the effect of such activities on adjacent equipment.
GAP guidelines GAP 2.5.2 – regarding safety distances criteria is used as basis to develop the plot
plan.Facility has been graded as INTERMEDIATE HAZARD(Reference GAP 2.5.2.A) based on the
type of inventories, equipment types, activities to be performed and associated hazard potential.
· Tools, valves, Instruments and control devices, including emergency control devices shall be
accessible.
· Provision for cleaning, maintenance and repair shall be taken into consideration.
· Potential source of hazard (release of hydrocarbons) e.g., flange joints, shall be located inside
hazardous areas.
6.7.1 Selection
Selection of piping components, branch reinforcement and materials of construction for individual
piping systems shall confirm to project” Piping Material Specification Doc. AGP-GPS-ANOGP-Z21-
0010”.
Generally, onsite piping shall be run overhead within the plant / compound limits.
Piping and structures shall be arranged to allow operation, inspection, maintenance and
dismantling of equipment. There shall be enough access to allow mobile lifting devices to approach
process equipment and make lifts without obstruction and with a minimal removal of pipe work.
Piping and pipe support shall be kept clear of fired heater tube and exchanger bundle removal
areas.
Piping routed at ground level shall not be located above manholes or drain trenches, nor
supported from grade above buried lines and cables. Attention shall also be given during routing
to avoid tripping and overhead hazards.
Piping system shall be adequately flexible and wherever possible this should be achieved by the
natural flexibility of the pipe work configuration. If necessary, the route of the piping should be
modified, or expansion loops incorporated to obtain enough flexibility to reduce the stress range
to acceptable limits as permitted by design codes.
Flanged connections must be provided within the vicinity of equipment to permit dismantling of
lines where removal of equipment is necessary for maintenance and inspection. Specific additional
flanged connections may be required to allow chemical cleaning or pigging of lines.
Adequate spacing shall be provided for installation of bolts and nuts. Additional care needs to be
taken where hydraulic bolt tensioning device will be applied.
All piping shall be arranged in a manner to avoid / minimize gas and liquid pockets except where
required by process. Branch connections for Gas lines shall be taken from the top of the parent
pipe and branch connections for liquid lines shall be taken from the bottom of the parent pipe.
All piping shall be arranged to provide specified headroom and clearances for technical safety,
easy operation, Inspection, maintenance and dismantling. Attention shall be addressed to
clearances required for the removal of pump and fan drivers, exchanger bundles, compressors.
Access and clearance around heaters shall be enough to allow for easy maintenance and operation
of burners, soot blowers, air filters, fans etc.
Piping shall be kept clear of manholes, access openings, inspection points, hatches, davits,
overhead cranes, runway beams, clearance areas for instrument removal, tower dropout areas,
access ways and emergency escape routes.
Pipes, fittings, valve controls, access panels or other equipment shall not extend in to access /
egress routes.
Piping should be arranged on horizontal racks at specific elevations. When changing direction
(from longitudinal to transverse or vice versa) the piping should change elevation, but care shall
be taken to avoid creating zones of vapor traps within piping.
Wherever possible the following lines shall be located at or near to the pipe rack edge:
Consideration shall be given to placing flare headers on the outboard side of the pipe racks. For
Multi-tier racks, the Process service shall be laid below the Utility service and Steam service and
the rack shall be designed to accommodate all piping system together with Instrument and
electrical cable trays, Space for future expansion shall be provided where specifically agreed by
client.
Interposed between expansion loop groups, anchor bays should be located. These bays will have
additional bracing which will have to be avoided by piping entering or exiting the rack.
In deciding the levels at which piping will run the lowest level for piping in the unit area will
determine the base from which subsequent levels will be calculated. The alternate levels running
east-west and north-south with the distance between the alternates being determined by the
minimum distance that the largest line requires to roll through a combination of 45°and 90° elbows
to exit the rack.
In general, adequate space shall be provided to support instrument & electrical cable racking and
electrical lighting conduits from the pipe rack structure.
Wherever possible the pipe rack design shall incorporate a vertical section to include the battery
limit valving. This arrangement will allow safe permanent access for spading,
pressure/temperature measurement and depressurizing of the system, as an exception, the flare
header can be routed with a nominal slope through and over the battery limit area.
When expansion loops are required, line should be grouped together and located on the outside
of the rack.
Where header block valves are required, and there is no suitable access platform in the vicinity,
the valve shall be located in the branch line immediately outboard of the pipe rack edge. The
location should allow safe access from temporary ladders, staging etc., without the need to enter
the pipe rack structure.
The pipe rack shall be constructed as modules with hook up spool between the two modules or
without hook up spools, based on the requirements as identified during detail design.
The use of flanges in piping transporting corrosive fluids in pipe racks shall be avoided wherever
possible.
Flanges and valves shall not be located on pipe racks at road crossing.
Vertical down comers alongside of pipe racks and other structures shall have a minimum clearance
of 300mm between the back of pipe and face of structure.
The foundation / pedestal for the pipe rack modules shall be based on the Civil and structural
design basis.
The minimum size of pipe running longitudinally on the pipe rack shall be NPS 2” except for
chemical injection lines.
Where double pipe banks are required, steel columns and supports built up from concrete piers
or sleepers shall be used, as a minimum, adequate clearance between the two banks shall be
provided.
Where piping at grade is required to cross road, it shall pass through a buried pipe sleeve with a
minimum cover height of 450mm.When bunch of pipes are required to crossroad they shall pass
through pipe trenches.
Buried metallic piping shall be suitably protected for corrosion with coating. The most common
method used is coating and wrapping by PE tape. The coating shall extend till the interface of AG.
Flanged joint shall be provided near the location of underground to above ground transition,
where the buried line is provided with cathodic protection, the flange joint shall have insulation
gasket.
Valves on buried lines shall be installed in valve pits. These valves shall be operated by one of the
following ways.
· Providing extended spindles (loose or permanent) so that the operation can be done from
the ground.
· Providing access /operating space to enter the pit and operating from inside.
Proper sealing shall be provided where pipes enter underground pits through openings in the pit
walls. In case of pipe flexibility is required at the openings, then adequate measures, such as
provision of flexible sealing material or expansion joints, shall be taken to allow necessary
movements.
Insulated lines shall not be buried. These shall be routed in concrete trenches.
For buried pipes operating at 60°C or below, there shall be clear distance of at least 300mm
between the pipe and any electrical or instrument cables.
For buried pipes which have impressed current cathodic protection, there shall be clear distance
of 600 mm between the pipe and any parallel running cables.
Soil settlement and thermal expansion of the piping shall be taken into account in the design of
underground piping.
Piping shall be designed so that the complete system can be flushed and cleaned. (e.g. Dead ends
should be avoided)
Buried metallic piping shall be wrapped, coated and cathodically protected as per project
specification “Painting and Coating Specification Doc. SEP-OPE-GEN-P15-00007”.
For buried pipe systems where the emission of aromatic hydrocarbons and or/ toxic fluids is a HSE
concern, e.g. pollution of ground waters, bolted joints shall not be used. Valves in these piping
systems shall be installed in pits.
Sloping lines shall be supported using standard shoes trimmed to suit or shimmed to suit for
smaller make up dimensions.
Module size and layouts shall be developed taking into account the client requirement for
transportation, the site master plan and construction requirements to allow for flexibility in
Module movement and installation. When routing pipework within modules ensure that the
envelope dimensions used for transportation and planning are not exceeded by the addition of
pipework, ladders or access platforms.
Modularization of pipe racks and units will entail greater attention to structural bracing locations
to avoid clashes. Where pipe rack modules connect, a short pup piece is welded into each line as
a closure.
Piping shall remain connected to all static equipment’s and piping systems and nozzles shall be
designed accordingly.
Interconnecting piping between modules shall only comprise piping and elbows with flanges
incorporated only where the module break has been extended to an appropriate flanged
connection. Pipe supports on these hook-up spools shall be kept to a minimum in line with project
standards and wherever possible the module steel shall be used to gain support to negate
additional steel to grade.
Temporary pipe supports shall be minimized and tie-downs adorn/ lashings during sea transport
shall be provided if required by the stress analysis.
Cuts for module separation should be at locations where headers or piping is running
perpendicular to the module so that these piping can be installed by minimizing field welding.
Piping routing must be developed completely inside the frame of the module, no installation of
piping must be performed at site inside of the module structural frame, the use of scaffolding at
site has to be minimized.
If one skid is segregated to multiple levels due to transportation limitation, in that case line
interface from upper skid to lower skid deck shall be provided with welded or flanged joint
NA-XXXZ
6.8 Valves
Isolation valves shall preferably be accessible from ground level. However, if this is not possible,
valves shall be positioned such that access from maintenance platforms is obtained. Fire water
ring main isolation valves shall always be accessible from ground level.
Pressure relief devices (relief valves, rupture discs) shall be accessible and installed for easy
removal. Relief valves shall be installed with the stem in the vertical position. Other valves may be
tilted as long as the stem is above horizontal position.
Valves operated by a lever and fitted with locking device shall be installed horizontally with the
stem in the vertical position to avoid gravity movement of the handle bar.
Gate valves in relief and flare services shall be installed with the stem downward in case if access
is not available with the stem in vertical position.
In the event of two block valves being used as a double block and bleed arrangement, the layout
shall be designed in a manner that the valves are as close as possible to each other.
Gate valves in fouling services shall be positioned with stem oriented in horizontal. This is to
mitigate closing difficulties when bottom cavities get filled with solids / dirt’s.
Valves that are only required to isolate equipment for maintenance purpose for complete or
partial plant shut down may be accessible from portable platform or ladder.
The minimum distance between the handwheels and any obstruction shall be 100mm.
Valve stems and handles shall not be project into passage ways and become obstruction.
Grating shall be provided only inside skids where ever access is required.
Control valves operated by a local controller unit, shall be located within the visual range of the
controller to enable the operation of the valve to be observed while adjustments are made on the
controller.
When an increase in line size is required downstream, the control valve shall be located as close
to the reducer as possible. where control valves are less than in size, the reducers shall be placed
adjacent to the valve. Spools or reducers between flanged block and control valves shall be made
long enough to permit bolt removal.
Where high pressure drop conditions exist across control valves, sonic harmonics together with
extreme noise levels can be expected, piping subjected to these conditions must be carefully
evaluated and designed to ensure that its size and configuration downstream of the valve prevents
transmission of excessive vibration and noise.
Supports at control valves shall be such that assembly is self-supporting when the valve is
removed.
Control valve and their actuator shall have sufficient clearance (refer recommendation of vendor)
to permit their removal for maintenance.
Relief valve discharge lines and blow down valve lines shall be self-draining into flare header, or
direct to atmosphere at a safe location if permitted. Inlet leads shall drain back to source
When relief valves discharge to atmosphere, the elevation at the top of the discharge line shall
typically be 3M above all adjacent equipment and platforms. This is to keep adjacent equipment
outside plume area.
Relief/ Blow down valve discharging to flare system shall be installed so as to prevent liquid being
trapped on the outlet side of the valve. All relief lines and headers shall be designed to eliminate
pockets.
Relief / blow down valve headers shall slope towards the knock out drum, taking into account
anticipated ground topology. Pockets are to be avoided.
Unless specifically noted on the P&ID, all branch connections on relief and blow down systems
shall be at 90° to the pipe run a weep hole shall be drilled through the underside of the discharge
line at the lowest elevation.
Relief valves must be arranged on platforms and spaced to allow adequate access to individual
valves. To enable maintenance relief valves shall have isolating valves upstream, downstream and
on the bypass lines of the relief valve as shown on the P&ID.
Suitable pipe supporting arrangement shall be considered for pipes around relief valve to arrest
any reaction forces due to relief valve pop up.
Thermal relief valves (TSV) protected blocked-in piping or equipment shall discharge to a suitable
drain or closed blowdown system.
6.9.1 General
Vents and drains exclusively used for hydrostatic pressure testing or shut down / start up shall be
provided if those showed on the P&IDs are not sufficient / suitable. If long connections are
required e.g. due to thick insulation on main pipe, the line shall be properly supported, braced.
Drain lines shall be run to the nearest drain, avoiding walking areas. Open drains shall be located
such that discharge may be observed. Open pipe ends shall extend well into tundishes to avoid
spillage.
Hydro test vent and drains shall be plugged or flanged with a blind.Drain / vent details shall be as
per project piping design standard Doc. AGP-GPS-ANOGP-Z19-0403-001.
Hydrostatic test vents are not required for piping below 1 ½”.
Drain shall be located so that there is sufficient free space underneath to install temporary
facilities to discharge the drained liquid.
Vent and drain lines shall be as short as possible. Vent and drain connection shall be taken from
top and bottom.
Process connection available for instruments, special items and inline instrument can be used for
hydrostatic vent and drain.
Samples should be taken from a vertical pipe where possible; where this is not possible:
· For gaseous products in horizontal pipes, sample take off connections shall be installed at the
top of the pipe.
· For liquid products in horizontal pipes, sample take off connections shall be installed at the
side of the pipe.
· For Mixed phase services sample shall be taken by means of quills.
Sample take off connections shall not be located at dead ends of piping and be easily accessible
and should be at ground level. However, sample pipes shall be as short as possible as and not
longer than 8m. If a short sample take off pipe cannot be fitted, a closed loop shall be provided.
The closed loop shall be a connection to the same process stream, at different pressure. The loop
shall be provided with block valves at the connections with the process pipe.
Permanent access at grade shall be provided for manual sample points. In exceptional
circumstances platform accessible by stairs shall be provided. There should be escape routes for
personnel, where practicable. Avoid locating liquid sample points in particular above grade.
7 EQUIPMENT PIPING
7.1 General
Piping connected to equipment shall be designed, so that any forces or moments caused by
thermal expansion, dead, dynamic and operating loads shall be considered; do not exceed the
limits specified by the manufacturer. Auxiliary piping shall be neatly routed along the equipment
base plate and shall not extend across the operating floor. The piping shall not obstruct any items
which require access for operation and maintenance.
Piping configuration at equipment shall be designed and supported so that equipment can be
dismantled or removed without adding temporary supports or dismantling valves and piping other
than removing spool pieces or reducers adjacent to equipment. Clearances shall permit installing
blind flanges or reversible spades on block valves on hazardous fluids or high-pressure lines. Break
out spools shall be as short as possible. All piping connections shall be flanged or else that specified
by equipment vendor.
In the design of piping for rotating equipment provision shall be made for sufficient flexibility
without the use of flexible couplings and expansion bellows.
Where ground pipe supports are required at pumps, compressors or turbines, they shall be
supported on integral extensions of the equipment support structure and not be anchored to
equipment base plate. This requirement shall apply to resilient as well as fixed supports, guides
and anchors.
Provision shall be made for the isolation of equipment with blinds or the removal of spool pieces
for pressure testing and maintenance.
Piping shall be balanced through the use of spring supports and other supports to minimize the
load exerted on the compressor nozzles. The same is applicable for nozzle of large centrifugal
pumps.
7.2.1 Pumps
For horizontal pumps/ compressors where process, safety and layout constraint allow, pumps.
Compressors should be oriented with motor end towards the access way for ease or
maintenance/hoisting access and to reduce risks associated with potential leaks.
Pumps shall not be installed beneath equipment containing flammable or combustible fluids.
Adequate access for maintenance shall be provided around the pumps. When vertical pumps are
installed, there should not be any overhead obstruction for removable of pumps or to crane boom
to lift the pumps.
Suction lines shall be as short as possible and designed without pockets where vapor or gas can
collect. Where possible the piping shall be self-venting to the suction source. The suction line shall
be checked to ensure that the NPSH available (Net Positive Suction Head) fulfils the relevant pump
requirements, including recommended margin.
Eccentric reducers shall be used in horizontal runs. If there is a possibility for air or gas pockets,
the flat side shall be mounted up. Concentric reducers shall be used in vertical piping.
To minimize the unbalancing effect of liquid flow entering double suction centrifugal pumps,
vertical elbows are preferred adjacent to suction flanges. If the requirement cannot be met, the
elbows in piping shall be at least 5 pipe diameters upstream of the pump suction flanges with the
following qualifications:
Where no reducer is employed between the pump flange and the elbow, a straight run at least 5
pipe diameters long shall be provided.
Valves in pump discharge lines shall be located as close to the pump nozzles as possible.
All valves adjacent to pumps shall be accessible for hand operation without use of chains or
extension stems. Hand wheels and stems shall not interfere with the operational passageways or
the removal of pumps.
Suction piping shall be designed to enable strainers to be easily installed or removed without
springing the pipe. The strainer body shall be equipped with drain connection where applicable;
pumps are to comply with API 610 allowable loads unless vendor allowable nozzle loads have been
submitted. The pump nozzle loads shall be qualified at operating temperatures as per API 610.
It is recommended that the pipe support immediately near the horizontal suction nozzle to be
adjustable support, when pumps are located in offskid. Adjustuble supports will not be used if
pumps are located inside the skid.
Check valves in discharge line shall be preferably be in the horizontal position and upstream of
block valve.
The length of the straight pipe from the last elbow to the suction nozzle shall be sufficient to
ensure minimum turbulence at the pump suction. The minimum length, which shall not include
any reducer, strainer, or stop-flow valve, shall be as stated below:
* For vertical close coupled pumps with 1.5 D straight length, eccentric reducers (bottom flat) are
preferred.
** It shall be studied how unequal flow to the impeller eye can best be avoided. The advice of the
pump Manufacturer should be sought in this respect.
Valves and instrumentation shall be arranged for startup and shut down convenience
In order to prevent transmission of vibrations to a compressor house, compressor piping shall not
be supported or connected to the building structure.
In order to avoid a fire hazard, lubricating oil, control oil and seal oil pipes shall not be routed in
the vicinity of hot process or hot utility pipes. Lube and seal oil consoles shall be located adjacent
to and at a minimum distance from the compressor. Oil return lines from the compressor and
driver shall have a minimum slope of 40mm per meter to the inlet connection of seal traps,
degassing tanks, and/or oil reservoir.
When locating compressors, consideration must be given to accessibility, maintenance and loss
prevention requirements.
Suction and discharge piping on bottom entry installations should preferably be run close to grade
to facilitate supporting and provide maximum possible straight run for inlet piping. Do not support
the compressor piping from the compressor foundation structure.
Heavy parts such as upper or inner casing and rotor shall be accessible to mobile/hoisting
equipment
Full platforming at operating level shall be provided to maintain and operate the compressor.
All operating valves must be readily accessible preferably from grade. Group compressor block
valves with hand wheels facing in one direction where possible.
Correct alignment is more easily achieved if adequate field fit up welds are allowed in spools
connecting to machine cases.
Avoid branch connections in headers mid-way between supports; locate them close to a support
whenever possible. Make branch connections in the top of the headers to avoid liquid carry over.
Temporary strainers must be fitted between the block valve and the inlet nozzle on all suction lines
mesh size to be as per the vendor recommendations.
The suction pipe between a knock-out drum and the compressor shall be as short as practicable,
should have no pockets and should slope down towards the knock-out drum
Suction line silencers, where required shall be located as close to the compressor suction
connection as possible according to the compressor manufacturer’s instructions.
Flow straightening devices to reduce the required straight length of compressor inlet piping, such
as vanned elbows or other piping internals may be used only with the approval of the OWNER.
If two or more compressors are combined, their suction pipes should enter at the top of the
header, except that suction pipes at least one pipe size smaller than the header may enter at the
side of the header.
Piping for steam turbines shall be designed to permit steam-blowing up to the inlet and outlet
flanges of the turbine before start-up.
Steam vents shall be routed to a safe location and shall not be combined with any lubricating oil,
seal oil or process vents
The fuel oil header shall not be “dead ended” to simplify cleaning / purging. Also, the fuel return
line shall be as per the equipment vendor requirements.
Where a positive static head is required from the day tank, the minimum operating level shall be
300mm above inlet of the injection pump.
The drain line from the day tank shall be positioned so that the drain line outlet into the main drain
is visible from the drain valve position.
7.4 Heaters
If possible, the process piping equipping a heater shall be laid out symmetrically so that the
pressure drops of the various passes are equivalent. The layout shall consider the various
operating cases (decoking operation, reduced production, starting up etc.). Also, the problems
related to the flexibility of piping and movements; the resulting forces and moments are to be
taken into consideration.
The piping must not obstruct the disassembly hatches, nor interfere with the withdrawal or
dismantling of soot sweepers and blowers and other apparatus with which the heaters are
equipped.
The adjustment valves on the fluid fed to the burners shall be placed closed to the observation
windows so that they can be operated while observing the setting of the flame.
When heaters are equipped with a steam snuffing system, the valves controlling the system shall
be grouped together behind a fire wall and preferably installed on control room side.
Space and access shall be allowed for the pulling of tubes of the heaters which will be performed
by mobile machine.
Piping at columns shall be oriented radially about this column and facing the pipe way side.
Manways shall be located on the access side and shall be kept clear of piping and instruments. The
piping shall be kept clear of man way drop out areas.
Tower piping shall be routed with adequate flexibility to accommodate tower and line growth for
the identified design conditions.
Platforms shall be provided for access to valves, instruments, blinds and man ways. Where
possible, piping shall be grouped to simplify supporting. Adequate space shall be allowed between
adjacent lines and between lines and the vessel shell to allow installation of pipe supports and
insulation where possible.
Vessel piping shall be designed in such a way that man way and platforms shall be located on the
access side.
Vertical vessels or Towers that have removable internals, packing or requiring loading or unloading
of catalyst shall have a paved dropout area located at grade directly beneath or in line with vessel
manhole or davits. The area shall have un obstructed access to roads and maintenance to access.
Platforms shall be provided at manways above 4.5 m centerline elevation from the highest point
of finished surface. Platforms shall be positioned such that the manhole centerline is not less than
750mm and not more than 1050 above the platform. Preferred height shall be 750mm.
Adjacent columns may be provided with combined platforms at common elevations whenever
possible.
If block valves shall be connected directly or close to the vessel nozzle, the valves shall be
accessible from the ground, ladder or an operating platform.
Vessel drain valves shall be located so an operator can observe the liquid level gauge while
manually adjusting the valve.
Vertical lines running down columns or vessels shall have a minimum 600mm clearance from the
outside of the shell to back of pipe.
Valves and flanges shall not be located inside the vessel skirts.
Davits for handling internals, relief valves, etc. shall be provided for vessels not accessible by
mobile crane. Davits shall be oriented to allow the lowering of appurtenances in the drop pout
areas.
Vertical nozzles adjacent to or passing through platforms shall be elevated such that face of flange
is clear of the kick plates and the flange bolt nuts below the bottom flange can be removed.
The Horizontal vessels shall be laid perpendicular to pipe rack and shall be placed minimum 3m
away from pipe rack. The clearance between adjacent horizontal vessel shall be minimum 2m or
800mm clear aisle.
The number of pipelines in the tank dyke shall be kept minimum and shall be routed in the shortest
practicable way to main pipe track outside the tank dyke, with adequate allowance for expansion.
Within one tank dyke the piping connected to that tank shall only be routed.
Manifolds shall be located outside the tank dyke & by the side of the roads, easily accessible by
the walkway.
Special consideration shall be given as regards to spacing of nozzles while installing special item
like hammer blind, MOV etc.
Design piping around tank inside dike basically as sleeper piping. For piping on a sleeper, arrange
utility piping in the middle and on both sides, arrange process piping connected on tank to the side
with corresponding tank.
Design that piping so that it does not penetrate dike as possible except pump suction pipe. Pump
suction pipe that penetrates dike should be flexible so that heavy load by thermal expansion does
not influence pump nozzle.
Pipes connected to tanks shall be sufficiently flexible to cope with thermal Expansion/contraction,
tank settlement, the outward movement of the shell and the inclination of nozzles under
hydrostatic load.
The first pipe support shall be located sufficiently far away from the tank to prevent damage to
lines and tank connections owing to settling of newly erected tanks, and the thermal expansion of
the vertical pipe leg. The distances indicated in below table may be used as a guide. If tank
settlement above an acceptable limit is expected, precautions shall be taken to cope with this
settlement (e.g. by using loops / spring hangers or expansion joints). These expansion joints should
be used only in services where the fluid properties are such that plugging of the bellows cannot
occur. They should be anchored and guided, should not be subjected to torsional loads, and should
be capable of ready inspection.
Piping shall be connected to Tank Nozzles and supported after hydrostatic testing of the tank.
There shall be access to manholes, mixing nozzles, drains and other facilities on the tanks. Small
bore utility piping required for more than one tank may be routed along an interconnecting
overhead walkway, if available.
Manways shall be oriented to provide free ventilation through the tank. Shell man ways shall be
oriented on the opposite side of the roof man ways.
· Cranes shall be able to access tanks from outside the bund wall.
· Piping around the tanks shall be routed such that there is clear access to one side of each
tank.
Tank settlement, outward movement of the shell and nozzle inclination under full liquid load
conditions shall be taken into account when calculating bending moments and forces on tank
nozzles. Piping connected to storage tank nozzles shall be provided with isolation valves.
The combined effects of settlement and tank bulge may suggest supporting the piping on springs.
The use of springs shall be limited due to the possibility of the line becoming drained and an
excessive upward load being applied to the tank nozzle.
Differential settlement at tanks is particularly important and data shall be obtained prior to the
design of piping and this shall provide the:
· Amount of settlement (and recovery) that will occur following construction and hydro test.
· Amount of settlement after hydro test and period of time over which it will occur.
Pipes passing through earthen walls shall be protected against external corrosion.
Pipes passing through concrete shall be routed through sleeves to allow for expansion of the Line.
7.9.1 General
LPG storage vessels shall be located downwind of process units, important buildings and facilities.
Bullets should not point towards other vessels, vital process equipment and control room.
Height of bullets should be such as to permit free flow of air below the vessel.
There shall be no depressions, large ditches and low-lying areas around LPG storage as the leaked
gas can accumulate, being heavier than air.
Access for mobile firefighting equipment should be provided from two sides upwind of the vessels.
Plants should be serviced by primary roads adjacent to processing units, utility plants, materials
handling and loading unloading areas. Secondary roads should be provided between process units,
utility plants and offsite area for maintenance and firefighting access.
Grading: Concrete flooring of the ground shall be provided under the vessel. The floor shall have
a slope of 1:100 (Min.) so as to direct spillage to a shallow sump away from the sphere.
The size and depth of the foundation shall be designed to limit settlement of the vessel to prevent
excessive stresses in the tank and connected piping.
Nozzles to which product transfer piping, product drains and pressure relief systems are connected
shall be at least DN 50 (NPS 2).
Flanges in piping under vessels shall be avoided for safety reasons (flame impingement in the event
of fire).
7.9.3 Piping
Only piping directly associated with the storage vessels shall be located within the storage area.
Product pipes in the storage area shall be as short as possible, preferably above ground and, where
appropriate, protected against collision/impact. The number of connections to the storage vessel
should be minimized.
The routing of piping shall be designed to minimize pipe contents and thereby reduce the potential
hazard.
Process piping shall be not less than DN 50 (NPS 2). Threaded connections shall not be used.
Pipes shall be adequately supported, and provisions shall be made for expansion, contraction and
vibration.
Freeze protection shall be considered for all drain lines and potential water collection points.
Abnormal operating conditions, such as might occur during abnormally cold weather, should be
considered where water might collect and freeze protection is needed.
When a storage facility handles more than one type of product, dedicated loading and unloading
lines between tanks and racks shall be considered for each type of product.
Valves shall not be located directly on top of channel nozzles, to avoid obstructing the removal of
channel ends. Spool pieces shall be provided to facilitate the tube pulling and maintenance.
All piping around shell and tube exchangers should allow for bundle removal and easy
maintenance of exchanger. Sufficient space shall be kept between adjacent HEX inlet and outlet
valve manifolds.
The fixed and sliding saddle of the horizontal shell and tube heat exchanger shall be decided in
such a way that helps releasing the expansion / contraction of the connected piping.
Single shell exchangers may be grouped in pairs with the minimum maintenance access between
tube sheets, but clear access way shall be provided between adjacent pairs of heat exchangers.
Exchangers shall be located with the channel nozzle away from the pipe way to facilitate tube
bundle removal.
The tube bundle pulling, and maintenance area shall be kept free in front of the header boxes /
channels. The area shall be determined as tube length plus 1 meter.
Piping shall be arranged to permit easy removal of shell covers, channels, and tube bundles. The
piping shall be provided with removal spools and be adequately supported such that bundles can
be removed without the use of additional supports.
Piping for exchangers in parallel service shall be designed for equal pressure drop.
Special care shall be taken with Plate and frame type exchangers to minimize the loads applied to
the exchanger. Loads shall be within the applicable code or Exchanger vendor’s allowable loads.
7.10.2 Reboiler
Reboilers shall be located next to the tower they serve except fired heater type. The elevation of
reboiler shall be as given in the P&IDs. Horizontal thermosiphon exchangers are located at a
minimum elevation. Vertical thermosiphon types are usually supported by the tower and are
located away from rack so that it is accessible for maintenance. Large vertical types may require
an independent supporting structure that cannot be supported from the tower/column. Reboiler
piping shall be checked for pressure drop before finalization. For vertical reboilers adequate space
to be kept so that there should be no obstruction for bundle pulling/rodding. Suitable swinging
type davit of adequate capacity to be provided for removal/handling of the cover flange of vertical
reboiler.
For safety reasons, no flanges in hydrocarbon lines shall be located directly under the air fin
coolers.
Air coolers may be supported above pipe racks or be free standing with 3.5 m clearance from
grade.
Air fin structures are not to be used as pipe supports without approval from the vendor.
Unobstructed crane maintenance access shall be provided for removal of tube bundles.
Air cooler shall be provided with walkways / platforms to service valving, fan motors and
instruments.
On forced draft cooler, platforms to access motors shall be sized and positioned such that the
motors can be lowered onto platform and trolley to a single drop-out area. Minimum access
clearances shall be maintained alongside of the motor on at least one side.
Platforms shall be provided to access header boxes for removal of covers and plugging of tubes.
Removal spools shall be provided in the piping as require to permit lifting of tube bundles for
maintenance.
All piping to Air fin coolers shall be sufficiently flexible to accommodate nozzle displacements;
particularly at sliding end headers. Piping shall be appropriately supported to meet vendor nozzle
loads. For all multi bundle air fin coolers, inlet lines shall be closed coupled (minimum piping).
Outlet lines shall be close coupled where the air fin cooler has a split header box arrangement. For
non-split header boxes (ie. inlet and outlet header is one fabrication), the piping shall be designed
with sufficient flexibility to meet vendor allowable nozzle loads. The header piping will be solid
supported.
Air fin cooler piping design shall be conformed as acceptable in accordance with stress analysis
procedures. Allowable nozzle stresses used in calculations shall be agreed with the air fin cooler
vendor prior to calculations.
Air piping shall have self-draining provision at all low points for the collection of condensates.
Instrument air headers and manifolds shall not be dead ended but supplied with blind flanges for
cleaning and maintenance.
Instrument connection shall be oriented so that instrumentation does not obstruct aisles, ladders
or platforms, whilst still being accessible.
Those Dial type Instruments with local reading shall be oriented for easy reading and monitoring
from a safe accessible location from grade, platform, ladder.
Level instrument and their isolation valves, vent/drain valves shall be accessible either from grade,
platform or ladders. Minimum 800mm clearance below the orifice tapings required for liquid
service.
Level gauge glasses at vessels shall be visible wherever possible from the valve which controls the
level in the vessel.
Orifices shall be installed in horizontal lines wherever possible. If installed in vertical lines, flow
shall be upward for liquids and downward for gases.
When determining the elevation of flow orifice, it shall be noted that for gas service, the
transmitter shall be located above the orifice taps and for liquid service it shall be below the taps.
Flow meters except Rota meters should be located in the horizontal line. Permanent access not
required if orifice plates are located no more than 4.0 m vertically above grade level or 2.5m above
a permanent platform.
Sufficient upstream and downstream straight length pipe shall be provided for the flow meter
piping as per vendor recommendation.
The requirement of air volume bottles for control valves and shut down valves shall be identified
and shall be suitably located near the instrument.
The minimum pipe size for thermo well installation is NPS 4” except where installation is in a NPS
3” elbow or tee at a change of direction. Piping smaller than NPS 4” shall be locally swaged up to
NPS 4”.
Location, orientation and accessibility of thermo wells shall take account of withdrawal space
required for the instrument.
Different types of couplings shall be used for different Utility services, but quick release connect
coupling for all utility line are more advisable to use, for easy engagement / dis engagement.
Utility air piping for the utility stations should be branched from the top of the headers and utility
water shall be branched from the bottom of the pipe header.
Where utility hose stations are specified they should be located so that all points of use in the area
can be reached by 15m long hoses. Each type of utility medium shall be provided with a dedicated
type of hose with quick coupling type connection to prevent contamination and inadvertent
connection to the wrong utility medium.
The permanent ends of quick coupling connectors shall be oriented downward direction to
prevent accidental injury to operating personnel. It shall be supported adequately to absorb the
forces during the connection and disconnection of hoses.”.
When relief valves discharge to safe location, the elevation at the top of the discharge line shall
be minimum 3m above all adjacent equipment and platforms. This is to keep adjacent equipment
outside plume area. A weep hole shall be drilled through the underside of the discharge line at the
lowest elevation.
Relief valves discharging to a flare system shall be sloped towards header and relief valve inlet to
be sloped towards the protecting equipment so as to prevent liquid being trapped on the outlet
side of the valve. All relief lines and headers shall be designed to eliminate pockets, but if a relief
valve is located at a lower elevation than the header, an automatically operated drain valve shall
be installed at the valve outlet and piped to a collecting vessel or closed drain.
Relief valve headers shall slope towards the knock-out drum, taking into account anticipated
ground topology. Pockets are to be avoided, but where a pocket is unavoidable, some approved
means of continuous draining for the header shall be incorporated.
Relief valves must be on board of platform and adequately spaced so as to allow access to
individual valves. To enable maintenance of relief valve isolation valves shall be provided on
upstream, downstream and on the bypass lines of relief valve.
· The firewater ring main shall be typically underground piping systems meeting the maximum
fire water demand;
· The fire water ring main shall be externally coated as per “Specification for coating and
wrapping”. Piping shall be designed considering the severe stress during start-up and
shutdown of fire pumps, hose streams, deluge assembly-valves and hydrants etc.;
· Fire water mains shall not be installed passing under the buildings and heavy structures. No
new structures shall be made over the fire water ring mains.
· Where firewater mains may be extended in the future, blinded flange should be provided for
future connections;
· Hydrants shall be readily accessible from roads and located in such a way that possible
damage by traffic/any other type of mechanical impact shall be minimized. They shall be
provided with a crash barrier. The location shall not be within 2.0 m from curb of the road
and at least 10.0 m from road crossings, sharp road curves, buildings or other structure as
pipe rack etc. For process areas, the distance to the nearest hydrant shall not exceed 30.0 m.
Each hydrant shall be provided with a hard-paved grade.
7.12 Fittings
7.12.1 General
All piping fittings shall conform to the relevant code or standards listed in clause 5.
Branch connections shall conform to the requirements of” Piping Material Specification Doc. AGP-
GPS-ANOGP-Z21-0010”
Expansion bellows and flexible couplings shall not be used. If required client approval to be
obtained.
Where line clean out facilities is required on headers, a blind flange shall be provided to close the
end. Where no clean out is required and no future extension is expected, the line shall be closed
with a welded cap.
Adequate space for swinging a spectacle blind, reinstalling and removing the blinds shall be
considered. Jackscrews shall be provided for spectacle blinds and their accessibility and
maintenance shall be considered (if needed, a special device such as lifting lugs should be
considered to allow for the installation of chain block and ratchet for example where maintenance
by mobile equipment is impractical).
Spectacle blinds shall not be used for Low Temperature Service, blind and spacer shall only be
used.
Spectacle blinds and spades shall be located so that they are accessible from ground level or from
platforms or walkways. The need for scaffolding shall be minimized.
For easier handling, spading points should not be installed in vertical piping; if this is unavoidable,
special precautions shall be taken to improve access and handling
Turning a spectacle blind requires all bolts except two to be, removed and a small opening to be
made between the flanges. A relatively large force is required to turn a large spectacle blind. A
spectacle blind cannot easily be turned using a crane or a hoisting device, and therefore the need
for cranes and hoisting facilities shall be avoided.
7.12.4 Strainers
The P&ID’s will indicate whether a permanent or a temporary strainer shall be used to protect
equipment. The mesh size of the strainer shall be as per the pump / equipment manufacturer
recommendation. Easy removal and cleaning of filters shall be possible.
The strainer housing shall conform to the appropriate material classification for the service in
which it is installed. The housing of permanent strainers shall have either flanged ends or butt-
weld ends.
Butt-weld ends are preferred due to weight saving, especially for the larger sizes. The installation
of permanent strainers shall permit cleaning without dismantling the strainer housing or piping.
Break out spool to be installed in conjunction with temporary strainers. The strainer itself having
body drain and vent point.
All new corrosion monitoring access fitting shall be installed at the 12'o / 6 ‘0 clock position in the
pipelines and the network piping as per the process requiements.
Requires 2500 (8-ft) clearance in a direct line along the axis of the access fitting from the bottom
of the pipe and adequate room for man oeuvre on at least on one side of a pipe should be allowed.
In Chemical injection, the TEE should be as short as practicable, but length should not be less than
100mm.
The tee pipe of the chemical injection access fittings should be oriented along the length of the
pipe to avoid accidental mechanical damages.
The space to install and remove retriever shall be considered in the layout which shall be 2.5 m
measured from the surface of the pipe. Refer “Piping Design Standard Doc. AGP-GPS-ANOGP-Z19-
0403-001”.
Wherever possible expansion loops installed in a horizontal plane, shall offset vertical to clear
adjacent piping.
The stress analysis of the lines shall be carried out and all piping shall be adequately supported
(Anchors, Guides, Limit stops etc.) to prevent excessive stress from expansion, weight, wind or
other mechanical loadings.
Lines subjected to blow down, surge and or impulse loadings shall be identified by process
engineer and the layout & supports shall be designed to avoid high loadings and vibrations.
All piping systems shall be designed so that the loads and moments applied at the flanges of the
equipment such as pumps, compressors, air coolers and vessels shall not exceed the permissible
reactions for the equipment as specified by the manufacturers of the equipment.
The location of fixed and sliding end for horizontal vessels and heat exchangers shall be
determined by piping flexibility with the sliding end away pipe rack as preferred arrangement.
Cold pull shall not be used to reduce loads on pumps, compressors, air coolers and other
machinery.
The software package Caesar II shall be used for the computer analysis of piping systems. The
analysis shall be documented in the form of reports and issued as a part of project documentation.
Stress analysis shall be done in accordance with Piping Stress Analysis Design Basis.
Piping at equipment which may require to be removed for periodic maintenance, shall be designed
so that equipment and associated valves can be readily removed without the necessity of
temporary supports.
7.15 Hoses
If hoses are used it shall be documented that they are suitable for the medium required pressure
and temperature. Hoses with associated couplings shall be marked in accordance with applicable
standards. Components should be designed so as to avoid being wrongly connected.
Hoses should be protected against damage from crushing/compression if their design will not
withstand such loads.
Hose connection to be designed to match the quick release couplings. All hoses and quick release
couplings are to be supplied by the same manufacturer.
7.17 Painting
Painting materials, application etc. Shall be based on recommendations of Project “Painting and
Coating Specification Doc. SEP-OPE-GEN-P15-00007”.
8 SPACE REQUIREMENTS
1. The above clearances are indicative. Actual values shall be based on maintainability studies.
2. Small pumps may be located in pairs without access between them.
3. Where valves are located between exchangers access must be increased to normal
operational access.
9 ATTACHMENTS