OBJECTIVE

Using the information provided in the case,


1. Develop a high level process map for the Akshaya Patra Foundation using Suppliers Inputs
Process Outputs and Customers (SIPOC). What insights can you draw from the high level process map?
2. Given that VK Hill kitchen needs to serve 87,045 students with 7 tonnes of cooked rice and 16,800
liters of Sambar per day, what is the total time required for cooking Sambar and rice?
3. If the food has to be delivered by 12.00 noon at the farthest school from the Vasanthapura kitchen
(which takes 4 hours to reach), what are the lower and upper specification limits for completion of the
first batch of Sambar? If the cooking starts at 5.00 am, calculate the corresponding Sigma Score
(process capability) assuming that the standard deviation of cooking Sambar is 10 minutes
4. For the upper and lower limits calculated in question 3 for Sambar cooking, calculate the optimal
start time for Sambar cooking that will maximize the Sigma score.
ANSWER
1. Supplier Input Process Output Customer

Raw food suppliers Mid-day Meal Package School students


which cooperate with Raw materials: for childrens and and childrens
PPP scheme students
- Rice
The Akshaya
Packaging and
Praya
supporting materials - Dhal and pulses
Foundation
suppliers
stakeholders
- Vegetables and
fruits
Cooking utensil dan
- Milk and milk
supporting equipments
products
suppliers
- Groceries
Gas company - Spices

Cooking utensil
Electricity company and supporting
equipments

Transportation services Gas, electricity,


company and water

Water services Packaging


company materials

Transport /
delivery vehicles
Employees
Trained
Employee
2. Cooking Rice process : 30 minutes , Can produces 0.875 ton of rice

Sambar Cooking takes 143 minutes, can produce 8400 litres, if 16800 means need 143x2=286
minutes or 4.8 hours, so total cooking time = Rice cooking + sambar cooking = 0.5 hours + 4.8 hours
= 5.3 hours or 318 minutes

3. Lower limit means Delivery come in time (12.00) to most farest school = 4 hours or 240 minutes,
Uper Limit means time that need to keep food 60 degree celcius = 6 hours or 360 minutes ,
If σ = 10 minutes, Cp (process capability)?
(𝑈𝑆𝐿−𝐿𝑆𝐿)
Cp= 6𝜎
360−240
Cp=
60

=120/60 = 2

4. To find optimal time we need happen when Cp min=Cp max


USL-X/3σ = X-LSL/3σ
X = (LSL + USL)/2
= (360+240)/2
= 300 minutes for process average or 5 hours

Must keep 60 degree before noon 12.00 is 6 hours, means must finish cook at 6 am.
So optimal start time to cook is 6 am – 5 hours = 1 am