Digital Project Management Platform including 5D-BIM, ERP, GIS Systems for Mumbai Pune

Expressway (MPEW) Missing Link project in the state of Maharashtra


Sr. Queries from Afcons Response from Bentley Response from Ceinsys Tech Ltd
No.
1 What would be CDE Client Yes
(Common Data
Environment) from this MSRDC is hosting CDE (Common
project? It will be hosted Data Environment)
by LB / Client?
2 Does Consultant scope Yes. Yes.
include modeling BIM Process is BS1192-
guidelines? They will 2007+A2:2016. EPC contractor and
have to adhere to the BEP AE will responsible
provided by us?
3 Asset tagging Assets are already identified. It
Yes. This will be discussed and
information is required needs to be further discussed
finalised in consultation with
by the client. By when we with MSRDC in AIMS workshop
MSRDC during workshop and
will receive the Asset and concluded.
concluded.
tagging register?
4 By when we will receive Same as Point No. 3 above
We will discuss during workshop
the Asset data
and conclude
dictionary?
5 Apart from tagging Meta data required for non-
register what other geometric is identified. It will be Meta data required for non-
information (any kind of discussed and finalized in geometric is identified. It will be
non-geometric info) is workshop as mentioned discussed and finalized in
expected for asset in Point No. 3 above workshop as mentioned above.
management?
6 Is material data to be Out of scope for Bentley for this We will discuss during workshop
incorporated in models project and cannot comment. and conclude
for asset management? If
yes, we need a material
master for the same.
7 Is Asset information to be Out of scope for Bentley for this We will discuss during workshop
linked with any FM project and cannot comment. and conclude
monitoring solution? If
yes, formats are to be
shared with us.
8 Quantification templates Out of scope for Bentley for this Not yet. This will be decided as
are defined? project and cannot comment. required
9 What kind of simulations Out of scope for Bentley for this Construction Simulation and
studies are expected project and cannot comment. Project Planning simulation
from models?
What shall be the Out of scope for Bentley for this Weekly model review is proposed
10 frequency of the Model project and cannot comment. in addition to model review session
review? required for MSRDC authority
11 For the creation of the Out of scope for Bentley for this The BIM model will be developed
As-built model what level project and cannot comment. for LOD 350, further information
of information shall be requirement for as built model will
shared? By whom? be decided in consultation with
Frequency? Formats? MSRDC
12 Site data capture Out of scope for Bentley for this Site data Captured is required.
(photographs) for project and cannot comment. Mechnisum wil be discuseed in
monitoring progress. Is it workshop
acknowledged?
13 Who will be checking Out of scope for Bentley for this Model checking is to be carried out
models with “technical project and cannot comment. by the BIM DDC with Authority
intent” Is it sign-off Engineer EPC for incorporation of
required? all required engineering details,
and to there satisfaction. Sing-Off
mechanisum can be descried at
EPC contractor level