Professional Documents
Culture Documents
The standpipe pressure schedule can therefore be corrected for the adjusted
circulating pressures.
As the drill pipe is displaced with kill weight mud, the standpipe circulating
pressure should be stepped down according to the standpipe pressure schedule.
Once the drill pipe has been displaced with kill weight mud, the final
circulating pressure is held on the drill pipe by manipulating the choke. As kill
weight mud is circulated up the annulus, the drill pipe pressure will tend to
increase. The choke should be adjusted to ensure that the drill pipe pressure is
maintained at the final circulating pressure, thereby ensuring constant bottom
hole pressure.
When the returned mud is at kill weight, the pump should be stopped and the
well shut-in and checked for pressure. A flow check should be carried out
before the rams are opened. If this flow check indicates no flow, the rams
should be opened and a further flow check k performed.
Furthermore, a complete hole circulation should be carried out prior to
continuing operations. A suitable overbalance can be added to the mud at this
stage.
Page 206
11. Well Kill Techniques
If the pipe is a considerable distance off bottom, out of the hole, or stuck
off bottom.
If the bit is plugged.
If the pipe has been dropped.
There are three techniques that may be required to deal with an influx that is
migrating up the hole. These are as follows:
1. Static Volumetric Control: One form of static volumetric control requires
using the drill pipe pressure to monitor bottom hole pressure, and is useful
when the drill pipe is on or near bottom.
2. Static Volumetric Control: A second form is useful when the drill pipe
cannot be used to measure bottom hole pressure.
3. Lubrication: This technique is
useful when the influx has migrated
to the stack, the influx is replaced
with mud as the influx is bled at the
choke.
The following sections may be used as
guidelines for the implementation of the
above-mentioned procedures.
Page 207
11. Well Kill Techniques
4. Allow drill pipe pressure to build by overbalance margin. The drill pipe
pressure should be allowed to build by a suitable overbalance margin. This
margin will be registered on the drill pipe as an increase in pressure over
and above the final shut-in pressure. The overbalance margin may typically
be in the range of 4 to 14 bar.
Page 208
11. Well Kill Techniques
Page 209
11. Well Kill Techniques
The principle of this procedure is that the bottom hole pressure is maintained
slightly over kick zone pressure by bleeding mud from the annulus to allow the
influx to expand as it migrates up the hole. Mud is bled in increments from the
well as the choke pressure rises due to migration. The volume of mud bled off
for each increment is determined from the increase in choke pressure and the
hydrostatic pressure that volume of mud represents in the wellbore.
For example, if the choke pressure increases by 100 psi (7 bar), a volume of
mud equivalent to a hydrostatic pressure in the annulus of 100 psi (7 bar) is
bled at the choke at a constant choke pressure. In this manner, control over the
bottom hole pressure is achieved. It should be noted that this method is only
applicable if the influx is migrating as the mud is bled from the well. The rate
of influx migration determines the time required to bleed each increment of
mud from the well. This technique is illustrated by Example 11.5.
Example 11.5
In this example, the following conditions apply:
Operating margin = 150 psi (10.3 bar)
Annulus = 8 1/2-in × 5-in.
Mud weight = 15.4 lb / gal (1.85 specific gravity)
Hydrostatic equivalent of mud = (1.85*0.098) / [(8.52-52) / 1973.5] = 7.56
bar/m3
Bleed (10.3 / 7.56) = 1.36 m3 of mud
Page 210
11. Well Kill Techniques
WELL NO. 26 RIG 10 DATE AND TIME 01-Oct-1999 09:36 SHEET NO, 1
HYDROSTATIC PRESSURE PER m3 OF 1.85 S.G. MUD IN 5" X 8-1/2" ANNULUS7.56 BAR/m3
19 00 45 0 0 0 0 16
19 15 INFLUX 59 + 14 0 + 14 0 16
MIGRATING
19 25 INFLUX 69 + 10 0 + 24 0 16
MIGRATING
01 35
01 3 INFLUX 79 + 10 0 + 24 0 17.36
5 MIGRATING
03
15
03 INFLUX 90 + 10 0 + 24 0 18.7
30 MIGRATING
04
45
Page 211
11. Well Kill Techniques
5 30
Page 212
11. Well Kill Techniques
MUD
GAS
Volume of
Pressure influx 10 bbl
Volume of
in bubble (1.6 cubic meter)
influx 10 bbl
Height 10,000 psi
(1.6 cubic meter)
of influx 66 m depth 11.860 ft (670 bar) 76 m
(3615 m)
BHP = Pa = 10,000 psi ( 690 bar) BHP = 10,200 psi (703 bar)
T = 15 min (assuming migration
T=0
rate of 300 m/hr)
3. Increase in surface pressure 4. 8.5 bbl (1.4 cubic meter) bled off whilst holding
for operating margin choke pressure constant
650 psi/Pa 650 psi/Pa
(69 bar) (69 bar)
Volume of
Pressure influx 18.5 bbl
Pressure in bubble (2.9 cubic meter)
in bubble now 5405 psi
Volume of
10,000 psi (373 bar)
influx 10 bbl
(670 bar) (1.6 cubic meter) 1824 m
133 m
BHP = 10,350 psi (714 bar) BHP = 10,200 psi (703 bar)
T = 25 min T = 6 hours
Page 213
11. Well Kill Techniques
As can be seen from Figure 11-7, the distance the influx must migrate (1824
m – 133 m) is 1691 m while the 1.36 m3 of mud is bled from the well. It is
clear that this operation will take several hours.
If the operating margin were quickly bled from the well, the original influx
would expand by approximately 0.06 m3 before the bottom hole pressure
dropped to the original kick zone pressure. If the remaining 1.3 m3 were bled
from the well, this would cause a further influx of 1.29 m3, as shown in Figure
11-8 below.
3a. Bleed mud from well 4a. 8.5 bbl bled off instantaneously
instantaneously well shut-in
Pa drops below Pa > 1000 psi
1000 psi (69 bar) (69 bar)
MUD
GAS
Volume of
influx 10.4 bbl
(1.65 cubic meter)
Volume of
influx 10.4 bbl
(1.65 cubic meter)
BHP drops
BHP = 10,000 psi below BHP = 10,000 psi
(690 bar) 10,000 psi (690 bar)
T = 25 min (690 bar) T = 6 hours
Page 214
11. Well Kill Techniques
7. Allow the choke pressure to build by the overbalance margin. The choke
pressure should be allowed to build by an overbalance margin that may
typically be in the range of 4 to 14 bar.
8. The total margin will depend on the resultant wellbore pressures at each
stage in the operation.
9. Bleed an increment of mud from the well at constant choke pressure. A
suitable volume of mud should be bled from the well to reduce the bottom
hole pressure by an amount equivalent to the operating margin. The choke
pressure must be held constant as the mud is bled from the well.
10.Continue the process until the influx migrates to the stack. Once the influx
has migrated to the stack, surface pressures should no longer rise, and
migration will cease to occur. Use the Volumetric Control Worksheet to
record all the relevant data (see Figure 11-6 above).
Page 215
11. Well Kill Techniques
11.Lubricate mud into the hole or implement the Dynamic Volumetric Method.
If this process has been implemented because the pipe was off bottom, it may
be feasible to circulate the influx out of the hole after the influx has migrated
to the bit.
See Figure 11-9 below for a typical choke pressure schedule for the Static
Volumetric Method.
170
Gas to Surface
160
150
140
130
120
Choke Pressure (bar)
110
Mud Bled @ Choke
100 (at cons tant choke
pres s ure until volum e
bled off corres ponds
90 to Operating Margine
80
70
60
50
40
30
-2 -1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Mud Volume (Cubic Meters)
Figure 11-9: Typical Choke Pressure Schedule for the Static Volumetric
Method
11.2.1.3 Lubrication
The technique known as lubrication may be used to vent the influx from below
the stack while maintaining constant bottom hole pressure. Lubrication can be
used to vent gas from the stack after implementing the Static Volumetric
Method, as well as to reduce surface pressures prior to an operation such as
stripping or bullheading.
When the influx has migrated to the stack, it is quite possible that the choke
line will become full of gas cut mud. In this situation it is impractical to
attempt to maintain control of the bottom hole pressure with the choke.
Page 216
11. Well Kill Techniques
Page 217
11. Well Kill Techniques
11.2.2 Stripping
Stripping is a technique that can be used to move the drill string through the
BOP stack when the well is under pressure. Stripping places high levels of
stress on the BOPs and the closing unit, and requires a particularly high level
of coordination within the rig crew. A contingency plan should be developed
regarding stripping procedure for all rigs. This section is intended to aid in the
design of a contingency plan. The following are proposed as the most
important considerations:
How to move the tool joint through the BOP.
Wear on BOP elements and the control unit.
The level of redundancy in the BOP and the control system.
Wellbore pressures in relation to the maximum allowable pressure for
equipment and the formation.
The monitoring of pressure and fluid volumes.
The organization and supervision of the drill crew.
Controlling increases in wellbore pressure due to surge pressure.
The condition of the drill pipe (drill pipe rubbers should be removed and
any burrs smoothed out).
The possibility of sticking the pipe.
The control of influx migration.
Manufacturers' information regarding minimum closing pressures for
annular preventers (this information should be available at the rig site).
The procedure to be adopted in the event that the surface pressure
approaches the maximum allowable as the pipe is stripped into the
influx.
See Section 12 for a decision analysis related to stripping operations.
Page 218
11. Well Kill Techniques
To avoid over pressuring the well, a volume of mud equal to the volume of
pipe and tool joints (the volume of metal plus the capacity) introduced into the
well, must be bled off.
Where possible, mud should not be bled from the well while the pipe is
stripped in. It is recommended that mud is bled from the well during each
connection. This ensures that there is a clear indication at surface of the
BHA entering the influx.
However, it is recognized that there may be situations in which it is
impractical to bleed mud from the well at connections. Such situations
include:
If the surface pressures are close to the maximum allowable prior to the
stripping operation.
If a high pressure water kick is taken. In this situation, the effective
compressibility of the fluid in the hole will be low; therefore, there may
be a very large pressure rise as pipe is stripped into the well.
If the pipe has to be stripped out of the hole. In this situation, there will
be a tendency for the volume of metal removed from the well to be
replaced by influx fluid.
In these circumstances, it may be necessary to implement the dynamic
stripping technique.
2. To compensate for influx migration
To compensate for influx migration, it is necessary to bleed mud from the
well. This is in addition to the volume of mud bled from the well when
introducing the pipe into the hole. Normally, the required volume of mud will
be very small in comparison to the volume bled off to compensate for the
introduction of pipe into the hole.
Influx migration is indicated by a gradual increase in surface pressure even
though the correct volume of mud is being bled from the well (however this
may be due to the BHA entering the influx). It is confirmed by increasing
surface pressure when the pipe is stationary. Implementing the Volumetric
Method controls influx migration.
3. To allow an increase in surface pressure as the BHA enters the influx
Page 219
11. Well Kill Techniques
When the BHA has been run into the influx, the height of the influx will be
considerably increased. This can cause a significant decrease in hydrostatic
pressure in the annulus, requiring a greater surface pressure to maintain a
constant bottom hole pressure (see Figure 11-10 below). A potential problem
arises if this condition is undetected. The choke operator may continue to
bleed mud from the well to maintain a constant surface pressure and
inadvertently cause further influx into the wellbore. It is therefore important to
accurately monitor the total volume of mud bled from the well.
It is recommended that the potential increase in surface pressure resulting from
entering the influx should be estimated before stripping into the hole.
Page 220
11. Well Kill Techniques
Page 221
11. Well Kill Techniques
annular has been closed. In order to reduce the annular closing pressure, in
this case, it will be necessary to loosen the annular, having closed another ram
to secure the well.
A better method is to loop the check valve with plumbing and a second needle
valve to adjust annular pressure at the closing unit. The check valve also
restricts gas from entering the closing unit if internal seals fail in the annular
ram.
Page 222
11. Well Kill Techniques
Page 223
11. Well Kill Techniques
volume of mud that is less than the volume of pipe introduced into the hole at
the start of the operation.
6. Reduce annular closing pressure. The BOP manufacturers recommend that
the closing pressure is reduced, prior to stripping, until a slight leakage occurs
through the BOP. This reduces the wear on the annular by lubricating the
element during stripping.
7. Strip in the hole. The pipe should be slowly lowered through the annular
while the surface pressure is
accurately monitored. The
running speed should be
reduced when a tool joint
passes through the annular.
Mud should be bled from
the well at each connection,
unless surface pressure
limitations dictate that this
should be carried out more
frequently. The pipe should
be filled with mud at suitable intervals, typically every five (5) stands. Use
original mud weight. A person should be posted at the driller's BOP control
panel at all times to be ready to shut-in the well in the event of failure of the
annular preventer.
8. Monitor surface pressure. Surface pressures and all relevant data should be
recorded on the Stripping Worksheet (see Figure 11-12 below.)
9. Strip to bottom. Kill the well. The only sure method of killing the well
will be to return the string to bottom and implement standard well kill
techniques.
Page 224
11. Well Kill Techniques
Stripping Worksheet
WELL NO. 3 RIG RIG 10 DATE AND TIME 01-Oct-99 10:45 SHEET NO 1
MUD WEIGHT IN HOLE 1.75 S.G. LUBRICATING MUD WEIGHT 1.75 S.G.
STRIPPING DATA
0.342 m3/STAND
MUD IN HOLE
Time Operation CHO Change BIT Pipe Hydrostatic Overbalan Volume of Total
KEMo in DEPT Stripp of mud bled / ce bar Mud Bled / Volume
Hr/M nitor Monitor H ed Lubricated Lubricated of Mud
in Pressu Pressure bar m3 m3
re (bar) m m
(bar) m3
Page 225
11. Well Kill Techniques
(Assume
BHA has
entered
influx)
Page 226
11. Well Kill Techniques
11 45 Bleed mud 101 -8.3 2243 243 N/A +8.3 +0.3 2.8
at 3.1
connection
+ ve - ve bled + ve + ve bled
increase overbalance
+ ve - ve
- ve lubricated - ve lubricated
decrease bled to underbalan
compensate ce
(to) pipe
Page 227
11. Well Kill Techniques
Page 228
11. Well Kill Techniques
Page 229
11. Well Kill Techniques
Page 230
11. Well Kill Techniques
Page 231
11. Well Kill Techniques
Page 232
11. Well Kill Techniques
Page 233
11. Well Kill Techniques
Page 234
11. Well Kill Techniques
choke should be used and the equipment rigged up as shown in Figure 11-19
below.
For this technique to be effective, the pump output must be considerably
greater than the rate at which the volume of pipe is introduced into the well. If
the pump output rate is too low, pressure surges will be caused at the choke as
the pipe is stripped in, and the choke pressure will fluctuate. The same is true
for stripping out of the hole, in which case the choke pressure may drop as
pipe is stripped from the well if the pump rate is too low. This may cause
further influx to occur.
The main problem associated with this technique is that migration and
entrance into the gas bubble may not easily be detected at surface. If no
allowance is made for these complications, further influx may be allowed to
occur. To avoid this, the mud tank levels should be closely monitored to
ensure that the levels rise, or drop, in direct relation to the volume of pipe that
has been stripped into, or out of, the well. If any discrepancy is noticed, the
well should be shut-in and the surface pressures verified. Influx migration
should be dealt with using the Volumetric Method.
Page 235
11. Well Kill Techniques
Page 236
11. Well Kill Techniques
5. Estimate the increase in surface pressure due to the BHA entering the
influx.
6. Allow the surface pressure to increase by the overbalance margin.
7. Line up the pump to the choke line (see Figure 11-19 above).
8. Ensure that the manual choke is fully closed. Open choke line valve(s).
9. Open the manual choke at the same time as the pump is brought up to
speed.
10.Maintain final shut-in pressure on the choke.
11.Reduce annular closing pressure.
12.Strip in the hole.
13.Monitor surface pressures and pit levels. If the choke pressure increases
significantly as the pipe is stripped into the hole, either reduce the pipe
running speed or increase the circulation rate. Use the Stripping Worksheet
to record all the relevant data. It is very important to accurately record
pressures and mud volumes while stripping.
14.Strip to bottom. Kill the well. Fill the pipe as required.
11.2.3 Bullheading
Bullheading is a technique that may be used in certain circumstances during
drilling operations to pump an influx back into the formation. This technique
may or may not result in fracturing the formation. Bullheading is, however, a
relatively common method of killing a well during workover operations. This
technique is generally used during workover operations when there is adequate
reservoir permeability.
Page 237
11. Well Kill Techniques
When a kick is taken with the pipe off bottom and it is not considered
feasible to strip back to bottom.
When an influx is taken with no pipe in the hole.
To reduce surface pressures prior to implementing further well control
operations.
Page 238
11. Well Kill Techniques
3. Slowly pump kill fluid down the tubing. Monitor pump and casing
pressure during the operation.
Example 11.6
Well Information:
Depth of formation/perforations = 10,170 ft (3100 m)
Formation pressure = 8.8 ppg (1.06 S.G.)
Formation fracture pressure = 13.8 ppg (1.66 S.G.)
Tubing = 4 1/2 in. N80
Internal capacity = 0.01521 bbl/ft (0.00793 m3/m)
Internal yield = 8,430 psi (581 bar)
Shut-in tubing pressure = 3,650 psi (252 bar)
Gas density = 0.1 psi/ft (.0.02263 bar/meter)
Page 239
11. Well Kill Techniques
Page 240
11. Well Kill Techniques
3650 PSI
(252 bar)
VALVE OPEN
VALVE CLOSED
BRINE
GAS
PACKER
Figure 11-21: Well Shut-in After Production (tubing full of gas prior to
bullheading)
Page 241
11. Well Kill Techniques
4000 PSI
(276 bar)TUBING PRESSURE
WITHIN ACCEPTABLE LIMITS
BULLHEAD
BRINE
VALVE OPEN
VALVE CLOSED
BRINE
GAS
PACKER
PERFORATIONS
Page 242
11. Well Kill Techniques
0 PSI
(0 bar)
VALVE OPEN
VALVE CLOSED
BRINE
GAS
PACKER
GAS TRAPPED
UNDER PACKER
PERFORATIONS
11.2.4 Snubbing
Snubbing is a technique used to force pipe into a shut-in well when the
upthrust due to well pressure makes it impossible to strip the pipe through the
BOP under its own weight. Snubbing is relatively common in some areas in
workover operations, usually when the well is allowed to continue flowing as
remedial work is carried out.
Snubbing may be considered during drilling operations for well control
purposes, either when it is impossible to introduce pipe into a well that is
under pressure, or if the rig BOP system is not considered adequate to provide
reliable pressure containment during a prolonged stripping operations.
Page 243