You are on page 1of 16

''q h

tt'
COSTAIN
INTERNATIONAL LIMITED
HUNTER PROJECT

SITE PROCtrDI.IRB SP / O4O

,I
E-

ORIGINAL

Issu.e status ntarked in rcd


The original of this procedurc
is held by the Q.A.M and may
be inspected upon application.
cgTJRoLLED
.dF
Fd"
COSTAIN
IN'TERNAIIONAL LIMITT,I) sP_040.Doc
IIUNTER PROJECT Rcvision : 0
Titlq Site Procedurc SP i 040 Ternporary Works Procedure Dare :30.3.95

Table of Contents

O.O RE\{ISION AND AI\{trNDMtrNT RECORI) 3

1.0 GtrNERAL 4

(-; 2.0 DESIGN OT TEMPORARY WORI{S 4

3.0 DESIGN 5

4.0 Tm TEMPORARY WOIU(S CO-ORDTNATOR C[WC) 6

5.0 PER]\{IT TO LOAD OR PROCEED 7

6.0 SIIB-CONTRACTOITS 7

7.0 QUALTTY RECORDS 8

8.0 APPENDICES I
i
'' '.a
*'
COSTAIN
lN'lllI{NATIONnLLIMITIID sp_o4o.Doc
IIUNTIII{ PROJECT '. Revision :0
. Title: Sitc Procedure SP / 040 Ternporary Works proccdure Date : 30.3.95

0.0 Revision and Arnendment Rccorcl

This document has been reviscd alrcl amenclecl as follows

Rev 0 30.3.9s First Issue

t;

t
COSTAIN
INTNRNATIONAL LIMITED sP_040.Doc
IIUNTDR PROJECT Rcvision : 0
Title: Site Procedure SP / 040 Temporary Works procetlure Date :30.3.95

1.0 General

1.1 The following defined terms, gensrally in arcordance with BS 5975, will be used:-

1.1.i Formwork: Tentporaty works used to give the required shape ancl support to poured
concrete, ie shutters.

1.1.2 Falsework: Any tenrporary structure used to support a permanent structure while it is not
self-supporting.

l.Z Other types of tenlporary work such as coffcrdarns, earthworks and acccsses are also
covered.

ti 1.3 In order to comply with tire requirenicnts of the Costain International Healttr and Safery
Procedures for the Hunter Projects, the following relevant procedures are mandatory.

2.0 Dcsign of Temporary Worlis

2.1 Every item of temporary works; eg falsework, cofferdams, access scaffold, forrnwork etc;
must be properly designed.

2.2 Drawings and/or sketches must be preparecl to enable temporary works to be constructed.
Any restraints to be applied to the loading of tenrporary works must be clearly shown on the
drawings or sketches and indicated in the calculations

2.3 Designs may be carried out iu the Project Office or by the supplier of a proprietary system.
In either of tltese qxes The Project lvlanager or Nominated Representative will write and issue a
Design Brief which will be copied to the Temporary Work Co-ordinator or his Delegated Deputy.
---/' Within the scope of the Hunter III Project the only area where tiris is expected to be required and
External designers for the ternporary work be used is scaffolding attached to the gantry cranes for
working on roof steel and M&E works at high level.

2.4 For the definition of minor tenrporary works see section 3.3.

2.5 The Design Brief will take the lbrrn shown in appendix 1. It may be amplified by
correspondence if llecessary. All pars of the proforma must be cornpletecl.

2.6 A requirernettt for an Independent Design Check may be inclucled for the scaffold in section
2.3 above. If it is not it will be assumecl that it is either not required by legislation or contract or
that other arraltgemelrs will be nrade.
'n COSTAIN
INT!,RNNTIONNL LIMN'ED
sP_040.Doc
IIUNTER PROJDCT
Revision : 0
Title: Site Procedurc SP / 040 Tenrporary Works proccdure Dare :30.3.95

3.0 Design

3.1 Chechs

3.1.1 Wren all independent Temporary Works Design Check is required by legislation or Contract
it will be done by a Chartered Engineer where possible. If a Chartered Engineeiis not available, t6e
clteck will be carried out by a suitably experieuced engineer. The degree of experience necessary
will be decided by the Projrct Managcr or Nominated Representative. lhis will be done by
reference to thc design type,conrplexity ancl any rclevant specification.

3.1.2 A Design Check ntust be INDEPENDENT of the Design as far as practicable.

3.1.3 A Checking Engineer may be from the Projrct concerned or another ProjecUOffice,but must
(
not ltave been involved with the initial design. If a suitable Checking Engineer is not available the
Chief Engineer will be consulted regarcling an external checking organisation.

3.1.4 A Design Brief will be issued in the same way as for an initial
design but must state clearly
that it is for an INDEPENDENT Design Check. Details of the checks required will be given ani
any requirernent for a Design Check Certificate stated.

3.2 Desigu Check Ccrtificates

3.2.1 A Design Check Certificate will be issued for clids done when required by a Brief. This
will either be of the Civil Engineering Division pattenl shown in upp.nOi* 2 or of a sirnilar
acceptable forrnat.

3.2.2 Copies of any Design Check Ccrtificates issued rnust be retained on Site by the Temporary
works Co-ordinator or his Delegatecl Deputy as Quality Records. Any rnodifications mactl to a
Ternporary works Design after the clcsign check has been conrpleted must be referred back to both
the designer and tire checker for approval. Modificatiolls may only be incorporated into tle
temporary works after these approvals have been received in writing. ' :

3.3 . Delurition of l\{inor Dcsigns

3.3.i All temporary works arc considerecl complcx cxcept as definecl below.
A MINOR DBSIGN is one that cloes NOT involve:-
a) Columns wltere effective lengtl is determined by lateral restraints along their lengtS
b) Shores placed olle upolt another to form support of more than one tier in height
c) Trusses exceeding 3m span
d) Members cotmected to each other, such that loacl in one nlay induce or alter the load
in another
e) Shores more than 3.0m in height
0 Support systetn to a treucli deeper than 1.2m unless a proprietary trench box system
is being used
COSTAII.{
IN'IA,RNATIONAL I-MffDD sp o4o.Doc
IIUN'IEI{ PROJIICT Revision : 0
, Title: Site Proccdure SP / 040 Temporary Works procedure Darc : 30.3.95

4,0 The Tcmporary lyorl{s Co-Orclinator (fWC)


4.L Appointrnent of the TWC

A Temporary works Co-ordinator (lWC) will be appointed for the Project. The Projrct Manager
will norninate a tnenber of Project Management in writing to act as the TWC ancl Delegated
Deputy.
Tlte TWC and his Delegated Deputy must have suitable temporary works experience.

4.2 Duties of thc TWC

The duties and responsibilities of the TWC or Delegated Deputy ale as follows:-
\-/
a) Co-ordinate all complex tetnporary works activities including those of sub-
contractors
b) Ensure that thc various responsibilities have been allocated and accepted
c) Eruure that a dcsign brief has been established with full consultation, is adequate,
and is in arcord with thc actual situation ou site
d) Ensure tllat a satisfactory temporary work design is carried out
e) Eruure that tlie design is independently checked for concept, structural adequacy
when required by BS 5975 or the Specification and cornplies with the Design Brief.
This check rnay be carried out by the TWC if suitably qualified
0 Checks will be recorded on drawings/sketches in the appropriate place and by the
issue of a Design Check Certificate if required
g) Where inslructed, ensure tltat the design is nrade available to other interested parties,
eg "The Engineer".
h) Register or record the drawings, calculatiorn ancl otier rclevant documents rclating to
the final design
D Etrure that tltose resporuible for on site supervision receive full details of the design,
including any lirnitations associated with it
j) Eruure that checks are nrade at appropriate skges covering the more critical factors
k) Emure that any proposed changes in materials or constructions are chrckecl against .t
the original design and appropriate action taken
l) Ensure that any agreed cltanges, or correction of faults, are correctly carrie<l out on
site
m) Ensure that during usc all appropriate maintenanrc is carried out
N) AF'TER FINAL PHYSICi\L CI{ECK, ISSUE FORMAL PROPOSAL I
APPROVAL (P/A) TO LOAD OI( TO PROCEED TO TFIE NEXT PHASE
o) Wren it has been confirnted that the pennanent structure has attained adequate
strength, contplete the (P/A) to load to allow loading of the permanent structure

4.3 The above points a to tr have been surnrnarisccl in thc Tenrporary works Co-ordinator Check
List (Appendix3). This will be completecl by thc TWC or his Dclegated Deputy for cach major
Temporary Works Design.
q

COSTAIN
IN'IERNATIONAL LMITEI)
sP_040.Doc
IIUNTER PROJECT
Revision : 0
Title: Site Procedure SP / 040 Temporary Works procedure Date:30.3.95

4.4 It
is recommended that the Ternporary Works Co-ordinator and his Delegated Deputy are
made aware of tlte guidelines of BS 5975. Particular attention should be paid to the sections
included in appendix 4 which are:-

BS 5975 :1982 Srctions 9, 10, 11,lZ, 13,14,43.1,50.

4.5 Authority of thc TWC or IIis Delcgated Dcputy

Tlte TWC or Delegated Deputy must be given thc authority to stop the work if he is not satisfied
with any aspect of the temporary work.

5.0 I'crruit to Load or Proccctl


(,
5.1 A Proposal/Approval (P/A) to load (Appendix 5) is valid far 24 hours. If the operation
concerned does not begin within this periocl the ternporary works must be inspected again by the
TWC or his Delegared Deputy.

5.2 A P/A to Proceed (Appendix 6) is valid until the nexr I-IOLD POINT indicarecl in the design
calculations, drawings, sketches or I&Tp is reached.

5.3 A P/A must be uncouditional. If the TWC or Delegated Depufy finds that there are faulg in
tire temporary works the PIA must ttot be issued. A P/A will only be issued when the faults have
been rectified and re-inspected by the TWC or Delegated Deputy.
An appropriate PERMIT must be issuecl by safefy officer prior to start of activities.
For repetitive work suclt as pouring of the capping bearn or ground support works such as trenches,
cofferdams etc wltere tlte issue of a 'Pertnit to [,oad' is inappropriate, the 'Permit to proceed' will
be used. The TWC or Delegated Deputy rnust ensure that the work are carried out according to
any methods and assulnptions stated in the dcsign. This will be done by regular inspection *6i.tt
may be recorded in the Diary of the Twc or his delegated cleputy.

5.4 The P/A profornta included as appendiccs to this section rvill be used on the project. All
sectionsof the form nust be complcted.

6.0 Sub-contractors

6.1 Where sub-contractors arc cniployccl who design and/or erect ternporary works, t6e duties of
the TWC or Delegated Deputy are unchanged. Tlre TWC or Delegated-Oeputy must carry
out the
duties described in Section 4.2 and, have the authority clcscribed in Section 4.3.
6.2 Costain lnternatiottal, as main Contractors, must monitor the sub-contractors' activities'to
ensure compliance with theCostain International Health and Safety Procedure for the Hunter Phase
III Project and all otirer relevant codes of practice. All sub-contractors' temporary works must be
designed, checked, erected and Perrnits issued as if under the direct control of Costain International
Limited.
a
a COSTAIN
INTERNANONAL LIMITED
IIUNTER PROJEC'I' sP_040,Doc
.. Revision : 0
Titls Site Procedure SP / 040 Tenrporary Worl<s proccdurc
Date: 30.3.95

7.4 QUALITY RECORDS


7.1 All docurnentatioll relating to thc design and co-ordination of Temporary Works are
designated Qualiry Records. They will be rnaintained in a safe
and securc way whilst the project is
in progress in accordance with Sp 160.

8.0 APPENDICtrS

8.1 Appendix 1 (1 page)

( 8.2 Appendix 2 (1 page)

8.3 Appendix 3 (1 pagc)

8.4 Appendix 4 (3 pages)

8.5 Appendix 5 (1 pagc)

8.6 Appendix 6 (1 page)


SP 040 - Appcndix 1
COSTAII{ COSTAIN INTERNATIONAL LTD.

AL YAMAMAH-HUNTER PROJECT PHASE III


TEMPORARY WORKS DESIGN BRIEF

Facilify:

Subject:

issued by: Position:

Design Brief given:

Documents provided:

Independent Design Check spccified: Yes n No tr Check formar.

Design required by (dare):

Date Brief issued: Signed:

initial conunent/guidance by Ciiief Engineer:

Chief Engineer:

Print name:
SP 040 - Appendix 2

COSTAIi{ COSTAIN INTERNATIONAL LTD.

AL YAMAMAH-HUNTER PROJECT PHASE III


CERTIFICATION OF TEMPORARY WORKS DESIGN

Certificate No:

Facility:

Subject:

Detailed checked:

, _)riginal Design by:


Checked by: Check date:

I have checked the above design detailed on docurnents:

and consider that the work can safely be


luilt to these details r,vith the foliowing provisos:
a

Signed:
?.c. Chief Engineer
Section Manager
Safefy Officer
SP 040 - Appendix 3

COSTAII\ COSTAIN INTERNATIONAL LTD.

AL YAMAMAH-HUNTER PROJECT PHASE III


TEMPORARY WORKS CO-ORDINATOR'S CHECK LIST

Design Title:

Design Reference:

Date Initials

1. All responsibilities for the scheme allocated


\-. (refer to correspondence).
2. Design Brief, Ref;- issued, is adequate
and in accordance wiflr actual site conclitions.
3. All design documents received and registered.
4. Design independently checked for concept,
structural integrity and compliance with the Brief
5. If Design Check Certificates required they are
complete and received.
5. Design Check Certificates in safe file.
Drawings marked as "Approved For Construction".
7. Documents distributed to:

8. Site supervisors are aware of Design restrictions


. Construction Method Statements procedures and
Construction Quality Plan Hold points.
9. Any modifications approved by Designer
and Checker used in the works.
i0. After final physical check appropriate approval
issued. approval No.
11. Permission to load the permanent structure given.
12. Permit No. issued by Safety Officer.
13. Ternporary Works removed.

Signed:
T.W.C
;1.c. Chief Engineer
Qa^fi^'. l,f^-^-^-
qS 5975 : 1982 : Extracts SP 040 - Appendix 4 Shcet L of 3
c
9. Comnrunication of rcquircnrcnts 1O.2 l,'alscworkcoordirrator

Falscwork dcsigns ancl schclncs should tlc courplctc with detailcd LO.2.I Whcn a construction organisation dccidcs to appoint a
proposals for thc foundations, connectiorx to othcr works and thc falscwork coordinator, hc should normally bc clirectly responsiblc
fonnwork, bcfore beiug offcrcd for use on sitc. Whcre thc to their site managcr. It is irnportaut that lds appointment gives
design bricf indicatcs that stanclard aud familiar cquipment and Irirn adcquate audrority to carry out his tasks. In ordcr to provide
matcrials can be uscd iu accordancc with stanclard dctails and adequate authority to stop work if it has not becn carricd out
instructions, it will only be ncccssary to provide infonnation to satisfactorily it may bc appropriate for thc falsework coordinator
ilrose persons on site as to the manner and exl.cnt to which ftc to be made responsible for the provision of fonnal pcrmission to
items should be uscd aud maintaincd to cnsurc safe practice. load, which whcn signed would thcreby certily that all
Thcse dircctions should bc givcn in conjunction with an appropriate stcps had bcen taken. The falsework coordirutor
arrangement drawing or sketch. Thc drawings and any rclatcd should not pcnnit crcction to continue bcyond auy critical stagc
irxtructions issued to site for the dircction of thc work rnay bc until it is to the standard specified. Once the falscwork has been
supportcd by, for cxamplc, s[andard dctails, or guitlcs to thc use chcckcd and passcd, it should not bc altcrcd uDtil that loading
of proprictary systems of falsework cquipmcnt. stagc has bcen completcd, and the dcsigu allows for it to be
dismantlcd or altcrcd. Iu dcmanding circurnsLan@s it will be
Thc drawings aud instructions rcsulting from thc clcsign slioulcl advisablc for drosc chccking critical iterns to sign whcn thc work
gcncrally bc adcquatc to dircct thc work ou sitc and to cuablc this is to thcir satisfaction. To ensurc the independcncc of checks,
to bc chcckcd. Particular carc should bc paid to cnsuring tha! thc l.hc falscwork coordinator should dclcgatc thc task to another if
infonnation supplicd is casy to undcrsl.aud, aud tJrat it draws hc himsclf has carricd out any of tbc activitics rcquiring
attention to thc nced to rcsolvc any dcLails or unusual situatious. checking. His appointrncnt should bc made known to all
'lhe positions of each componcnt aud thc naturc of its cross-
conccrncd.
'onnections to othcr components should bc showu. Drawings
,-;llould be uniqucly numbcred, clcarly idcntificd as to location for L0.2.2 Thc principal activities of thc falscwork coordinator
usc, and cross-rcfcrcnced to aily o$cr daLa with which thcy should bc to:
should bc uscd. lt is dcsirablc to adopt standard rnethods o[
noting csscntial hformation on the drawhgs and to usc suitablc, a) coordirute all falscwork activities;
easily read scalcs. To aid thc location ancl idcntification of b) cnsurc that thc various rcsponsibility havc bccn
particuiar areas, consideration should bc givcn to applying a allocated and acccpted;
system of grid rcfcrenccs to the schemc. c) cnsure tbat. a design bricf has been establ.ished with full
cousullation, is adequatc, and is in accord with the actual
Wherc construction is not straightforward, thc falscwork situation on sitc;
drawings are unlikely to sct down all thc pararnctcrs of usc. ln d) cnsure that a satisfactory falscwork dcsign is carricd out;
such cases a mcthod slatcrucnt or corutrucLion plan should bc c) ensurc that thc dcsign is indcpendcntly chcckcd for:
preparcd on sitc and madc availablc to all concenrcd. Wherc 1) concept
ihcrc arc any lirnitations in scqucncc or timilg, ilrcsc should bc 2) slructural adcquacy;
sct down explicitly as part of thc design for thc usc. 3) compliance with thc bricf;
f) where appropriatc, ensurc that the dcsign is made available
Imtructiorn should bc providccl iudicating how thc supporring to otlicr intcrcstcd partics, eg thc structural dcsigncr;
fouudations should bc prcparcd and clnplrasising thc nccd to g) rcgistcr or record thc drawings, calcula[ions and other
comparc the conditions found on thc sitc with thosc assuurcd in rclcvant documents relating to thc linal dcsign;
lhc initial dcsign for thc puqrosc of confinning thcir validity. lt) ensurc Lhat thosc rcsponsiblc for on-site supcrvision rcccive
ful[ dctails of thc dcsign, ilcluding any linitations associatcd with
_ .0. Coordination and supcrvision it;
i) cnsurc tlrat chccks arc rnadc al appropriatc stagcs covering
10.1 Gencral. Work on sitc should bc thc subjcct of carcful thc rnorc critical lactors;
direction, supcrvision and inspcc[ion [o cluure that thc falscwork j) clrsurc that any proposed changcs in matcrials or
structure is constructcd safcly in accordancc with thc agrccd corutruction are chcckcd agairxt thc origiml dcsign and
Ccsign with matcrials ol agrccd quality, ancl Lhat ouly whcn all appropriatc actions kken;
;hccks havc proved satislactory is thc s[ructurc first loadcd, and k) cnsurc thal any agrccd changes, or corrcctions of fauhs, are
ihcn disnantlcd in accordancc with an agrcccl proccrlurc. corrccl.ly carricd out ou sitc;
l) cnsurc that duriug usc all appropriatc mahtcnancc is carried
Communication tcnds to bc ouc of thc lnajor problcm arcas ol out;
ialscrvork bccausc of the rnultipricity of actions nonnally requirctr m) aftcr a luul chcck, issuc fonnal pcnni.ssiorr to loacl if this
ivhen falsework is bcing constnrctcd ancl put iuto scrvicc. Suclr chcck provcs satisfactory;
activitics may bc widcly scparatcd in tirnc and placc and it is n) whcu it has bccn confinncd that thc pennanent structure has
fcrcforc csscntial r.hat li'cs o[ conununicatio^ and rcspo'sibility attained a<lequatc strcngth, issuc fonnal pcnnission to dismantle
llre cxplicit. To facilitate progress, a mcthodical approach shoul<l thc falscwork.
cc adopted and it is rccouunendcd that cornprchcrxivc
Job notcs'
rrc maintaincd,
ils sgzs : 1982: Extracts SI' 040 - Appendix 4 Shect 2 of 3
D

11. Chccking One of the major dilfcrcnccs betweeu thc dcsign of falscwork
structurcs and pcmancnt works structures is that the falsework is
At all stagcs, qernrneucing with thc dcsign bricf, it is ncccssary to not normally hcld down to thc foundations and usually relics
check that thc information bcing uscd is corrcct and that thc work upon its own inhcrcnt stability and self-weight to remain stable
carried out is as spccificd, This is necessary, not only to olxurc througlout its lifc. Furtlennore, bccausc thc loads imposed on a
that, a safc and adcquate falscwork structurc is corutructed, but falscwork structurc arc known within closc limits, thc individual
also to facilitatc rcctification should this provc Dcccssary; it is clcmcnts of a falscwork structure arc morc likely to be strsssed to
frcqucntly difhcult to do this later. Dctails of chccking ncarcr thcir pcrmissible working strcsses than the pcnnancut
procedures arc given in 43 and clausc 50. structurc on which imposcd loadings may vary considcrably.

12. Altcrations

Changcs in thc rcquircmcntr of thc desigu brict should bc


rccordcd l,hcrcin as wcll as incorporatcd into thc dcsign and
50. Chccking falsovork
drawings (sec also 50.2). Thc cffccts of auy proposcd alteratiolu
should bc checkcd against thc origiual dcsign and appropriatc
50.1 When to chcck. Thcrc arc a numbcr o[ clcarly defined
sl.agcs in thc construction of ccrtain types of falsework when
action taken.
fonnal checks arc <lesirablc. Thcy may not be necessary for
sirnplcr arraugcmenLs, such as those describcd in section cight of
13. Loading thc lalscrvork
this codc whcn a fonnal chcck iuunediatcly prior to concrctiug
nray bc all that is rcquired.
As a mcans of cxercising a dcgrcc of control ovcr thc ral.c of
rogrcssion once thc slagc has bccn rcachcd Oat tbc falscwork
It is rccouuncndcd that thc nccd for a formal check sh<luld be
--rlray bc loa<Icd, it rnay be advisablc to havc a fonnal proccclurc
ccrnsidcrcd:
for giving pcrurission to load, as indicared in 10.2, pcrhaps in the
fonn of a 'Pcnnit to load'. ln siruplc cascs, a silglc pcnnit,
madc out as sooll as thc falscwork has bccn satislactorily
a) whcn thc proposcd founding lcvcl for thc falscwork is il
prcparation;
cltcckcd, may bc approirriatc. Iu courplcx, or largc cascs,
pcnnits may bc rcquircd at diffcrcnt stagcs, both as rcgards
b) whcn thc falscwork has atlaincd a height of 10ua or a height
cqual to 1.5 tirncs thc rninimurn of is plan dimensions;
loading aud for diffcrcut arcas. It will normally bc dcsirable to
iimit the pcriod of validity of thc pcnnit, as
c) wlien thc falscwork reachcs is support lcvcl;
subsequcut
modificatious may takc placc. Tirc area ovcr which loading may
d) at iltcmrcdiatc stagcs, whcn the strcngth or stability of the
falscrvork may havc been advcrsely affcctcd by cnvirenrnenlsl e1
nke place, and to what cxtent, should also bc sct down iu thc
othcr loading conditions or unauthorized interfcrcnce;
pcrmit, eg it may bc 'rcinforcemcut only'.
c) whcrc cquipmcnt is bcilg continually rcuscd aud periodic
chccks arc appropriatc;
L4. Disnrantling
l) irnnediately prior to loads being applicd.

Whcn the structurc bciug supportcd by thc falscwork has bccornc


Strould thc struclurc bc subjected to load redistribution due to
self-supporting, thc lattcr may be dismantlcd subjcct to a post-tensioning, a cons[ant obscrvation sliould bc maintained for
prcviously agrccd proccdurc and/or res[rictions irnposed by the
any novelncnb or sounds of distress in thc supporting falscwork.
pcrmancnt works, As at thc loading stagc, a pcnnit to disrnantle
It may in such insLanccs be ncccssary to carry out. a check beforc
or 'uuload' thc falsework rnay bc appropriate, particularly whcrc
'his takcs placc in stages. It rnay bc appropriatc to issuc it iu stressing continucs.

.=-;oujunctiou with tbc designcr ol thc pcnnancnt. structurc.


Critical factors of worlcrnanshill to which attcntion should be
givcn arc listcd in 49.1 and 50.2.

50.2 Iterns to bc chcckcd. At thc stages indicatcd in 50.1,


13. Analysis of falscrvork structurc thorough iuspcction o[ thc falsework is nccessary to cnsurc that
the complctcd stnrcturc will function as intended. Whilst the
43.1 Gcncral. Thc falscrvork solution chosen lor a following iist is not exhaustive, it will give guidance oll what to
particular strucLure nray bc subjcctcd to scvcral of thc forccs, tlrc look for iu a systcmatic manner.
magnitudc of which may vary at differcnt phascs of construction.
The irrspcctions should bc undcrlakcn with dircct rclcrcnce to
is rccormncndcd that for cach falscwork structurc thrcc tlcsign
It. any drawing or spccihcation that has been issued, and chccks
chccks be carricd out: subscqucnt to thc first should inspect cvery featurc tbat could
Iravc altcrcd in thc intcrvcning pcriocl.
a) otr thc structural strcngth of thc individual rncurbcrs and
thcir conncctions to transmit thc applicd forccs safely;
t ) on thc latcral stability of both thc indiviclual nrcrnbcrs and
Lhe structurc as a wholc;
c) on ovcrturning of thc falscwork.
Within thcsc thrcc chccks, sub.sidiary chccks rnay bc ucccssary to
catcr for thc diffcrent phascs of constructiou aud thc varying
stability aud rcslraint. conditions.
'IlF 5975 : L982 : Extracts SI' 040 - Appendix 4 Sheet 3 of 3
g

TIIII. RI'SULT OF CIIDCKS OIT INSI'I'CTIONS SIIOULT)


BII RECORDI'D IN WRITING AND ACTION T'AKI'N 'TO 5) thc numbcr and position of all bracing members
CORRECT ANY TIAULTS. (longitudinal, lateral and plan) ate correct. with
conncctiors closc to nodc points;
It should bc chcckcd that:
6) thc rcstraints arc cffcctivc whcrc falscwork is stabilised
a) General: by butting, wcdging or tying of lacilg rnernbcrs, instcad
of braci.og;
1) all thc drawings and writtcn irxtructions bavc bccn
strictly courplicd witlr; 7) forkhcads arc propcrly aligncd, aud any extcnsiou is
within ths pcrmittcd limits and braced whcrc Dcccssary;
2) only thc corrcct rnatcrials in scrviccablc coudition havc
bccn cmploycd, cspccially il spccific rypcs or qualitics 8) bcarcrs arc correctly spliced, ccntralizcd in forkheads,
were rcquircd as will normally bc the casc wiilr and if rcquircd wcdgcd and nailcd in thc fork;
structural stecl or tirnbcr;
e) bcaun, including {Ioor ccnters, havc adcqual.e scatings
b) At fouttding levcl and arc secured agairxt movclncut;

1) Lhc settilg oul. is corrcct; l0) any nccessary wcb stiffcncrs and lateral restraint have
becn provided;
2) thc ground has been adcquately prcparcd and is at a
satislactory level (foundations appcaring sound in dry 11) all pils, bols, clips and the likc, havc becn {itted, are
or frcczing conditious can bc quitc inadcquatc following of thc corrcct typc and arc sccurc:
rain or thatv);
12) scaflold couplcrs are propcrly tightcned (it will usually
3) suitablc solc platcs or othcr bascs havc bccn providcd bc sufficicnt to physically check some at random,
and havc bcen properll' lcvclcd; including the lcss acccssible regions);

4) solc platcs or othcr bascs havc not scttlcd; 13) wherc access is rcquircd by worklnen, ladders,
platforms, guardrails and toeboards are lxed and
s) solc plaLes have becn propcrly bcdded down (no conply with the rcquiremen[s of the Construction
cavitics undcrncailr), and stcps taken to prcvcDt Rcgulations (sec
erosion;

6) sole plates and othcr load-distributing mcrnbcrs laid on


thc slopc arc adequatcly prcvcntcd from moverucnt
down thc slopc;

7) any chccks or otltcr supports arc thc corrcct shapc, and


are adequatcly securcd;

,, 8) basclllatcs havc bccn uscd and arc propcrly spaccs aud


J ccutcrcd on thc solc pletcs;

9) the cxtcnsion of cach scrcw or acljustablc basc is rvithin


thc peru'ritted lirnits, and braccd if ncccssary.

c) Above touttdirtg levcl

1) ties and/or rakcrs havc bccn fittcd, lirfting all uprigtrts


in two dircctions rougirly nonnal to cach othcr, or at a
spccificd skcrv anglc;

2) Upright rncmbcrs arc plurnb (to do rlfs a fcw upright


rncmbcrs should bc chcckcd with suitablc ilstnmtcnt,s
and markcd; the rcrnaindcr can bc chcckcd by cyc);

3) joints in vcrtical mcutbcrs arc propcrly bu[cd and


aligncd, and rcinforccd if requircd;

4) thc spacing aud lcvcl of cach lift of lacing rncmbcr.s arc


corrcct;
tt SP 040 - Appendix 6

COSTAII{ COSTAIN INTERNATIONAL


LTD.

AL YAMAMAH-HUNTER PROJECT PHASE III


PROPOSAL/APPROVAL TO PROCEED
(Temporary Works) No:

Facility:
Description of works:
PART 1

Temporary Works to the section of the structure noted above are now complete in
accordance with the drawings and amendments listed below. I have carried out a
preliminary inspection and am satisfied that the Temporary Works are now ready
for work to proceed to the next HOLD POINT.

I am familiar with the design restraints that have


been imposed on the loading of the
Temporary Works and have passed these on to the Supervisor/Foreman in charge.

Signed: Time :
(Section Manager) Date :

The following drawings, schedules and their amendments refer to the Temporary
Works for this part of the structure :

PART 2
.l have inspected the Temporary Works to thc section of the structure noted ancl
..- found that they have been properly erectecl in accordance with the drawings (and
approved amendrnen[s).

Signed: Time :

VALID UNTIL NEXT HOLD POINT Date :

AUTHORISATION TO REMOVE TEMPORARY WORKS ENO IOEN TTTP


STRUCTURE
The Ternporary Works rnay be removed subject to the following restrictions and/or
sequence:

Signed: Time :
(Temporary Works Co-ordinator)
Date :
AppROpRf ATIf pnTliliff'T' l\/ff TSrn nr:r! fCSTTnT\ IIV QArlrr/rqa\,r nr;rr.lrarrlD T)T)TnD
SP 040 - Appendix 5

COSTAIi\T COSTAIN INTERNATIONAL


LTD.
AL YAMAMAH-HUNTER PROJECT PHASE III
PROPOSAL/APPROVAL TO LOAD
No:
Facility:
Description of works:
Proposed date/time of pour:

Temporary works to the section .f th:t*:,I,r. nor.o above are now cornplere in
accordance with the drawings and amendments listed below. I have carried out a
preliminary inspection and am satisfied that the Temporary Works are now ready
for loading, subject to the final inspection by the Temporary Works Co-ordinator.

I am familiar with the design restraints that have been imposed on the loading of the
Temporary Works and have passed these on to the Supervisor/Foretnan in charge.

Signed: Time :
(Section Manager) Date :
The following drawings, schedules and their amendments refer to the Temporary
Works for this part of the structure :

PART 2
I have inspected the Temporary Works to the section of the structure notecl and
found that they have properly erected in accordancc with the drawings (and
_ approved amendments).
THESE TEMPORARY WORKS CAN NOW BE LOADED
Signed: Time :
(-femporary Works Co-ordinator)
AUTHORISATION VALID FOR 24 HOURS Dare :
AUTHORISATION TO REMOVE TEMPORARY WORKS AN' LOAD THE
STRUCTURE
I have checked that the section of structure referred to above is safe without support
from Temporary Works
Criteria used:
i The Temporary Works may be r.-ou.d
sequence:

Signed: Time :

(Temporary Works Co-ordinator) Date :


ADItftf\DDf AtTtr;t T)T;trrtrrrrrt rrrryom nn rd^?h

You might also like