Dear Sir,
Referencecs:
1. Prior to the commencement of the cofferdam activity we have submitted the MS, but we did
not receive any comments or official document if it is approved to this date.
2. The Design for the GFC drawings for cofferdam is not applicable to actual site condition along
Alibunan River. The redesign for the invert level for Siphon #2 is lower than the previous GFC
drawings which makes the water pressure at the slope areas during excavation greater in
addition to strong water current during heavy rain making the GFC design prone to scouring or
being washed out.
3. Refer to the attached documents for your reference.
Attachment list:
1. JRMP II-ICB-2019-422 dated December 10, 2019 – Monitoring report No. 22 of the consultant
as of November 29, Under Contract No. JRMP II-ICB-C-1
2. High Line Canal issues and recommendations.
3. WRF-19-A2-000-18 – Cofferdam Sand Bagging
4. WRF-19-A2-000-19 – Cofferdam Embankment
5. JF-272 Cofferdam Layout for Siphon
DAEWOO Office
Jalandoni St, Calinog, Iloilo
Philippines
T +63.2.551.2316 F + 63.2.550.1897
www.daewooenc.com
Yours faithfully,
Ju-Seok Kim
Project Manager
JRMP-II Project
Issue Type ■for Approval □for Certification □for Consent/Acceptance □for Determination □Notice
Response Expected ■ Yes ■Cat 1 (Within 3 days) □Cat 2 (Within 5 days) □Cat 3 (Within 10 days)
□ No