Refractory dryout
1. Ensure both Boiler fill pump & Boiler feed pump availability.
3. Eco drains at water wall drain header are kept open & other drains to be kept in closed condition.
5. Start one Boiler fill pump, open pump discharge valve and then open discharge Water wall inlet
header valve at ‘0’ ML for Boiler feeding ,fill up to normal working level.
7. When drum level reaches to required level, close discharge valve and then stop the pump.
8. Boiler feeding during refractory dry out shall be done with one Boiler fill pump.
9. During refractory dry out process maintain drum level by starting/stopping boiler fill pump.
10. In case of non availability of both fill pumps drum level to be maintained by boiler feed pump.