MATERIAL ESTIMATE FOR FIRST FLOOR SLAB

S/N DESCRIPTION ` UNIT RATE AMOUNT


A REINFORCEMENT

I 12mm Iron Bar 4 TON - -


II 16mm Iron Bar 1 TON - -

B CARPENTARY/FORMWORK
I Planks/Wood 280 PCS - -
II 2*3*12 wood 140 PCS - -
III Bamboo 200 PCS - -
IV Nails - - - -

C1 CONCRETE WORK @ 1:2:4 MIX RATIO

I Concrete volume (slab and Beams) 36 M3 - -


II Cement 140 BAGS - -
III Sand 3 5-TON - -
IV Aggregate (Granite) 5 5-TON - -
ALTERNATIVELY………………
C2 Concrete Work @ 1:3:6 Mix Ratio

I Concrete volume (slab and Beams) 36 M3 - -


II Cement 105 BAGS - -
III Sand 3 5-TON - -
IV Aggregate (Granite) 6 5-TON - -

NOTE: WORKMANSHIP FEE

MASON/BRICKLAYER+LABOUR+MIXING MACHINE 150,000-170,000

IRON BENDER 80,000-100,000

CARPENTER 80,000-100,000

*THE CARPENTER CAN RENT PLANKS AND CHARGE A LUMP SUM OF 320-350k