Explana

WP2
Plan
NO REMAINING WORKS REMAINING QTY
Start

MAIN LINE 2175


A AREA CLEAR AND CLEAN 1488 20-Jan-18

2nd Critical ( area Depok-Gambringan) 767 20-Jan-18

Others Area 721 20-Jan-18

B AREA BERMASALAH 687 5-Feb-18


1 Lahan Tunggak Perhutani & Lahan Warga 400 5-Feb-18

2 Lahan Jambon 287 5-Feb-18

HDD
A AREA CLEAR AND CLEAN

Ngrombo 1 21-Jan

B AREA BERMASALAH

N/A

AUGER

A AREA CLEAR AND CLEAN

N/A
WP3

1 MAIN LINE 5006


A AREA CLEAR AND CLEAN 4116

All Others Clear and Clean 4116 18-Jan-18

A AREA BERMASALAH 890 5-Feb-18

1 Lahan Balun - Nganjuk (lahan bebas terkendala) 524 5-Feb-18

2 Lahan Balun - Cepu (Re-Instaement) 366 19-Feb-18

2 HDD

A AREA CLEAR AND CLEAN 6-Feb-18

4 Titik HDD (Wadu, Sumber Rejo, Kali Randu,Rowo) 4 6-Feb-18

B AREA BERMASALAH

N/A ( All area Clear)

3 AUGER

A AREA CLEAR AND CLEAN 1-Feb-18


Road Crossing Aryo Jipang 1 , Road Crossing Aryo Jipang 2, St. 15-Feb-18
Cepu , Road Crossing Kapuan

B AREA BERMASALAH 1-Feb-18

8 Lokasi Bermasalah ( Asumsi Clear by 15 Maret 2018)Ijin KAI 1-Feb-18


untuk pemindahan tiang signal belum keluar.

WP1

MAIN LINE 12009


AREA CLEAR AND CLEAN

All area Exclude Kali gawe dan Mukti Hardjo 9945 11-Jan-18

B AREA BERMASALAH 2064 11-Jan-18

Kali Gawe 550 7-Feb-18

Ngablak-Muktiharjo 1514 11-Jan-18

HDD

AREA CLEAR AND CLEAN

6 Lokasi HDD area Clean ( 2 On Progress Kali Gawe dan 10-Jan-18


Juragung)
AREA BERMASALAH

Tidak ada HDD WP 1 yang bermasalah

AUGER
A AREA CLEAR AND CLEAN 26-Jan-18

Sisa 6 titik crossing 6 26-Jan-18

B AREA BERMASALAH

1 13-Feb-18
River crossing sungai sedadi ( saluran irigasi )

1 4-Mar-18
Pemukiman Yos Sudarso

2 15-Mar-18
Rel KA Mranggen dan Jalan Aspal Brumbung dan Rel Muktiharjo
Explanation Delay Gresik - Semarang Pipeline Transmission Pro

Plan Actual Forecast


Vraiance Finish
Finish Start Finish Start Finish

25-Feb-18 18-Jan-18 12-Mar-18

25-Feb-18 18-Jan-18 12-Mar-18 (15.000.00)

25-Feb-18 10-Mar-18 (13.000.00)

24-Feb-18 12-Mar-18 2-Apr-18


24-Feb-18 12-Mar-18 1-Apr-18 (36.000.00)

24-Feb-18 12-Mar-18 2-Apr-18 (37.000.00)

17-Feb 21-Jan 10-Mar-18

12-Mar-18
21-Mar-18 28-Feb-18 15-Apr-18 (25.000.00)

20-Mar-18 5-Mar-18 19-Apr-18

16-Mar-18 5-Mar-18 19-Apr-18 (34.000.00)

20-Mar-18 12-Mar-18 11-Apr-18 (22.000.00)

15-Mar-18 15-Mar-18 12-Apr-18

15-Mar 15-Mar-18 12-Apr-18 (28.000.00)

29-Mar-18 15-Feb-18 29-Mar-18


29-Mar-18 15-Feb-18 29-Mar-18 -

21-Mar-18 15-Mar-18 2-May-18

21-Mar-18 15-Mar-18 2-May-18 (42.000.00)

21-Apr-18 11-Jan-18 5-May-18 (14.000.00)

21-Apr-18 15-Mar-18 29-May-18

24-Mar-18 23-Mar-18 20-Apr-18 (27.000.00)

21-Apr-18 15-Mar-18 29-May-18 (38.000.00)

9-Apr-18 10-Jan-18 10-May-18 (31.000.00)


12-Apr-18 30-Apr-18

12-Apr-18 (18.000.00)
30-Jan-18 30-Apr-18

15-Mar-18 30-Apr-18

3-Mar-18 (41.000.00)
29-Mar-18 13-Apr-18

22-Mar-18 (39.000.00)
15-Apr-18 30-Apr-18

20-Apr-18 15-Mar-18 20-Apr-18 -


g Pipeline Transmission Project

Jan-18 Feb-18 Mar-18 Apr-18


Explanation of Delay
10 17 24 31 07 14 21 28 07 14 21 28 04

KM 14+800 - KM 15+200 belum bisa dikerjakan karena lahan


merupakan milik Perhutani dan Warga
Proses Pembebebasan lahan PTG, target paralel dengan
pengikatan dan pembayaran pekerjaan konstruksi bisa dimulai.

Adanya Permasalahan Sosial, dan Permasalahan Teknis pengeboran


Low Pructivity, Accesability, Hujan tinggi

PTG Perlu Negosiasi dengan KAI mengenai Metode Re-Instatement

1. Untuk Sumber dan Wadu, adalah akibat delaynya Pekerjaan


Sebelumnya ( Ngrombo)
2. Adanya permasalhan issue sosial di Lokasi
3. Untuk Kali Randu dibutuhkan jembatan temporary untuk akses
mobilitas HDD
On Progress St. Cepu, & Road Crossing Kapuan

Ijin KAI untuk pemindahan tiang belum keluar sehingga tiang belum
bisa dipindah

Low productivity,

Pembebasan rmah di Jalan Yos Sudarso untuk CL dan LK

Ijin KAI untuk pemindahan tiang signal belum keluar, dibutuhlkan


durasi yang cukup lama untuk pengerjaan, area kerja rob

ada dua target individual delay, Yaitu Kali Gawe dan Sunagi Juragung.
Perubahan pergeseran CL kearah selatan menghindari tiang pancang irigasi. PTG
harus koordinasi dg BBWS terkait penggunaan lahan BBWS
Ada 3 opsi yang diajukan KWRK ke PTG :
1. Reroute, 2. Boring, 3. Open Cut,
Masih menunggu keputusan dari PTG

Izin prinsip dari PTG ke KAI


Apr-18 May-18 Jun-18
11 18 25 02 09 16 23 30 06 13 20 27
Detail Monitoring Mainline
30,957.0 33,005.3
Section No. Team KM KM Ruas Panjang Plan Cumm. Remaining
Start Finish Progress
Actual Work

WP1 9C 1 ADP 3 ORF kaligawe Kaligawe 550.0 7-Feb-18 24-Mar-18 0.0 550.0
WP1 2 ADP 4 Kaligawe 3+400 Kaligawe 100.0 25-Mar-18 6-Apr-18 0.0 100.0
WP1 3 ADP 1 3+400 5+150 Ngablak & Muktiharjo 1,750.0 11-Jan-18 21-Apr-18 236.1 1,513.9
WP1 4 TF 2 5+150 5+200 Ngablak 50.0 30-Mar-18 8-Apr-18 0.0 50.0
WP1 5 TF 1 11+690 12+100 Menur 72.0 20-Mar-18 29-Mar-18 0.0 72.0
WP1 6 ADP 2 13+000 13+300 Brumbung 300.0 26-Feb-18 19-Mar-18 0.0 300.0
WP1 7 ADP 2 13+300 13+800 Brumbung 500.0 25-Feb-18 23-Mar-18 0.0 500.0
WP1 8 ADP 2 13+850 13+985 Brumbung 270.0 19-Feb-18 3-Mar-18 256.2 13.8
WP1 9 ADP 2 13+250 13+400 Brumbung 150.0 24-Mar-18 2-Apr-18 0.0 150.0
WP1 10 Kinarya 1 13+400 14+400 Mranggen 1,000.0 17-Feb-18 19-Mar-18 454.2 545.8
WP1 11 Kinarya 1 15+400 16+400 Kembangarum 650.0 20-Mar-18 1-Apr-18 36.6 613.4
WP1 12 TF 1 16+900 17+000 Kuripan 100.0 25-Feb-18 7-Mar-18 0.0 100.0
WP1 13 Kinarya 1 17+000 17+200 Kuripan 200.0 20-Mar-18 7-Apr-18 0.0 200.0
WP1 14 Kinarya 2 17+700 17+800 Kuripan 100.0 1-Apr-18 18-Apr-18 0.0 100.0
WP1 9C TOTAL 5,792.0 983.1 4,808.9
WP1 9B 1 TF 1 17+800 17+900 Kuripan 100.0 16-Mar-18 26-Mar-18 0.0 100.0
WP1 2 Kinarya 3 19+700 21+000 Brambang 1,300.0 10-Feb-18 11-Apr-18 0.0 1,300.0
WP1 3 TF 4 21+000 22+100 Rejosari 1,100.0 16-Feb-18 7-Mar-18 0.0 1,100.0
WP1 4 TF 5 22+100 23+000 Sidorejo 900.0 8-Mar-18 24-Mar-18 0.0 900.0
WP1 5 Eko 23+000 23+100 Tegowanu 150.0 8-Mar-18 15-Mar-18 0.0 150.0
WP1 6 TF 3 27+900 28+800 Kuwaron 200.0 22-Mar-18 6-Apr-18 0.0 200.0
WP1 7 TF 3 29+330 29+760 Kuwaron 430.0 8-Mar-18 21-Mar-18 0.0 430.0
WP1 8 TF 3 29+760 29+880 Kuwaron 120.0 23-Feb-18 7-Mar-18 0.0 120.0
WP1 9 Kinarya 2 29+880 30+100 Gubug 270.0 4-Mar-18 15-Mar-18 0.0 270.0
WP1 10 Kinarya 2 30+100 30+800 Gubug 750.0 5-Feb-18 18-Feb-18 0.0 750.0
WP1 11 Kinarya 2 30+800 31+100 Gubug 300.0 16-Mar-18 29-Mar-18 0.0 300.0
WP1 9B TOTAL 5,620.0 0.0 5,620.0
WP1 9A 1 TF 4 34+700 34+850 Mlilir 150.0 3-Apr-18 15-Apr-18 0.0 150.0
WP1 2 Rohmadi 35+000 35+100 Saban 100.0 21-Mar-18 2-Apr-18 0.0 100.0
WP1 3 Rohmadi 37+000 37+100 Tungu 100.0 1-Apr-18 14-Apr-18 0.0 100.0
WP1 4 Sriyono 38+450 38+550 Sumurgede 100.0 18-Mar-18 1-Apr-18 0.0 100.0
WP1 5 Kinarya 4 40+100 40+830 Rawoh 730.0 21-Feb-18 31-Mar-18 0.0 730.0
WP1 9A TOTAL 1,180.0 0.0 1,180.0
WP1 8B 1 TF 2 52+600 53+000 Sedadi 400.0 24-Feb-18 18-Mar-18 0.0 400.0
WP1 8B TOTAL 400.0 11-Jan-18 21-Apr-18 0.0 400.0
WP1 TOTAL WP 1 12,992.0 21-Apr-18 983.1 12,008.9
WP2 8B 1 Geger 57+725 60+400 Depok 2,255.0 20-Jan-18 25-Feb-18 1,487.9 767.1
WP2 2 Andi 10+100 10+300 Tambirejo 200.0 22-Jan-18 3-Feb-18 200.0 0.0
WP2 3 Karno 1 11+400 11+450 Tambirejo 50.0 14-Feb-18 22-Feb-18 50.0 0.0
WP2 4 11+800 11+850 Tambirejo 50.0 14-Feb-18 22-Feb-18 50.0 0.0
WP2 5 Karno 1 12+000 12+700 Plosoharjo 700.0 15-Jan-18 11-Feb-18 706.0 116.0
WP2 6 Edward 1 13+600 13+750 Boloh 150.0 9-Feb-18 24-Feb-18 85.4 125.6
Section No. Team KM KM Ruas Panjang Plan Cumm. Remaining
Start Finish Progress
Actual Work

WP2 8B TOTAL 3,405.0 2,579.3 1,008.7


WP2 8A 1 Nur Cahyo 13+750 15+200 Boloh dan Tunggak 1,450.0 14-Jan-18 25-Feb-18 1,079.3 370.7

WP2 2 Rohmadi 15+200 16+200 Tunggak 1,000.0 29-Jan-18 24-Feb-18 901.4 98.6
WP2 3 Rohmadi 16+200 16+775 Tunggak 575.0 29-Jan-18 15-Feb-18 516.0 59.0
WP2 4 Edward 2 20+000 20+200 Ngrandah 200.0 5-Feb-18 20-Feb-18 170.8 29.2
WP2 5 20+800 21+000 Jambon 287.0 5-Feb-18 24-Feb-18 0.0 287.0
WP2 6 Khaerul 23+580 23+695 Pojok 115.0 1-Feb-18 16-Feb-18 115.0 0.0
WP2 7 Sriyono 26+900 27+800 Panunggalan 750.0 15-Jan-18 24-Feb-18 439.0 311.0

WP2 8A TOTAL 4,377.0 3,221.5 1,155.5


WP2 7B 1 Agus Darmanto 1 29+200 29+385 Panunggalan 185.0 29-Jan-18 13-Feb-18 136.4 48.6

WP2 2 Agus Darmanto 2 29+850 29+935 Panunggalan/Sidorejo 85.0 14-Feb-18 23-Feb-18 0.0 85.0
WP2 3 30+500 30+561 Panunggalan/Tuko 61.0 23-Jan-18 5-Feb-18 61.0 0.0
WP2 4 Eko 32+900 33+085 Crewek 185.0 31-Jan-18 8-Feb-18 134.2 50.8
WP2 5 35+800 35+920 Kradenan 120.0 9-Feb-18 23-Feb-18 120.0 0.0
WP2 7B TOTAL 636.0 451.6 184.4
WP2 TOTAL WP 2 8,418.0 25-Feb-18 6,252.4 2,348.6
WP3 7B 1 Edward 4 36+200 36+700 Ds. Kradenan (Pemukiman) 500.0 8-Feb-18 6-Mar-18 256.2 243.8
WP3 2 Edward 4 37+000 38+400 Ds. Kradenan (Persawahan) 1,400.0 18-Jan-18 7-Feb-18 1,352.8 47.2
WP3 3 Edward 3 39+500 39+700 Sungai Pandanharum 200.0 3-Feb-18 23-Feb-18 70.8 129.2
WP3 4 Edward 3 39+700 39+900 Pandanharum 200.0 28-Feb-18 17-Mar-18 73.2 126.8
WP3 5 Karno 1 41+380 41+380 Crossing Gabus 50.0 7-Mar-18 14-Mar-18 0.0 50.0
WP3 7B TOTAL 2,350.0 1,753.0 597.0
WP3 7A 1 Guntur 44+700 44+730 Sulursari (Opencut Sungai CWC) 30.0 21-Jan-18 6-Feb-18 30.0 0.0
WP3 2 Rohmadi 45+700 45+750 Tahunan (Opencut Sungai CWC) 50.0 6-Feb-18 17-Feb-18 0.0 50.0
WP3 3 Wasudi 46+300 46+350 Tahunan (Opencut Sungai CWC) 50.0 17-Feb-18 28-Feb-18 0.0 50.0
WP3 4 TBA 50+760 50+800 Gabusan (Crossing Rel KA) 40.0 6-Mar-18 18-Mar-18 0.0 40.0
WP3 5 Guntur 50+800 52+100 Gabusan 1,300.0 31-Jan-18 8-Mar-18 1,118.6 181.4
WP3 6 Guntur 53+050 53+100 Crossing Puskesmas 50.0 23-Feb-18 6-Mar-18 0.0 50.0
WP3 7 TBA 54+750 54+786 Doplang (Crossing Rel KA) 36.0 9-Mar-18 17-Mar-18 0.0 36.0
WP3 7A TOTAL 1,556.0 1,148.6 407.4
WP3 6B 1 ADP 3 56+300 56+700 Rowo (HDD) 400.0 15-Feb-18 3-Mar-18 48.8 351.2
WP3 2 ADP 4 59+525 59+825 Randulawang (HDD) 300.0 15-Feb-18 1-Mar-18 0.0 300.0
WP3 3 TBA 63+050 63+100 Kadengan (Cross Rel KA) 50.0 4-Mar-18 12-Mar-18 0.0 50.0
WP3 4 TF 1 64+500 64+600 Kadengan (Exit HDD) 100.0 26-Jan-18 5-Feb-18 72.7 27.3
WP3 5 Andi 64+900 65+200 Wulung (Gang Branjangan) 300.0 6-Feb-18 8-Mar-18 0.0 300.0
WP3 6 Khaerul 65+200 65+500 Wulung (Ruas PU) 300.0 20-Jan-18 24-Feb-18 300.0 0.0
WP3 7 TBA 65+850 65+900 Kediren (Cross Rel KA) 50.0 13-Mar-18 21-Mar-18 0.0 50.0
WP3 6B TOTAL 1,500.0 421.5 1,078.5
WP3 6A 1 Purwanto 1 70+150 70+450 HDD Kali Sumber 300.0 1-Feb-18 15-Feb-18 240.0 60.0
WP3 2 Andi 71+100 71+650 Jompong (Selatan) 550.0 18-Jan-18 31-Jan-18 509.2 40.8
WP3 3 TBA 71+632 71+668 Sumber (Cross Rel KA) 36.0 6-Mar-18 18-Mar-18 0.0 36.0
WP3 4 Purwanto 1 71+760 71+832 Sumber (Opencut Sungai CWC) 72.0 25-Feb-18 11-Mar-18 0.0 72.0
WP3 5 Purwanto 2 72+150 72+200 Sumber (Cross Jalan) 50.0 12-Mar-18 20-Mar-18 36.6 13.4
WP3 6 Purwanto 2 72+200 73+450 Sumber Wates (Reroute SPP) 1,250.0 5-Feb-18 26-Feb-18 841.8 408.2
6A

Section No. Team KM KM Ruas Panjang Plan Cumm. Remaining


Start Finish Progress
Actual Work

WP3 7 TBA 73+450 73+486 Sumber Menden (Crossing Rel KA) 36.0 13-Mar-18 21-Mar-18 0.0 36.0
WP3 8 Purwanto 3 75+200 75+300 Crossing Pipa Pertamina EP 100.0 2-Mar-18 10-Mar-18 0.0 100.0
WP3 9 Purwanto 3 76+200 76+600 Wado (HDD) 400.0 2-Feb-18 14-Feb-18 400.0 0.0
WP3 10 Wasudi 77+100 77+172 Wado (pasar) 72.0 18-Jan-18 2-Feb-18 72.0 0.0
WP3 11 Wasudi 78+300 78+600 Kemantren 300.0 3-Feb-18 10-Feb-18 226.8 73.2
WP3 12 Edward 5 83+200 83+400 Kapuan (Barat LBCV) 200.0 10-Feb-18 24-Feb-18 0.0 200.0
WP3 13 Edward 5 83+400 83+835 Kapuan (Timur LBCV) 435.0 24-Feb-18 10-Mar-18 0.0 435.0
WP3 14 TBA 83+835 83+875 Kapuan (Crossing Rel KA) 40.0 27-Feb-18 9-Mar-18 0.0 40.0
WP3 15 Geger 83+900 84+200 Cepu AURI 300.0 8-Feb-18 5-Mar-18 0.0 300.0
WP3 6A TOTAL 4,141.0 2,326.4 1,814.6
WP3 5B 1 Khaerul 88+115 88+639 Balun, Nganjuk Sumberpitu 524.0 5-Feb-18 16-Mar-18 0.0 524.0

WP3 2 Eko 88+699 88+769 Balun 70.0 9-Mar-18 17-Mar-18 0.0 70.0
WP3 3 Edward 1 88+784 88+878 Balun 94.0 23-Feb-18 5-Mar-18 0.0 94.0
WP3 4 Edward 2 88+893 88+947 Balun 54.0 11-Mar-18 19-Mar-18 0.0 54.0
WP3 5 Sriyono 89+027 89+393 Balun, Cepu 366.0 19-Feb-18 20-Mar-18 0.0 366.0

WP3 5B TOTAL 1,108.0 0.0 1,108.0


WP3 TOTAL WP 3 10,655.0 21-Mar-18 5,649.5 5,005.5

TOTAL WP 1-3 32,065.0 12,884.9 19,363.1


SCHEDULE PEKERJAAN BORING PER WP HIDROTEST

Baseline
WP 2 WP 3

Forecast WP 2 WP 3 WP 1 WP 4 WP 5
Status : 28/02/18
Baseline
No Section KM Lokasi Panjang WP Subkon (20/01/2018) Start Finish Januari Februari Maret April Mei Status
Start Finish W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
WP 2
SCHEDULE PEKERJAAN BORING PER WP HIDROTEST

Baseline
WP 2 WP 3

Forecast WP 2 WP 3 WP 1 WP 4 WP 5
Status : 28/02/18
Baseline
No Section KM Lokasi Panjang WP Subkon (20/01/2018) Start Finish Januari Februari Maret April Mei Status
Start Finish W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

1 8A 20+750 Tower Telkomsel - St.Jambon 23.41 WP 2 Cancelled 1-Feb-18 16-Feb-18 15-Feb-18 15-Feb-18 Cancelled

Road Crossing & mushola -


2 8A 15+200
Tunggak
60 WP 2 OGSPRO 1 20-Jan-18 4-Feb-18 20-Jan-18 4-Feb-18 Finish

Road Crossing & bangunan -


3 8A 13+680
Mboloh
44.21 WP 2 CPM 1 10-Jan-18 25-Jan-18 10-Jan-18 3-Feb-18 Finish

River crossing irigasi - Pilang


4 8A 57+700
Payung
23.41 WP 2 OGSPRO 4 16-Jan-18 31-Jan-18 16-Jan-18 12-Feb-18 Finish

WP 3
1 5B 89+000 Rel KA , cepu 61.25 WP 3 ACM 21-Feb-18 15-Mar-18 15-Mar-18 29-Mar-18 v
Road Crossing Aryo Jipang -
2 5B 89+950
balun ( re-route )
15 WP 3 OGSPRO 2 2-Feb-18 17-Feb-18 16-Mar-18 29-Mar-18 v
Road Crossing Aryo Jipang -
3 5B 89+950
balun ( re-route )
20 WP 3 OGSPRO 4 18-Feb-18 5-Mar-18 14-Mar-18 29-Mar-18 v

Road Crossing Aryo Jipang -


4 5B 89+950
balun ( re-route ) St. Cepu
70 WP 3 OGSPRO 1 18-Feb-18 5-Mar-18 15-Feb-18 12-Mar-18 On Progress

5 5B 83+835 Rel KA, Kapuan 36.66 WP 3 OGSPRO 1 28-Jan-18 20-Feb-18 14-Mar-18 31-Mar-18 v

6 6A 83+200 Road Crossing Kapuan 16.58 WP 3 OGSPRO 2 1-Feb-18 16-Feb-18 25-Feb-18 14-Mar-18 On Progress

Izin Tambahan masih dalam proses dari PTG


7 6A 73+450 Rel KA, Menden 38.36 WP 3 OGSPRO 1 20-Jan-18 11-Feb-18 2-Apr-18 19-Apr-18
ke KAI

8 6A 83+200 Road Crossing Desa Sumber 17.48 WP 3 OGSPRO 2 17-Feb-18 4-Mar-18 31-Jan-18 22-Feb-18 Finish

Izin Tambahan masih dalam proses dari PTG


9 6A 71+650 Rel KA, Menden 37.32 WP 3 PINTAGO 2 12-Feb-18 6-Mar-18 10-Mar-18 27-Mar-18
ke KAI

Rel KA Kadengan, Randu Izin Tambahan masih dalam proses dari PTG
10 6B 63+065
Blatung
32.7 WP 3 PINTAGO 1 20-Jan-18 11-Feb-18 10-Mar-18 26-Mar-18
ke KAI

Rel KA Kadengan, Randu Izin Tambahan masih dalam proses dari PTG
11 6B 65+900
Blatung
32.69 WP 3 PINTAGO 1 12-Feb-18 6-Mar-18 27-Mar-18 12-Apr-18
ke KAI

12 7A 54+700 Rel KA, Doplang 29.63 WP 3 SUYITNO 24-Feb-18 14-Mar-18 30-Mar-18 15-Apr-18 v

13 7A 50+750 Rel KA, Doplang 36.03 WP 3 SUYITNO 5-Feb-18 23-Feb-18 12-Mar-18 29-Mar-18 v

WP 1
River crossing sungai sedadi ( Perubahan pergeseran CL kearah selatan menghindari
1 8B 52+600
saluran irigasi )
54 WP 1 PINTAGO 2 13-Feb-18 3-Mar-18 29-Mar-18 14-Apr-18 tiang pancang irigasi. PTG harus koordinasi dg BBWS
terkait penggunaan lahan BBWS

2 9A 40+500 Bangunan desa Rawoh 26 WP 1 SUYITNO 26-Jan-18 12-Feb-18 17-Apr-18 30-Apr-18 v

BBWS Pemali Juana, Sungai


3 9A 37+000
Sekunder Tungu
29 WP 1 TRIBARA 17-Feb-18 7-Mar-18 28-Mar-18 13-Apr-18 v

4 9A 34+700 Jalan Aspal, Milir 27.9 WP 1 PINTAGO 2 8-Mar-18 24-Mar-18 16-Apr-18 30-Apr-18 v
Rel KA, Mranggen dan Jalan
5 9C 14+050
Aspal Brumbung
63 WP 1 PINTAGO 3 2-Apr-18 20-Apr-18 10-Mar-18 27-Mar-18 Izin prinsip dari PTG ke KAI

6 9C 13+300 Jalan aspal, Brumbung 9 WP 1 SUYITNO 25-Mar-18 12-Apr-18 30-Jan-18 10-Mar-18 On Progress

Rel KA Muktiharjo dan


7 9C 5+200
Muktiharjo Raya
36 WP 1 PINTAGO 3 15-Mar-18 1-Apr-18 29-Mar-18 14-Apr-18 v

8 9C 3+800 Jl. Industri Barat, Muktiharjo 12 WP 1 PINTAGO 3 23-Mar-18 10-Apr-18 16-Apr-18 30-Apr-18 v

Ada 3 opsi yang diajukan KWRK ke PTG :


9 9C Pemukiman Yos Sudarso 68.9 WP 1 TRIBARA 4-Mar-18 22-Mar-18 15-Apr-18 30-Apr-18 1. Reroute, 2. Boring, 3. Open Cut,
Masih menunggu keputusan dari PTG
SCHEDULE PEKERJAAN BORING PER WP HIDROTEST

Baseline
WP 2 WP 3

Forecast WP 2 WP 3 WP 1 WP 4 WP 5
Status : 28/02/18
Baseline
No Section KM Lokasi Panjang WP Subkon (20/01/2018) Start Finish Januari Februari Maret April Mei Status
Start Finish W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
WP 4
1 3B 152+640 Baureno 52 WP 4 OGSPRO 4 2-Mar-18 19-Mar-18 24-Feb-18 12-Mar-18 v
145+600 -
2 3B
145+630
Ngemplak 28 WP 4 OGSPRO 3 25-Jan-18 9-Feb-18 14-Feb-18 28-Feb-18 Finish

145+480 -
3 3B
145+457
Pohwates 27 WP 4 OGSPRO 4 10-Feb-18 28-Feb-18 31-Mar-18 15-Apr-18

Jalan akses Desa


4 3B 143+043 Margoagung dan DI Pacal 22.6 WP 4 LFE 1 9-Jan-18 24-Jan-18 9-Jan-18 28-Feb-18 On Progress
Sekunder Medalem

Jl. Raya Pekuwon (samping


5 4A 139+050
STKA Sumberejo), Sumberejo
28.39 WP 4 ACM 12-Jan-18 24-Jan-18 5-Feb-18 15-Feb-18 Finish

6 4A 133+200 Suwaloh 11.23 WP 4 LFE 1 31-Mar-18 14-Apr-18 4-Mar-18 26-Mar-18

Desa Kapas,Jalan akses Desa


7 4A 130+718
Kedaton dan Saluran BKKA
26.58 WP 4 TRIBARA 14-Mar-18 30-Mar-18 3-May-18 20-May-18

Desa Tikusan Jl. Raya Desa


8 4B 126+400
Wedi, Kalianyar
9.5 WP 4 OGSPRO 2 25-Jan-18 9-Feb-18 31-Mar-18 15-Apr-18

Jl. Akses RIG EMCL, Desa


9 4B 117+000
Kalipang
18 WP 4 ACM - - 10-Feb-18 21-Feb-18 Finish

10 5A 110+200 Jl. Raya Ngasem, Kalitidu 16 WP 4 ACM 18-Jan-18 1-Feb-18 27-Jan-18 4-Feb-18 Finish

11 5A 105+830 Desa Celangap 87.3 WP 4 OGSPRO 1 4-Apr-18 19-Apr-18 21-Apr-18 7-May-18

12 5B 93+000 Jalan akses Ds. Kuncen 12 WP 4 OGSPRO 2 10-Feb-18 25-Feb-18 17-Apr-18 3-May-18 v
SCHEDULE PEKERJAAN BORING PER WP HIDROTEST

Baseline
WP 2 WP 3

Forecast WP 2 WP 3 WP 1 WP 4 WP 5
Status : 28/02/18
Baseline
No Section KM Lokasi Panjang WP Subkon (20/01/2018) Start Finish Januari Februari Maret April Mei Status
Start Finish W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

13 5B 93+050 Rumah di Desa Kuncen 18 WP 4 OGSPRO 2 26-Feb-18 13-Mar-18 5-May-18 20-May-18 v

WP 5
1 1 KP 0+020 Rel depan GRE Station 20.8 WP 5 TRIBARA 09-Jan-18 27-Jan-18 9-Jan-18 25-Mar-18 v

2 1 KP 9+150 Jl. Desa Banjarsari 41.43 WP 5 OGPRO 3 2-May-18 17-May-18 7-May-18 23-May-18

Jl. Raya Bunder - Cerme,


3 1 KP 9+240
Banjarsari
20.56 WP 5 OGPRO 3 8-Apr-18 1-May-18 20-Apr-18 5-May-18

4 2A 202+630 Rel KA Desa Sumari, Tebaloan 34 WP 5 OGSPRO 1 8-Mar-18 1-Apr-18 9-May-18 26-May-18

5 2A 197+164 Jl. Desa Tambakrejo 35.22 WP 5 OGPRO 3 28-Jan-18 12-Feb-18 3-Apr-18 18-Apr-18 v

6 2B 183+970 Jl. Desa Pangkatrejo 18.9 WP 5 OGSPRO 4 22-Apr-18 9-May-18 6-May-18 22-May-18 v

7 2B 177+700 Sukodadi 31 WP 5 OGSPRO 4 1-Mar-18 15-Mar-18 19-Apr-18 4-May-18 v

8 2B 174+300 Jl. Desa Karang Tinggil 36 WP 5 OGPRO 3 21-Apr-18 6-May-18 28-Feb-18 15-Mar-18 v
Rumah Bpk. Sutrisno, Desa
9 2B 173+400
Waru Wetan
44 WP 5 OGPRO 3 20-Mar-18 4-Apr-18 17-Mar-18 1-Apr-18 v
160+940 -
10 3A
161+080
Bangunan rumah Desa Babat 106.6 WP 5 ACM 23-Mar-18 7-Apr-18 19-Apr-18 6-May-18 v

11 3A 160+900 Jl. Somowiharjo, Babat 9 WP 5 LFE 1 5-Apr-18 21-Apr-18 21-Apr-18 13-May-18 v


Rel KA, Gendongkulon
12 3A 160+700
Sebelum STKA Babat
34 WP 5 ACM 1-Mar-18 17-Mar-18 19-Feb-18 28-Feb-18 On Progress

Rel KA, Gendongkulon


13 3A 160+470
Rel Kereta Barang
34 WP 5 ACM 5-Mar-18 22-Mar-18 14-Feb-18 23-Feb-18 Finish

14 3A 160+020 Rel KA, Gilang 34 WP 5 ACM 17-Feb-18 4-Mar-18 31-Mar-18 17-Apr-18 v


Jl. Raya Babat - Jombang,
15 3A 160+000
Banaran
16 WP 5 LFE 1 30-Mar-18 14-Apr-18 28-Mar-18 19-Apr-18 v

16 3A 158+270 Rel KA, Gajah 33.5 WP 5 ACM 1-Feb-18 16-Feb-18 10-Mar-18 18-Mar-18 v

17 3A 156+130 Rel KA, Gajah 22 WP 5 ACM 13-Feb-18 28-Feb-18 28-Feb-18 10-Mar-18 v

Bulan Februari Maret April Mei


Work Pack Hidrotest WP2 WP3 WP1 W4 WP5 WP2 WP3 WP1 W4 WP5 WP2 WP3 WP1 W4 WP5 WP2 WP3 WP1 W4 WP5
Target per WP 4 1 0 5 2 0 9 2 2 4 0 3 7 2 4 0 0 0 4 7
Target per Bulan 12 17 16 11
Aktual Finish 10
Estimasi Finish 10
SCHEDULE PEKERJAAN BORING PER WP HIDROTEST

Baseline
WP 2 WP 3

Forecast WP 2 WP 3 WP 1 WP 4 WP 5
Status : 28/02/18
Baseline
No Section KM Lokasi Panjang WP Subkon (20/01/2018) Start Finish Januari Februari Maret April Mei Status
Start Finish W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

Resources Boring
Subkon Jumlah Status
1. On Progress di Jln. Stasiun Cepu
2. On Progress di Jln. Desa Kapuan
OGSPRO 4 3. On Progress di Ngemplak
4. On Progress di Baureno

Current ACM 1 On Progress di Stasiun Babat


Resources TRIBARA 1 On Progress di Rel GRE Station
LFE 1 On Progress di Medalem
SUYITNO 1 On Progress di Jln. Aspal Brumbung
CPM 1 Demobilisasi dari Mboloh
Total 8
Pintago 3 Prepare shipment
Additional
Total 11
SCHEDULE PEKERJAAN HDD PER WP HIDROTEST
Baseline WP 2 WP 3 WP 1

Forecast WP 2 WP 3 WP 1 WP
WP45
Status : 28/02/18

No Section Lokasi Panjang WP Subkon Baseline Re-Plan


(20/01/2018) Januari Februari Maret April Mei Explanation Delay
Start Finish Start Finish W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

WP 2
Social Issue, Technical error , Sticky Clay, Sehingga memperlambat proses pekerjaan
1 8B Ngrombo 429.11 WP 2 TUNE 2-1 21-Jan-18 17-Feb-18 21-Jan-18 10-Mar-18 T2 T2 T2 T2 T1 T1 T1
HDD
WP 3
1 6A Kali Wadu, Desa Wadu 413.5 WP 3 TUNE 1 8-Feb-18 28-Feb-18 17-Mar-18 12-Apr-18 T1 T1 T1 T1 Menunggu Penyelesaian dari Ngrombo

KWRK sudah melakukan open cut. Namun keputusan final menjadi HDD sehingga
2 6A Kali Sumberejo, Desa Sumberejo 232.06 WP 3 TUNE 2 6-Feb-18 26-Feb-18 12-Mar-18 9-Apr-18 T2 T2 T2 T2
diperlukan pengangkatan pipa tertanam & preparation
Kali Randu Lawang, Desa 1. Keterbatan sequensial resource
3 6B Randulawang 323.1 WP 3 KELSRI 1 10-Feb-18 6-Mar-18 17-Mar-18 12-Apr-18 K1 K1 K1 K1
2. Akses masuk sangat kecil, butuh jembatan sementara untuk akses masuk
1. Keterbatan sequensial resource
4 6B Kali Rowo, Desa Asem Tanggung 357.7 WP 3 LINE 1 19-Feb-18 15-Mar-18 12-Mar-18 7-Apr-18 L1 L1 L1 L1
2. Akses masuk sangat kecil, butuh pengurukan untuk akses masuk

WP 1
1 9B Desa Gubug 675.16 WP 1 MERSING 1 25-Feb-18 24-Mar-18 15-Mar-18 10-Apr-18 M1 M1 M1 M1 akibat dari delay mersing di kaligawe

2 9B Makam-rumah Gubug 220 WP 1 MERSING 1 24-Feb-18 18-Mar-18 12-Apr-18 8-May-18 M1 M1 M1 sequensial efek dari hdd gubug

3 9B Sungai Jragung 216.51 WP 1 MTT 1 10-Jan-18 31-Jan-18 10-Jan-18 28-Mar-18 MT1 MT1 MT1 MT1 MT1 MT1 MT1 MT1 MT1 MT1 MT1 Technial issue & akan di open cut

4 9B Sungai Cabean 354.01 WP 1 TUNE 1 27-Jan-18 18-Feb-18 14-Apr-18 10-May-18 T1 T1 T1 T1 Impact stuck dari HDD jragung

5 9C Gudang Holcim 214 WP 1 LINE 2 16-Mar-18 9-Apr-18 14-Mar-18 7-Apr-18 L2 L2 L2

6 9C Kaligawe 625.35 WP 1 MERSING 1 1-Feb-18 24-Feb-18 9-Feb-18 8-Mar-18 M1 M1 M1 M1 M1 tanah berbatu, kondisi sulit

7 9C Sungai Dombo Sayung 409 WP 1 TUNE 1 17-Jan-18 5-Feb-18 17-Jan-18 13-Feb-18 T1 T1 T1 T1

WP 4
1 3B Kali Pudung Kembar, Sraturejo 203.74 WP 4 PDC 2 1-Mar-18 25-Mar-18 3-Mar-18 1-Apr-18 P2 P2 P2 P2 Akses Exit banjir. Efek meluapnya anak sungai bengawan solo

2 3B Jl. Imam Bonjol, Mejuwet 718.2 WP 4 TUNE MAXI 18-Mar-18 14-Apr-18 6-Mar-18 30-Mar-18 M M M M

Ds. Talun dan DI Pacal Kanan


3 3B Sekunder Talun 230 WP 4 LINE 1 5-Feb-18 28-Feb-18 14-Apr-18 6-May-18 L1 L1 L1 Original plan menggunakan alat dari mekuris, (mekuris stuck)

4 3B Kali Mekuris, Desa Mekuris 242.89 WP 4 FARREL 1 13-Jan-18 8-Feb-18 13-Jan-18 15-Mar-18 F1 F1 F1 F1 F1 F1 F1 F1 Technical Error / Stuck

5 4A Kali Prambukan, Desa Prambukan 275.66 WP 4 KELSRI 1 10-Feb-18 6-Mar-18 15-Apr-18 16-May-18 K1 K1 K1 K1 Sequensial dari kali rowo

Jalan masuk menuju pabrik batako,


6 4A Margomulyo
199.83 WP 4 LINE 2 1-Mar-18 25-Mar-18 5-May-18 28-May-18 L2 L2 L2 Sequensial pekerjaan

7 4B Kali Kilan/Kali Loro 218.58 WP 4 TUNE 2 7-Mar-18 31-Mar-18 11-Apr-18 5-May-18 T2 T2 T2 T2 Propose open cut

8 4B Jl. Monginsidi, Bojonegoro 275.01 WP 4 LINE 1 2-Apr-18 1-May-18 7-May-18 29-May-18 L1 L1 L1 Belum Bebas

9 4B Jl. Panglima Polim, Sidodadi 479.44 WP 4 MERSING 2 2-Mar-18 1-Apr-18 11-Apr-18 6-May-18 M2 M2 M2 M2 Belum Bebas

10 4B Jl. HOS Cokroaminoto Sawahan-Jetak 232.14 WP 4 LINE 2 25-Mar-18 21-Apr-18 9-Apr-18 3-May-18 L2 L2 L2 L2 Belum Bebas

11 4B Kali Ganggang, Ngablak 206.34 WP 4 PINTAGO 1 26-Feb-18 22-Mar-18 1-Apr-18 30-Apr-18 PG1 PG1 PG1 PG1 Sequensial pekerjaan

12 4B Sekolahan Desa Pumpungan 287.93 WP 4 TITAN 1 7-Mar-18 31-Mar-18 23-Mar-18 13-Apr-18 TN1 TN1 TN1 Sequensial pekerjaan
SCHEDULE PEKERJAAN HDD PER WP HIDROTEST
Baseline WP 2 WP 3 WP 1

Forecast WP 2 WP 3 WP 1 WP
WP45
Status : 28/02/18

No Section Lokasi Panjang WP Subkon Baseline Re-Plan


(20/01/2018) Januari Februari Maret April Mei Explanation Delay
Start Finish Start Finish W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

13 5A Mayang Geneng 238.2 WP 4 KELSRI 1 2-Feb-18 25-Feb-18 15-Feb-18 15-Mar-18 K1 K1 K1 K1 Late Start akibat transportasi HDD

14 5A Ds. Sumengko 223 WP 4 TITAN 2-1 23-Mar-18 16-Apr-18 3-Mar-18 21-Mar-18 TN2 TN2 TN1

Kali Prudung dan Solo Valley


15 5B Purwosari
326.4 WP 4 TITAN 1 4-Mar-18 1-Apr-18 15-Apr-18 6-May-18 TN1 TN1 TN1 Evaluasi design penambahan panjang akibat tidak bebasnya lahan perhutani

16 5B Kali Mbludug 264.18 WP 4 TITAN 2-1 18-Jan-18 7-Feb-18 3-Feb-18 28-Feb-18 TN2 TN2 TN2 TN1

Jl. Dr. Soetomo, Padangan


17 5B Banjarejo-Kuncen 620 WP 4 MERSING 2 18-Feb-18 17-Mar-18 14-Mar-18 8-Apr-18 M2 M2 M2 Late Start akibat transportasi HDD

18 5A Kali Ranting Kulon, Desa Kalitidu 286.62 WP 4 PDC 2-1 12-Jan-18 17-Feb-18 12-Jan-18 27-Feb-18 P2 P2 P2 P2 P2 P1

19 5B Kali Gandong, Beged 296.61 WP 4 TITAN 1 25-Jan-18 10-Feb-18 29-Jan-18 18-Feb-18 TN1 TN1 TN1 TN1

20 4A Kali Besuki, Desa Besuki 252.49 WP 4 PDC 1 19-Jan-18 12-Feb-18 27-Jan-18 20-Feb-18 P1 P1 P1 P1

WP 5
1 2A Kali Deket Kulon Ds. Deket Kulon 261.20 WP 5 PDC 1 11-Feb-18 27-Feb-18 3-Mar-18 29-Mar-18 P1 P1 P1 P1 Lahan Exit baru bebas tanggal 23 Feb 18

Jl. Jendral Sudirman dan Rel


2 2A (Taman Lamongan) 367.42 WP 5 TITAN 1 22-Apr-18 19-May-18 8-May-18 30-May-18 TN1 TN1 TN1 Belum Bebas

3 2A Kali Otik, Sidokumpul 211.62 WP 5 TUNE 2 24-Apr-18 17-May-18 7-May-18 31-May-18 T2 T2 T2 Belum Bebas

4 2A Rel KA Lamongan 322.8 WP 5 PINTAGO 1 - - 2-May-18 30-May-18 PG1 PG1 PG1 PG1 Belum Bebas

Kali Temenggung (depan RS


5 2B Muhammadyah) 278.74 WP 5 PDC 1 28-Feb-18 24-Mar-18 1-Apr-18 27-Apr-18 P1 P1 P1 P1 Sequensial pekerjaan

Kali Plalangan (depan Stikes


6 2B Muhammadyah) 198.77 WP 5 PDC 2 25-Mar-18 18-Apr-18 4-Apr-18 30-Apr-18 P2 P2 P2 P2 Sequensial pekerjaan

7 3A Kali Semar Mendem, Gunungsari 321.3 WP 5 PDC 1 22-Apr-18 15-May-18 30-Apr-18 26-May-18 P1 P1 P1 P1 Lahan kerja banjir, sequensial pekerjaan

Bulan Februari Maret April Mei


Work Pack Hidrotest WP2 WP3 WP1 W4 WP5 WP2 WP3 WP1 W4 WP5 WP2 WP3 WP1 W4 WP5 WP2 WP3 WP1 W4 WP5

Target per WP 1 0 1 4 0 1 0 2 4 1 0 4 2 3 2 0 0 0 2 3
Target per Bulan 6 8 11 5
Aktual Finish 5
Estimasi Finish 6

Resources HDD
Subkon Jumlah Status

1. Finish pullback di Dombo Sayung


TUNE 3 2. On Progress di Ngrombo
3. Mobilisasi ke Mejuwet

1. Finish pullback di Kali Gandong


TITAN 1 2. On Progress di Kali Mbludug
Current
Resources 1. Finish pullback di Kali Besuki
PDC 2 2. On Progress di Kalitidu

MERSING 1 On Progress di Kaligawe


KELSRI 1 On Progress di Mayang Geneng
MTT On Progress di Sungai Jragung
FARREL On Progress di Kali Mekuris
Total 8
MERSING 1 Prepare shipment dari Malaysia
Line 2 Custom clearance di Tg. Priuk
Additional
Pintago 1 Prepare shipment
Total 15
SCHEDULE PEKERJAAN HDD PER WP HIDROTEST
Baseline WP 2 WP 3 WP 1

Forecast WP 2 WP 3 WP 1 WP
WP45
Status : 28/02/18

No Section Lokasi Panjang WP Subkon Baseline Re-Plan


(20/01/2018) Januari Februari Maret April Mei Explanation Delay
Start Finish Start Finish W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4

No Section Lokasi Panjang WP Subkon Start Finish Januari Februari Maret April Mei
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
Jalan aspal, Tegowanu Kulon PINTAGO 2
1 9B (MHDD) 100 WP 1 MHDD 15-Mar-18 6-Apr-18 PG2 PG2 PG2

Pabrik Kayu, Kuripan PINTAGO 2


2 9C (MHDD) 118.7 WP 1 MHDD 8-Apr-18 30-Apr-18 PG2 PG2 PG2

Jl.Akses Kedanyang, Banjarsari PINTAGO 2


3 1 (MHDD)
178.56 WP 5
MHDD
3-May-18 25-May-18 PG2 PG2 PG2