You are on page 1of 12

HS.SAF.09.

F12

CONTRACTOR WORK METHOD STATEMENT (EHS)

1. Contractor Name : DANWAY E & M ENG’G 3. Trades / Disciplines Involved In Work :


Engineer, Supervisor, Electricians and Helpers.
(TK-4842/ABB)

2. Work Location : GIS Building

Proposed Starting Date :

4. Brief Description Of Work To Be Undertaken : GIS 5. Tools / Substance


PREPARATION FOR HIGH VOLTAGE TEST
Portable Tools
Hand Electrical Pneumatic
Hazardous Substances
Toxic Flammable Corrosive
Harmful Irritant
Environment Impact
Health & Hygiene Effect

Environmental Impact Health & Hygiene

Yes No Yes No

Hazardous waste Significant Dust Generation


Emissions Noise (above 85 DbA)
Discharge to sea or drains Hazardous substances (if yes attach list)
If answer to any of the above is yes, please circulate to If answer to any of the above is yes, please circulate to
Manager, Environmental Affairs Senior Occupational Hygienist

6. Person Completing The Work Method Statement :

Name : Joachim Kuhlmann Position : Joachim Kuhlmann Company : ABB Switzerland

Signature : Date : 30.11.2011

Revision: 0(26-May-2011) Page 1 of 12


HS.SAF.09.F12

7. Approvals

Contractor Site Rep. Name Maan Al-Eshaiker Signature : Date : 30.11.2011

EMAL Contract Admin. Name       Signature :       Date :      

Area Owner Name       Signature :       Date :      

Name       Signature:       Date:      

 The completed Work Method Statement must be submitted at least seven full working days prior to the
commencement of activities.
 Where the Work Method Statement indicates the use of Hazardous Substances, a Material Hazard Data
Sheet must be attached.
• After the Area Owner’s approval the Work Method Statement shall be forwarded to EHS department for
approval
• The approved Work Method Statement must be attached to the permit(s) to work and all persons involved
in the job instructed in its requirements.

2. RISK ESTIMATOR CHART


The Risk Estimator chart should be used as an assistant for filling out the work
method statement.

Severity
Probability Low x1 Medium x 2 High x3
Low x1 Low Probability x Low LP x MS LP x HS
Severity 1 x 1 = 1 1x2 = 2 1x3 =3
Medium x2 MP x LS MP X MS MP x HS
2x1 =2 2x2 =4
2x3 =6
High x3 HP x LS HP X HS HP x HS
3 x 1 =3 3x2 = 6 3x3=9

Significant Risk = High Risk (6-9) or Medium Risk (3-4) in terms of probability and severity
Tolerable Risk = Risk reduced to an acceptable level = Low Risk (1-2)
Residual Risk = Risk remaining after implementing recommended control actions (usually very minor).

Revision: 0(26-May-2011) Page 2 of 12


HS.SAF.09.F12

8. Safety Analysis

Identified Persons Precautions and Plan of Severity x


Individual Hazard(s) Exposed actions To Be Taken To Probability =
Activities To Associated With To Hazard Remove / Control Hazards Risk
Complete Work. Activity
List In Sequence Residual Risk
of Activity
(Use Risk
Estimator
Chart)

Emal /
1.PREPARATI  Slips, trips SNC  Maintain housekeeping
ON. and fall at the rep., around in the working
same level. Engr., area. 1x2=2
Supv.
Elec.
Helpers
Emal /
SNC All workers involve in the
rep., activity must be aware of
 Hot
Engr., heat stress, supervisor to 2x2=4
weather.
Supv. ensure drinking cold
Elec water is available.
Helpers.
Emal /
SNC  Wear P.P.E.'s at all times
rep., (hard hat, Clear safety
 Not using Engr., glass, safety shoes, hand 2x2=4
P.P.E.'s Supv. gloves, dust mask, fire
Elec,Hel retardant long sleeve shirt
pers. / pants).

 Electrical Engr.,  Only qualified employees


shock, fire Supv. will work near or on 3x2=6
and arc flash. Elec,Hel electrical equipment.
pers
 Use only proper tools
that have a current colour
coding.

 Failure to Engr.,  Depending on the type of


interact with Supv. activity, the employer
each other Elec,Hel shall ascertain that the
and absence pers employees of other
of a Job employers working 2x2=4
Hazard nearby have been
Assessment. adequately instructed
with regard to the
hazards of each other
tasks and processes to

Revision: 0(26-May-2011) Page 3 of 12


HS.SAF.09.F12

reduce risk.
 Ensure that adjacent
work activates and
associated risks are
understood. Stay out of
non-ABB work areas.

 Work with Supv.  Complete and document


hazardous Elec,Hel hazard communications
substances. pers training for employees.
Follow operation 2x2=4
instruction.
 Ensure relevant PPE is
used.
 Avoid skin contact and
inhalation potential.

 Use of tools Supv.  Use proper tools that


Elec,Hel have been inspected
pers Only qualified and trained
employees are allowed to 2x2=4
work.
 All tools must be
inspected on a quarterly
basis and prior to use by
the employee.

 Work with Emal /  Energized parts within


energized SNC working area are
equipment. rep., insulated.
Engr.,
Supv.  Ensure relevant PPE is
used. 3x2=6
Elec
Helpers  Prohibit unauthorized
entry.
 De energized and ground
when possible.

Revision: 0(26-May-2011) Page 4 of 12


HS.SAF.09.F12

 Utilize only qualified and


trained employees.
 Follow operation
instruction.

2.INSTALLATI
ON  No
specific Supv,El  Supervisor to ensure
available ect & approved PTW is 1x3=3
permit. helpers available on site.

Supv,El  Check qualifications prior


ect & to allowing employee to
 Electrocution 2x2=4
helpers work on electrical
systems.

 Unauthorized Supv,El  Ensure that approval is


and untrained ect & obtained from site 2x2=4
staff working helpers management prior to
in an unsafe starting work.
manner

 Unknown Supv,El  Single line must be


aspects of ect & available for review and
circuits can helpers use,updates required
lead to must be reviewed and 3x2=6
electrocution approved.
 Continuous interface with
site management and
client.

 Encountering Supv,El  All work planned for the


energized ect & day must be reviewed
equipment helpers and risks assessed,
thought to be detailed job plan must be 2x2=4
dead. updated daily.
 Ensure that site
management and
installation crew interface
daily.

Revision: 0(26-May-2011) Page 5 of 12


HS.SAF.09.F12

 Failure to Supv  An assessment of


recognize or ,Elect & electrical hazards relative
understand helpers to ongoing work and
risks. adjacent work must be 2x2=4
included in the job hazard
assessment.
 Daily tool box talk
conducted before start
the work .

 Untested tools Supv  Only tools with a current


used ,Elect & certificate of testing will
conducting helpers be used for high voltage
current. work. 2x2=4
 Only use tools that are
appropriate for the task
and have a current
certificate of testing.

2.1Staging and  Crush, knock, Supv  No transport and lift


installing strike, shear, ,Elect & above persons.
equipment etc. helpers
 Crane be qualified and a
lift plan current.
 All lifting equipment must
have a current annual
inspection and inspected
daily.
2x2=4
 Equipment to be secured
against turn over.
 Ensure relevant PPE is
used.
 Inform personal about
working activity. Follow
operation instruction.
 Defect lifting equipment
to be marked and

Revision: 0(26-May-2011) Page 6 of 12


HS.SAF.09.F12

secured against reuse.


 Discuss communication
between Crane driver
and rigger before lifting
activity.

2.2 Installation  Crush, knock, Supv  Only qualified and trained


of GIS strike, shear, ,Elect & employees are allowed to
parts etc. helpers work.
 Relevant PPE to be
used.
 Use the insulated tools 2x2=4
when working on or near
energized equipment.
 Inform personal about
working activity. Follow
operation instruction.
 Only use approved tools
and equipment.

2.3Filling  Release of Emal /  Only qualified and trained


equipment SF6 gas to SNC employees are allowed to
with SF6 the rep., work.
gas Engr.,
environment
Supv.  Relevant PPE to be
Elec used.
Helpers  Use the correct tools. 3x1=3

 Use only closed cycle


system with work SF6
gas.
 Use recycling equipment
to capture the SF6 gas
and make sure that all
connections are secure
and leaks do not occur.

Revision: 0(26-May-2011) Page 7 of 12


HS.SAF.09.F12

 Displacement Emal /  Only qualified and trained


of air by SF6 SNC employees are allowed to
gas rep., work.
Engr.,
Supv.  Relevant PPE to be
Elec used.
Helpers  Use the correct tools.
 Use only closed cycle
system with work SF6
gas.
3x1=3
 Generally provide a good
air supply of the work
space.
 Ventilate all basement
areas to ensure that a
buildup for SF6 in lower
areas is prevented.
 Eating, drinking and
smoking in the work area
are prohibited.
 Warn employee by using
warning signs.
 Follow operation
instruction.
 Prohibit unauthorized
entry.

 Exposure to Emal /  Only qualified and trained


high pressure SNC employees are allowed to
release rep., work.
Engr., 2x2=4
Supv.  Relevant PPE to be
Elec used.
Helpers  Use the correct tools.
 For filling of equipment
follow operation
instruction and gas
layout.
 Warn workplace by
caution label.
 Inform personal about

Revision: 0(26-May-2011) Page 8 of 12


HS.SAF.09.F12

working activity.
 Check the quality of the
pressure hoses.

2.4Evacuate  Release to Emal /  Only qualified and trained


SF6 gas. the SNC employees are allowed to
environment rep., work.
Engr.,
Supv.  Relevant PPE to be
used. 2x2=4
Elec
Helpers  Use the correct tools.
 Use recycling equipment
to recycle SF6 and
ensure that charging
operations stop when any
leak of SF6 is observed.
 Follow operation
instruction.
 Inform personal about
working activity.

 Eliminate air Emal /  Only qualified and trained


by SF6 gas SNC employees are allowed to
rep., work.
Engr., 3x1=3
Supv.  Relevant PPE to be
Elec used.
Helpers  Use the correct tools.
 Use only closed cycle
system with work SF6
gas.
 Ensure that supply
ventilation is used in the
work area.
 Ventilate cavities and
more deeply lying areas.
 Eating, drinking and
smoking in the work area
are prohibited.

Revision: 0(26-May-2011) Page 9 of 12


HS.SAF.09.F12

 Warning Workplace by
caution label.
 Contaminated objects
with SF6 gas to be
separately disposed.
 Consider operating
instruction.
 Follow operation
instruction.
 Prohibit unauthorized
entry.

 High pressure Emal /  Only qualified and trained


SNC employees are allowed to
rep., work.
Engr.,
Supv.  Relevant PPE to be
used. 3x1=3
Elec
Helpers  Use the correct tools
 Warn workplace by
caution label.
 Inform personal about
working activity.
 Check the quality of the
pressure hoses.

2.5Installation  Crush, knock, Emal /  Only qualified and trained


of strike, shear, SNC employees are allowed to
secondary etc. rep., work.
equipment Engr.,
Supv.  Relevant PPE to be
used. 2x2=4
Elec
Helpers  Inform personal about
working activity
 Follow operation
instruction.
 Only use approved tools
and equipment.

Revision: 0(26-May-2011) Page 10 of 12


HS.SAF.09.F12

 Electrical Emal /  Only qualified and trained


shock. SNC employees are allowed to
rep., work.
Engr., 2x2=4
Supv.  Relevant PPE to be
Elec used.
Helpers  Use the correct tools.
 Follow operation
instruction.

2.6Installation  Crush, knock, Supv.  Only qualified and trained


of parts strike, shear, Elec employees are allowed to
etc. Helpers work.
 Relevant PPE to be
used. 2x2=4
 Use the correct tools.
 Follow operation
instruction.
 Inform personal about
working activity.

 Electrical Supv.  Only qualified and trained


shock. Elec employees are allowed to
Helpers work.
 Relevant PPE to be
used. 2x2=4
 Use the correct tools.
 Follow operation
instruction.
 Inform personal about
working activity.

This sheet must be properly completed detailing all of the steps required to complete the job along
with the sequence of events and each of the hazards arising. Failure to properly complete the form
will result in non-approval.

Revision: 0(26-May-2011) Page 11 of 12


HS.SAF.09.F12

(Additional sheets to be used as required)

9. Chemical Analysis (This form to be used as required)

Product Name

MSDS supplied Yes / No

Dangerous Goods Class

Hazardous Material Yes / No

Nature of Hazard Irritation / Carcinogen / Corrosive / Toxic / Other


…………

Form Solid /Liquid / Gas / Dust / Vapour / Mist

Exposure Route Inhalation / Skin / Eye / Ingestion

Number of People Exposed

Duration of Exposure

Frequency of Exposure

Controls to be implemented

Estimate of Exposure Negligible / Marginal / High


This sheet must be properly completed detailing all the necessary information. Failure to
properly complete the form will result in non-approval.

Revision: 0(26-May-2011) Page 12 of 12

You might also like