You are on page 1of 72

Compensation Grouting

Breakthrough in Tunneling Short Course


September 12-15, 2016
Boulder, CO

Dennis W. Boehm
www.HaywardBaker.com
Presentation Outline

• What is Compensation Grouting


• Installation Methods/Monitoring
• Modeling of compensation grouting
• Finite element calculations for compensation
grouting at Antwerp Central Station
• Case Histories
• Summary and conclusions

2
Presentation Outline

• What is Compensation Grouting


• Installation Methods/Monitoring
• Modeling of compensation grouting
• Finite element calculations for compensation
grouting at Antwerp Central Station
• Case Histories
• Summary and conclusions

3
Grouting Processes

4
Compensation Grouting -or- Soilfrac® Grouting

• Originally developed in the oil industry for


fracturing formations to aide in the production of
the well.
• Keller/Hayward Baker developed the process to
accommodate small scale installation process
for the geotechnical construction industry
• Allows precise control of lifting structures and
when coupled with computer monitoring, control
within millimeters

5
Soilfrac® Process

6
Uses for Soilfrac® Grouting

7
Typical Grouting Ranges

8
The injection pipes are made of multiple ported
tubes that allow design placement of grout

Injection Pipe

Sleeve Port Pipe

Grouted Sheeth

Injection Port

Grout

Grout after fracture initiated

Packer

Known as Tube-A-Manchette Pipes

9
Exposed Soilfrac lenses following a single
grout injection

10
Grouting Efficiency

• Ratio of ground volume change to grout volume


injected
• Varies from site to site due to ground conditions

11
Presentation Outline

• What is Compensation Grouting


• Installation Methods/Monitoring
• Modeling of compensation grouting
• Finite element calculations for compensation
grouting at Antwerp Central Station
• Case Histories
• Summary and conclusions

12
Several methods of installing the grout pipes are
available based upon site restrictions

13
Compensation grouting from a shaft

14
Compensation grouting from nearby basement

15
Control of grouting parameters possible in real
time

All grouting parameters


under real time control

Use of computer
controlled pumping
units allow grout
quantities to be
individually controlled
controlled
16
Typical instrumentation types and locations
considered for compensation grouting

17
Sophisticated and non sophisticated methods
allow for movement monitoring

Systems allow monitoring


within 0.005 in
18
Presentation Outline

• What is Compensation Grouting


• Installation Methods/Monitoring
• Modeling of compensation grouting
• Finite element calculations for compensation
grouting at Antwerp Central Station
• Case Histories
• Summary and conclusions

19
Grout Consumption Corresponds to the
Settlement

20
Problem Statement for modeling analyis

21
Comparison of grouting techniques and how they
are modeled

BASIC MODELLING OF THE GROUTING PROCESS AND


DEFINITION OF GROUTED AREA
Volume Volume
V0+∆V V0+∆V
Volume
V0
∆V
∆Vi
a

∆V=Σ∆Vi

initial situation- compaction fracture


grouted area grouting grouting

22
Deformation modes of the grouted zones used in
the modeling
heave
due to grouting
surface
x
O

h
a
grouted zone

∆a0 ∆a´
a

ε = ∆a0 / a δ = ∆a´ / a

Initial ε > 0 contraction δ > 0 vertical shortening


Deformed ε < 0 expansion δ < 0 horizontal shortening

23
Analytical solution proposed by Sageseta (1987)
DISPLACEMENTS AT GROUND SURFACE
2*α −1
a 1  1 − x '2 
sz = 2 * ε * a *   * * 1 + ρ * 
Vertical: h (1 + x' ) 2 α

2 
1 + x' 

2*α −1
a x'  1 − x '2 
Horizontal: s x = −2 * ε * a *   * 1 + ρ * 
h (1 + x' ) 2 α

2 
1 + x' 

sz … vertical displacement
sx … horizontal displacement
h … depth of injection/excavation
a … radius of grouted zone/excavation
x´ … normalized horizontal distance (x/h)
ε … uniform radial deformation
δ … ovalization
ρ… relative ovalization (δ/ε)
α … exponent for drained cases

24
Presentation Outline

• What is Compensation Grouting


• Installation Methods/Monitoring
• Modeling of compensation grouting
• Finite element calculations for compensation
grouting at Antwerp Central Station
• Case Histories
• Summary and conclusions

25
ANTWERP CENTRAL STATION

Historical
Landmark

High Loads
considered

Minimal
movement

26
ANTWERP CENTRAL STATION

 84 TAMs
 3500 m borings
 45 m max. length

shaft

TAMs
shaft

wells

picture: Eurostation, Brussels

27
ANTWERP CENTRAL STATION

pipe roof

tunnel wall

picture:
Graphic:
Eurostation,
Eurostation,
Brussels
Brussels
28
ANTWERP CENTRAL STATION

+8.0 m

0.0 m

A B C D E F G H pipe roof

-13.0 m tunnel

Boomse Clay

29
Compensation Grouting efficiency at Antwerp
Station

30
FE-CALCULATIONS ANTWERP PROJECT
FINITE ELEMENT MODEL

P 455 P 470

foundations

conditioned zone
pipes A-B-C-D

tunnel

Antwerp Sand

Boomse Clay
COMPARISON MEASUREMENT – FE-MODEL
VERTICAL DISPLACEMENTS AT WATER LEVEL POINT P455
3,0

2,5
displacement [mm]

2,0

1,5

1,0

measurement P455
0,5 calculation P455

0,0
g

t.

C
*

v.
B

A
B*

C
in

ca
p.
pe

pe

p.
pe
ro
nn

p.

p.

pe
m

ex
m
tg

pi

pi
pi
m

m
gi

pi
co

co
co

co
ac

el
be

nn
nt
co

tu
COMPARISON MEASUREMENT FE-
MODEL
VERTICAL DISPLACEMENTS AT WATER LEVEL POINT P470
3,5

3,0
displacement [mm]

2,5

2,0

1,5

1,0
measurement P470
0,5 calculation P470

0,0
g

t.

C
A

v.
B

A
B*

C
in

ca
p.
pe

pe

p.
pe
ro
nn

p.

p.

pe
m

ex
m
tg

pi

pi
pi
m

m
gi

pi
co

co
co

co
ac

el
be

nn
nt
co

tu
Presentation Outline

• What is Compensation Grouting


• Installation Methods/Monitoring
• Modeling of compensation grouting
• Finite element calculations for compensation
grouting at Antwerp Central Station
• Case Histories
• Summary and conclusions

34
Soilfrac® - City-Tunnel Leipzig
Central Station
„Bayrischer Bahnhof“

Wilh. Leuschner Platz


Central Station
Station Markt
Soilfrac® - City-Tunnel Leipzig
Drilling
Soilfrac® - City-Tunnel Leipzig
Control of drilling deviation
Soilfrac® - City-Tunnel Leipzig
Monitoring
Soilfrac® - City-Tunnel Leipzig
Grout control

Vertical displacement
Grout volume

TAM
Project “San Ruffillo”, Bologna, Italy
N Tunnel excavation
 twin tunnels
with 15m
distance

www.KellerGrundbau.com
length 6,112m
 diameter 9.4m
 excavated
area 69.81m²
 cover 15 –
21m
 EPB-shield

Start shaft Pk 0+966

Compensation
grouting
To Florence
Problem statement
expected volume loss of the TBM-excavation: 1%
maximum advancement of the TBM: 10m/day
Compensation of differential settlements of piers
Allowable differential settlement: Δ uij <= l/3000

pier i pier j

displacement i
displacement j

span l
www.KellerGrundbau.com
Compensation grouting “San Ruffillo”
TYPICAL CROSS SECTION

Original design with SHAFT

www.KellerGrundbau.com
railway bridge
fill
sand

gravel, sandy,
shaft silty

grouting pipes
2 layers

tunnel
9.1m diameter
Compensation grouting “San Ruffillo”
TYPICAL CROSS SECTION

railway bridge

fill
sand
grouting pipes
2 layers gravel, sandy,
maximum length 68m silty
HDD-drilling

tunnel
9.1m diameter

w43
Compensation grouting “Via Emilia”
existing railway
bridge
length 112m
1 central arch (l=16.0m)

www.KellerGrundbau.com
8 lateral arches (l=8.1m) Florence
Milano

Via Emilia Levante


Compensation grouting “Via Rimesse”

Milano Florence

existing railway

www.KellerGrundbau.com
bridge
length 41m
1 central arch (l=14.4m)
2 lateral arches (l=7.2m)

Metro line („Suburbana“)


Compensation grouting “Via Rimesse”

Upper circuit > vertical displacements

transition point

Lower circuit > monitoring of vertical


displacements (and rotations)

w46
Compensation grouting “Via Rimesse”
Displacements resulting after TBM 2
> Maximum differential settlement 1.9mm

www.KellerGrundbau.com
Compensation grouting “Via Rimesse”

3D graph of total grout volume

www.KellerGrundbau.com
San Francisco 3rd Street Light Rail - Central Subway
Drilling and Grouting Programs
 Chinatown Station (CTS)
 Issue: Adjacent Building Settlement along
Station Excavation
 Solution: Compensation Grouting
 Union Market Square Station (UMS)
 Issue: Adjacent Building Settlement along
Station Excavation
 Solution: Compensation Grouting

9/26/2016 49
3rd Street Light Rail - Central Subway
Project Alignment

Chinatown
Station (CTS)

Union Market
Square Station
(UMS)

Moscone
Station (YBM)

9/26/2016 50
CTS Compensation Grouting
Pre-conditioning Statistics
 Total Installed Grout Holes = 94
 Drilling Rigs = 2 on 2 Shifts
 TAM Installed = 13,320 LFT
 TAM Installation Rate = 73 LFT / Rig Shift
 Whips = 4
 Grout Injected = 86,000 Gal
 Grout Injection Rate = 1385 Gal / Shift
 Treatment = 10 Buildings – 41,150 Sq. Ft.
 Completed 10/08/15

9/26/2016 51
CTS Compensation Grouting
TAM Pipe Array

9/26/2016 52
CTS Compensation Grouting

Drilling and TAM Installation


9/26/2016 53
CTS Compensation Grouting

Pre-conditioning Grouting
9/26/2016 54
UMS Compensation Grouting
Pre-conditioning Statistics
 Total Grout Holes = 209
 Drilling Rigs = 1 on 2 Shifts
 TAM Installed = 19,605 LFT
 TAM Installation Rate = 94 LFT / Rig Shift
 Whips = 4
 Grout Injected = 204,000 Gal
 Grout Injection Rate = 1416 Gal / Shift
 Treatment = 15 Buildings – 126,815 Sq. Ft.
 Anticipated Completion = September 2016
9/26/2016 55
UMS Compensation Grouting
TAM Pipe Array

9/26/2016 56
UMS Compensation Grouting

Drilling and TAM Installation


9/26/2016 57
UMS Compensation Grouting

Pre-conditioning Grouting
9/26/2016 58
Case History
Annunciation Church
Layout of Soilfrac® Pipes and Jet Grout
Columns
Amount of Movement Required
Sleeve Pipe Installation
Frac Grouting
Results of Survey
Grouting Recap

 Installed 93 full and half triple system jet grout


columns to depths exceeding 25 feet.
 Installed 86 Soilfrac® pipes and pumped 4,178
cft of grout
 Achieved plumbness within 0.12° of perfectly
plumb from 0.44° and 0.34°, 65 to 75%
correction.
A New Foundation for
Years to Come
Compensation Grouting Program at
Jack II
• Access Shaft
• 34 Secant Piles
• Monitoring Instrumentation
• Getec UK
• Hydrostatic Leveling Cells (HLC)
• Tiltmeters
• Extensometers
• Preconditioning of TAM pipes
• 3500+ ports
• 5200 CFT grout
• Compensation Grouting
• 9000 CFT grout

67
Compensation Grouting

Isometric View Looking Southwest

68
Compensation Grouting
• Grouting Efficiency Factor
• 12 Quadrants
• GEF = (Grout Tributary Area*Avg. Heave)/Grout Volume

69
Compensation Grouting

Soil
Frac
Pipes

70
SUMMARY and CONCLUSIONS

• Finite element model proposed to simulate the


effects of compensation grouting
• Numerical model compares well with analytical
solution for elastic, undrained behaviour
• Compensation grouting allows for quicker
tunnelling applications
• Precise levelling of sensitive structures is more
efficient with compensation grouting
• HDD installation procedures extend the
treatment possible on project sites

71
This is the Last Slide
Thank You!! Questions?

Dennis W. Boehm
dwboehm@haywardbaker.com
281-668-1870
72

You might also like