WORK METHOD STATEMENT

WMS Rev.No 0

ACTIVITY: CIVIL WORK COMPANY NAME DATE xxxx

DESCRIPTION OF CONCRETE POURING/REPAIRING WORKS,REBAR WORK,FORM PROJECT SITE/ LOCATION


BNPP/PPS –EAST OCA AREA
WORK WORK,PIPING WORK, WATER PROOFING WORK,EXACAVATION,
BACKFILLING & SCAFFOLDING WORKS
CONTACT NO. 050-1366523

JHA REF. NO.


PERSON COMPLETING THIS STATEMENT: KARTHIK BABU
JHA REV. NO. 0

Task Step
Tool and Equipment Required Description of Work (In detail) Remarks
(Activity)

1. Start-up checks 1. Surveying Equipment’s 1. Ground conditions to be assessed by the soil investigation reports 1. Refer to the procedures BNPP-HSE-
prior to work 2. Clearance from the relevant authorities to be taken P28.
3. Preliminary Survey to be carried out to plot the existing ground profile 2. Before start the activity conduct TBM
4. Necessary Road signages & safety signages & barricading to be done 3. Barricading the area and visible
signed.
4. First Aider to be available.
5. Methods to be available and followed.

2. Piping installation in the


excavation  Conduit glue, coupling Proper material arrangement and shifting materials to the excavation. Lay out of
area(PVC,HDPE Pipe)  pipe pipe and join with Pipe glue & butt fusion welding machine. Maintain manual
 Roller handling training procedure[BNPP-HSE-P39]
 Butt fusion welding machine

Page 1 of 6
3.Hydro testing filling -Hydro test equipment -Remind all workers through TBM to use only the right tools for the job.
of water from mainline -Ensure equipement should be in good condition.
-Water pump
water supply using -Test area must be rounded by hard barricade.
-Unauthorized entry
pump
-Whip lashing of water hose
-High pressure
-Failure of hydro test equipent
-Over pressure
-Water spillage

3.Draining -Water pump PPE (Safety helmet, Coverall, High visibility vest, Safety glass, Safety
/Dewatering using -Spark shoes, Hand gloves, Full face shield ,welding mask, apron)
water pump -Welding area must be adequately ventilated to take away fumes.
-Hot surfaces
-Fire -Flammable materials must be removed from areas where gas cutting
works is to be undertaken.
-Explosion
-Electrocution

4. Installation Rebar
1. The surface of the reinforcing steel bar to be placed shall be free
from loss mortar, dirt, mud, oil, ice, snow or other nonmetallic
1.spreader beam coatings that adversely affect bonding capacity
2.moblie crane 2. Reinforcing steel bars shall be securely tied with No.16 or heavier
3.tower crane gauge tie wires and shall be held in position by approved supports
3. All size of reinforcing steel bars shall be in accordance to Drawing.

Page 2 of 6
5. Repair of concrete 1) Imperfections in formed concrete shall be repaired as soon as practicable after removal
surface 1. Grinders
of forms, imperfections in sound concrete shall be removed by chipping with
2. Pneumatic Chisel heads
perpendicular chip edges.
3. Power Tools
2) No feather edges shall be permitted
4. Drilling & Grinding
3) Application of the adhesive shall conform to the manufacturer’s written instruction.
Machine
After repair, all filling shall be bonded tightly to the surface of the holes.
5. Leak injection machine 4) Repair, except for tie rod holes shall be cured in accordance to curing section
mentioned above

Page 3 of 6
6.Erection &
Dismantling Of  Mobile Crane 1. Mobilization of materials shall be done with due safety and care 1. Refer to the procedures BNPP-HSE-
2. Remind all workers through TBM to use only the right tools for the P21 and BNPP-HSE-P25, P39.
Scaffolding  Boom Truck
job. 2. The workers shall be physically &
 Hand Tools
3. Examine each tools for any signs of damage and removed psychologically fit.
 Spirit level. immediately from service if found defective. 3. Closely monitored the supervisor by
4. Keep tools in good condition and store it properly at designated qualified experienced and trained.
storage room or tool box after usage
5. Timber shall be placed at the base to support the scaffold
6. The standards, and the entire cup lock system shall be set up as
per approved drawings and by authorized personnel.
7. Bracing tubes, universal clamps other such support mechanisms
shall be placed at designated areas for proper supports
8. To provide protection to the workers guard rails shall be provided
at appropriate heights and also toe board shall be installed to
prevent the falling of objects from scaffolding heights
9. Lifting area to be covered and appropriate signages to be
posted.Tag line to be placed at corners of loads,
10. Ensure load is balance, stable and secure during lifting.
11. All working platforms to be erected by competent personnel as
close as possible to reinforcement bar locations to prevent steel
fixers over reaching
12. Remove all obstruction in pathways.
13. Tools and materials to be secured with tool tie or place din
secured storage container.
14. Competent supervision and tool box meeting
15. PPE (Safety helmet, Coverall, Safety glass, Safety shoes, Hand
gloves)

Page 4 of 6
7. FORMWORK – 1. mobile crane/crawler 1. Form design shall include considerations of the following
fabrication, installation &
de shuttering crane/tower crane/Hiab Truck i. Rate and method of placing concrete
etc.
ii. Density of concrete
iii. Construction loads including vertical, horizontal and
impact loads
2. Forms shall be readily removable, without the injury of concrete.
Forms shall be wood, metal, structural hardboard or other suitable
material that will produce the required surface finish

8.Assemble, laying 1. Mobile Crane 1. All personnel not to exceed 15kg for manual lifting capacity.
and installation of 2. Hand Tools 2. Supervisor to ensure safe work rest period when personnel are
Waterproofing repetitive manual lifting.
Membrane System
3. Use mechanical means whenever possible
4. PPE (Safety helmet, Coverall, Safety glass, Safety shoes, Hand
gloves)
9. Excavation & 1.Backhoe loader 1. The area to be excavated shall be properly mark and clear before
Backfilling 2.JCB starting the work
3.Excavator 2. The depth of excavated shall be periodically checked by a surveyor to
avoid over excavation. The bank of excavated area shall be slope 30
degrees and shall be maintained to avoid collapse of bank into the
excavated area.
3. All excavated materials shall be kept minimum of 1.0 meter from the
edge of excavation or shall be shock piled to the area designated by the
engineer
4. For all excavation activities, adequate safety barriers, sign boards,
advance warning signs would be used.

Page 5 of 6
10. PLACING OF 1. Concrete Pump Car 1. Placing equipment shall be of adequate size and capacity to handle the concrete
CONCRETE & Grout
a. Lean concrete, 2. Conveyors mixes furnished. Conveying and placing shall be in accordance with the ACI
Screed concrete, 3. Chutes regulations.
Mud mat,
2. Before depositing concrete, all placing equipment shall be cleaned. All compacted
soil, rock or concrete surfaces to receive concrete shall be thoroughly moistened
before placement
3. The free fall of concrete shall be limited to approximately 6ft. (1892mm). The
horizontal flow within the mass from the point of deposition shall be limited to
approximately 5ft.(1524mm)
4. The concrete placing shall be completed within 1 ½ hours after introduction of
the mixing water to the cement and aggregates
5. Concrete shall be deposited in layers not deeper than 24 in. (610mm), the step
method of placement as described in Section 5.6 in ACI 304R shall be followed
for mass concreting in order to minimize the occurrence of cold joints
6. Concrete shall be deposited at or near its final placement position and shall not
be caused to flow such that the lateral movement will permit or cause segregation
of the coarse aggregate, mortar or water from the concrete mass.
7. Concrete and the exposed surface of fresh concrete shall be protected from rain
and snow during and after placement