Company Name: Rakan Trading and Contracting Company
Contract Name: P&C of Labor Camp – Phase 1
Contract No: 021-C09
Document Number: 01-746-00
1. Description of Works
3. Access/Egress
SEE ATTACHED TMP
6. Work Methodology
f) Wipe the ground areas with clean solvent / cloth to remove the collected dust
and any surface moisture
g) Ensure prepared surface area is cleaned, dry and free of dust prior for
lamination.
4. Assembly of manholes and rings using Butt-Wrap Lamination
a) Once the surface is ready for the lamination then proceed for the alignment
of manholes and rings.
b) Align each pipes and fittings for joint correctly with approximately 3-10 mm
root gap for lamination.
c) Align properly by adjusting the pipe and until required levelness achieved &
accurate dimension.
d) Before commence for lamination ensure the ends of the pipes and fittings are
squared and aligned perfectly.
e) Upon securing the required alignment, squared edges and dimension then
proceed for lamination.
f) Upon securing the position of the new spool, proceed on applying the putty
on the gap, completely filling it with no visible trace of void or hollows. Allow to
harden and dry.
g) Once the putty is cured commence the lamination.
h) Lamination should be avoided in foggy conditions when temperature ≤22°C
and humidity is ≥ 75. And, lamination should be avoided at high temperature
(temperature ≥ 40°C)
i) Lamination activities shall not stop in between unless the resin cured. If resin
is cured before completion of required number of layers, the activities shall be
stopped until the joint cured completely (it will take approximately 1 hour), and
the balance number of layers shall be completed after preparing the surface.
j) Mix manually the resin and hardener in a clean dry plastic bucket using a
clean and dry wooden stick as per quantity specified in recipe to maintain the
right ratio.
k) The lamination kits of this repair includes resin, Catalyst, Woven roving, CSM
and top tape
l) Each layer of consists of one full wrap of woven roving impregnated with
resin.
m) Joint lamination for each joint is divided in two part;
m.1 Application of fit-up layers
i. The functions of the fit layer are, firstly to ensure proper positioning and
secondly, to create a seal (see Fig. below).
x. Wind 2 layers of top tape glass around the laminate to extract the excess
quantity of resin and to provide smooth surface.
xi. The joint is undisturbed until it cures under ambient temperature. The
curing time varies between 16 to 24 hours depending on the sunlight exposure
and temperature
Note: No Laminating machine involve. All activities will be executed outside the
manhole no Confined Space Entry will be involved.
5. Pressure test:
After completion of all activities at site, service test of line shall be carried out at
operating pressure.
7. Resources
48” GRP RING for corrosion resistant and can be used for a wide range of
applications, such as cooling water, industrial waste water and
effluents, fire water lines, seawater lines, acid cleaning and
chlorination lines.
C-veil (tissue) , Woven roving & Key role in forming the corrosion barrier's inner liner by acting as
CSM (Chopped Strand Mat) the carrier and stabilizer for the resin.
Measuring tape, pipe fitter’s For measuring purpose
wrap-around, marker pen,
Cleaning rags
Rotary disc grinder with For cutting and sanding
carborundum cutting & sanding
disc
Pair of scissors For cutting
Mixing tongue/stick and buckets For mixing chemical
Brushes, rollers Use for painting
Graduated Catalyst Dispenser Measuring the mixture
Styrene For cleaning
C-clamp, Emery cup, Backing disc For tighten
pad, Rubber mandrel
Barcol hardness tester Used to determine the hardness of both reinforced and non-
reinforced rigid plastics.
d. Chemicals Required
Item MSDS Number Specific Requirements
1 105 epoxy resin Wear protective chemical resistant gloves
/protective clothing/eye protection/face
protection. Eye wash station.
2 CORVE8190 Wear protective gloves/protective
clothing/eye protection/face protection. Eye
wash station.
3 EXH300, EXH900, EXH904, Wear protective gloves/protective
EXH905, EXH906, EXH001 clothing/eye protection/face protection. Eye
wash station.
Note that all works require mandatory PPE as follows Hardhat, gloves, safety glasses, safety
boots, hi-vis vest.
9. Permits
Any Permits Required (from RC ESH Manual or 3rd Party)
Permit Type Issued By Additional Information (Reference No. etc)
Hot work Foreman Inspected and verified by safety officer
Emergency Procedure:
1. At the first instance of incident worker should report directly to the foreman, safety officers, nurse or
to the engineer in charge.
2. Stay calm and do not panic.
3. While waiting if situation requires and does not affect the integrity of the patient, bring him in the
clear and fresh area.
4. Do not attempt to help or rescue if not trained or not ask to do so.
5. Do not block at anytime, make the path accessible for the rescue.
6. Upon the arrival of the rescue team, do not interrupt or attempt to help if you are not ask to do it.
The following contact person will be posted and displayed in a prominent areas and notify them in case
of emergency.
All incident must be investigated and reported to the RC Construction Department in timely mannered
as per accident notification and investigation
P&C OF LABOR CAMP PHASE-1
Contract # 021-C09
REGULATORY
ENGR. MAHMOUD J. ABUKABEER ENGR. MOHAMMED AL-DESTAWI MR. MUHAMMAD ISHAQ AGENCIES /
PROJECT MANAGER CONSTRUCTION MANAGER SAFETY MANAGER
THIRD PARTIES
050-5903-785 057-8859-957 056-2008-281
TESTING EQUIPMENT
S/N NAME TPC EXPIRY DATE REMARKS
1 Safety Relief Valve (Calibration Certificate) To be followed Third Party
2 Pressure Gauge (Calibration Certificate) To be followed Third Party
3 Manifold (Inspection Certificate) To be followed Third Party