Classic Schedule Layout Replacement of 34" inch GAS Pipeline Section X 11 Km PR-171-37

Activity ID Activity Name Start Planned Finish MMMMM A A A A MMMM J J J J J J J J J A A A A S S S S S O OO O N N N N D D D D D J J J J F F F F MMMM M A A A A MMMM M J J J J J J J J A A A A A S S S S O O OO N N N N N D D

11km-1 11 Km updated 14-Mar-19 A 20-Apr-20 20-Apr-20, 11km-1 11 Km updated

11km-1.11 Mobilisation and site preparation 14-Mar-19 A 01-Jan-20 01-Jan-20, 11km-1.11 Mobilisation and site preparation

A1000 Mobilisation & site preparation 14-Mar-19 A 01-Jan-20 Mobilisation & site preparation
11km-1.4 Engineering Documentation 14-Mar-19 A 30-Jan-20 30-Jan-20, 11km-1.4 Engineering Documentation

A1010 Engineering Documentation 14-Mar-19 A 30-Jan-20 Engineering Documentation


11km-1.7 Procurement of material 14-Mar-19 A 29-Feb-20 29-Feb-20, 11km-1.7 Procurement of material

A1020 Procurement of mterial 14-Mar-19 A 29-Feb-20 Procurement of mterial


11km-1.12 Training Session of SOC Engineering 01-Apr-20 15-Apr-20 15-Apr-20, 11km-1.12 Training Session of SOC Engineering

A1030 Training Sessio n 01-Apr-20* 15-Apr-20 Training Sessio n


11km-1.3 Right of way 25-Jun-19 A 29-Feb-20 29-Feb-20, 11km-1.3 Right of way

A1040 Land Surevy and identification of pipe route 25-Jun-19 A 29-Feb-20 Land Surevy and identification of pipe route
A1050 Removal of vegetal layer 25-Jun-19 A 29-Feb-20 Removal of vegetal layer
A1060 Grading and clearance of ROW 25-Jun-19 A 29-Feb-20 Grading and clearance of ROW
A1070 Identification of existing line alignement 25-Jun-19 A 29-Feb-20 Identification of existing line alignement
A1080 Benchmarking new line axis 25-Jun-19 A 29-Feb-20 Benchmarking new line axis
A1090 Seeting up sand bags for stringing 25-Jun-19 A 29-Feb-20 Seeting up sand bags for stringing
11km-1.8 Pipeline transportation and stringing 14-Mar-19 A 16-Nov-19 16-Nov-19 A, 11km-1.8 Pipeline transportation and stringing

A1100 Pipeline transportation and stringing 14-Mar-19 A 16-Nov-19 Pipeline transportation and stringing
11km-1.13 Topographic Survey 25-Jun-19 A 29-Feb-20 29-Feb-20, 11km-1.13 Topographic Survey

A1110 Surveying the ROW and generating the original file 25-Jun-19 A 29-Feb-20 Surveying the ROW and generating the original file
A1120 Identification of trench 25-Jun-19 A 29-Feb-20 Identification of trench
A1130 Topographic Survey during excavation 25-Jun-19 A 29-Feb-20 Topographic Survey during excavation
15-Sep-19 A
11km-1.2 Concrete Works CET ON WEIGHT for pipe support 29-Feb-20 29-Feb-20, 11km-1.2 Concrete Works CET ON WEIGHT for pipe support

A1140 Preparation Of steel shelters formworks and concreting works 15-Sep-19 A 29-Feb-20 Preparation Of steel shelters formworks and concreting works
A1150 Casting of concrete saddle block (Total required numbers) 15-Sep-19 A 29-Feb-20 Casting of concrete saddle block (Total required numbers)
A1160 Installation of concrete saddle block over the pipe and protective
15-Sep-19
coatingsA( Total required
29-Feb-20
number) Installation of concrete saddle block over the pipe and protective coatings ( Total required number)
A1170 Installation inspection and released for backfilling 15-Sep-19 A 29-Feb-20 Installation inspection and released for backfilling

11km-1.9 Welding and NDT 27-Jul-19 A 29-Feb-20 29-Feb-20, 11km-1.9 Welding and NDT
A1180 Alignment, Fit up and welding of total joints 27-Jul-19 A 29-Feb-20 Alignment, Fit up and welding of total joints
A1190 completion of radiographic test 27-Jul-19 A 29-Feb-20 completion of radiographic test
A1200 Installation of heat shrinkable sleeve 27-Jul-19 A 29-Feb-20 Installation of heat shrinkable sleeve
A1210 Completion of pinhole test 27-Jul-19 A 29-Feb-20 Completion of pinhole test
11km-1.14 Trenching Work 12-Dec-19 07-Mar-20 07-Mar-20, 11km-1.14 Trenching Work

A1220 Marking of trench centre line and borders 12-Dec-19* 07-Mar-20 Marking of trench centre line and borders
11km-1.1 Construction of reinforced concrete 01-Feb-20
pit for valve 05-Mar-20 05-Mar-20, 11km-1.1 Construction of reinforced concrete pit for valve

A1260 Construction of reinforced concrete pit for valve 01-Feb-20* 05-Mar-20 Construction of reinforced concrete pit for valve
11km-1.10 Pipeline road crossing 15-Jan-20 15-Feb-20 15-Feb-20, 11km-1.10 Pipeline road crossing

A1270 Pipeline road crossing 15-Jan-20* 15-Feb-20 Pipeline road crossing


11km-1.15 Pipeline Lowering in 28-Dec-19 21-Mar-20 21-Mar-20, 11km-1.15 Pipeline Lowering in

A1320 Pipeline Lowering in 28-Dec-19* 21-Mar-20 Pipeline Lowering in


11km-1.15.1 Connection of sections in trench 01-Mar-20 30-Mar-20 30-Mar-20, 11km-1.15.1 Connection of sections in trench
A1330 Connection of sections in trench 01-Mar-20* 30-Mar-20 Connection of sections in trench

11km-1.5 Backfilling 14-Dec-19 17-Mar-20 17-Mar-20, 11km-1.5 Backfilling


A1340 Backfilling 14-Dec-19* 17-Mar-20 Backfilling

11km-1.16 Hydrotest 22-Mar-20 11-Apr-20 11-Apr-20, 11km-1.16 Hydrotest


A1350 Hydrotest 22-Mar-20* 11-Apr-20 Hydrotest

11km-1.17 CP test point installation 15-Jan-20 30-Jan-20 30-Jan-20, 11km-1.17 CP test point installation
A1360 CP Test Point Installation 15-Jan-20* 30-Jan-20 CP Test Point Installation

11km-1.18 Cold Cut of the existing line & Tie in 21-Mar-20 31-Mar-20 31-Mar-20, 11km-1.18 Cold Cut of the existing line & Tie in
A1370 Cold Cut of the existing line & Tie in 21-Mar-20* 31-Mar-20 Cold Cut of the existing line & Tie in

11km-1.20 Reinstatement and Housekeeping 12-Apr-20 19-Apr-20 19-Apr-20, 11km-1.20 Reinstatement and Housekeeping
A1380 Reinstatement and Housekeeping 12-Apr-20* 19-Apr-20 Reinstatement and Housekeeping

11km-1.6 As builts drawings 20-Apr-20 20-Apr-20 20-Apr-20, 11km-1.6 As builts drawings

A1390 As builts drawings 20-Apr-20* As builts drawings, 20-Apr-20*

Actual Level of Effort Remaining Work Milestone Page 1 of 1


Actual Work Critical Remaining Work summary