Project Ejemplo

Solve

Change Gantt

Critical Graph

Update Schedule

Activity Data Activity Time Estimates


Most
Critical Name Description Predecessors Color Min. Likely Max.
1 1 Start Activity Start 0 0 0
2 0 A Activity A 1 2 3
3 1 B Activity B 2 3 4
4 0 C Activity C A 4 5 6
5 1 D Activity D B 8 9 10
6 1 E Activity E C D 2 5 8
7 0 F Activity F D 4 5 6
8 1 G Activity G E 1 2 3
9 1 End Activity End 0 0 0
6
Times(Proj. Weeks)
Due 19
Critical 19
Var. 1.3333
SD. 1.1547
On Time Prob. 0.5
Slack 0
Late 0
Current 0

Schedule Limits Schedule Decisions


Time Activity Early Late Early Late Sched. Sched.
Mean S.D. Var. Weeks Delay Sort Start Start Finish Finish Slack Start Finish
0 0 0 0 0 1 0 0 0 0 0 0 0
2 0.3333 0.1111 2 0 2 0 5 2 7 5 0 2
3 0.3333 0.1111 3 0 3 0 0 3 3 0 0 3
5 0.3333 0.1111 5 0 4 2 7 7 12 5 2 7
9 0.3333 0.1111 9 0 5 3 3 12 12 0 3 12
5 1 1 5 0 6 12 12 17 17 0 12 17
5 0.3333 0.1111 5 0 7 12 14 17 19 2 12 17
2 0.3333 0.1111 2 0 8 17 17 19 19 0 17 19
0 0 0 0 0 9 19 19 19 19 0 19 19
Gantt Parmeters
Bucket 1
Start 0
Horizon 19
Extra 1

dule Decisions Gantt Chart


Perc. Proj. Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Finished Time 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0% Activity Start 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0% Activity A 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0% Activity B 2 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0% Activity C 0 0 2 2 2 2 2 0 0 0 0 0 0 0 0 0 0
0% Activity D 0 0 0 2 2 2 2 2 2 2 2 2 0 0 0 0 0
0% Activity E 0 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 2
0% Activity F 0 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 2
0% Activity G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0% Activity End 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
18 19 20
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
2 2 0
0 0 0
Project Graphic Ejemplo

Name Start(1) Name A(2) Name C(4) Name E(6)


Time 0 Time 2 Time 5 Time 5
Slack 0 Slack 5 Slack 5 Slack 0
Start 0 Start 0 Start 2 Start 12
Finish 0 Finish 2 Finish 7 Finish 17

Name B(3) Name D(5) Name F(7)


Time 3 Time 9 Time 5
Slack 0 Slack 0 Slack 2
Start 0 Start 3 Start 12
Finish 3 Finish 12 Finish 17
Name G(8) Name End(9)
Time 2 Time 0
Slack 0 Slack 0
Start 17 Start 19
Finish 19 Finish 19
Network Ejemplo

Activity on Node Network


Sorted Activity Nodes Sorted Precedence Arcs
From To From To Critical
Index Sort Name Level Depth Index Index Index Name Name Arc
1 1 Start 0 0 1 1 2 Start A 0
2 2 A 1 0 2 1 3 Start B 1
3 3 B 1 1 3 2 4 A C 0
4 4 C 2 0 4 3 5 B D 1
5 5 D 2 1 5 4 6 C E 0
6 6 E 3 0 6 5 6 D E 1
7 7 F 3 1 7 5 7 D F 0
8 8 G 4 0 8 6 8 E G 1
9 9 End 5 0 9 7 9 F End 0
10 8 9 G End 1