Professional Documents
Culture Documents
HOT WEATHER
CONCRETING
1
25/04/1433
2
25/04/1433
3
25/04/1433
4
25/04/1433
5
25/04/1433
Estimate
evaporation rate.
Take precautions
if rate approaches
1 kg/m2/hr.
At 21oC concrete
and air
temperature, 50%
relative humidity,
rate of
evaporation at 16
km/hr is six times
larger than rate
when there is no
wind.
6
25/04/1433
7
25/04/1433
Effect of
concrete
temperature on
slump and on
water required
to change
slump
8
25/04/1433
9
25/04/1433
Water Requirements
1- At high temperature, larger amount of water is
required to increase the slump
2- Water has specific heat 4 times larger than
other ingredients, hence it has greatest effect
per unit weight on concrete temperature
3- Lowering water temperature by 4oC decreases
concrete strength by about 1oC
Water Requirements
10
25/04/1433
Effect of Cement
Slower hydrating cements reduces peak
temperature, and thermal cracking
Limit temperature of delivered cement
11
25/04/1433
Aggregates
60 to 80 % of concrete
Affect concrete properties
12
25/04/1433
Temperature Control
13
25/04/1433
Temperature Control
Temperature Control
Paint mixer surface white to reduce solar heat
gain. For 1 hour delivery, concrete in clean
white drum is about 1 to 1.5oC cooler than
black or red drum and 0.3oC cooler than
cream-colored drum
Spraying drum with water before batching
gives only a marginal benefit
Chill batch water by water chillers, cool by
liquid Nitrogen, or use crushed or flaked ice
Production requires planning well in advance
of placement and installation of specialized
equipment
14
25/04/1433
15
25/04/1433
Delivery
16
25/04/1433
Delivery
With passage of time:
Cement hydration
Temperature rise
Slump loss
Aggregate grinding
Slump Adjustment
Establish slump change between plant and
jobsite (accuracy of predicting slump limited)
If slump lower than required on arrival, water
may be added if maximum allowable water
content is not exceeded
If water added, drum or blades turned 30
revolutions at mixing speed
75 to 100 mm slump necessary for expeditious
placement of structural concrete
Can adjust slump using chemical admixtures if
not expected to cause segregation potential
17
25/04/1433
Retempering
Defined as in ACI 166 as “additions of water
and remixing concrete, or mortar which has
lost enough workability to become implacable
or unsaleable”
Strength reduction and other detrimental
effects proportional to amount of retempering
water added
Retempering prohibited
Adding Admixtures (HRWR) is very effective
to maintain workability
18
25/04/1433
Placing
Procedure under HWC similar to good practice
under normal conditions
Concrete handled and transported with
minimum segregation and sump loss
Placed where to remain
Placed in shallow layers (to assure vibration
well into layer below)
Minimize elapsed time between layers to avoid
cold joint
Joints made on sound, clean concrete
Curing
19
25/04/1433
20
25/04/1433
21
25/04/1433
22
25/04/1433
23
25/04/1433
24
25/04/1433
25
25/04/1433
26
25/04/1433
27
25/04/1433
28
25/04/1433
Testing
Testing on fresh concrete in accordance with
ASTM C 31, C 138, C 143, C 172, C 173, C
231, C 1064 so that sample is as representative
of actual structure as possible
Leaving sample exposed to hot sun, wind, or
dry air seriously impair accuracy and
usefulness of results
Desirable to conduct more tests than desirable
(temperature of materials, initial and final time
of set, slump loss, ambient temperature,
relative humidity when concrete is placed)
Testing
Plastic shrinkage is affected by evaporation
rate, which can be measured using a cake pan
(about 1ft2 = 0.093 m2 in area): Pan is filled
with water and weighed every 15 to 20 minutes
Particular attention to protection and curing of
strength test specimens used as basis for
acceptance (extra effort to keep their
temperature between 16 to 27oC and avoid
moisture loss during initial curing period
(ASTM C 31)
Provide sample with impervious cover if
possible
29
25/04/1433
Testing
If stored outside, avoid exposure to sun
In non-potentially absorptive test molds,
– Embed in damp sand (continuously moist)
– Cover with burlap (continuously moist)
– Continuous fog spray
– Total immersion in water (cement is hydraulic),
need not covered with cap, but generally are
Mold must not be potentially absorptive
Maintain moisture during transfer to test facility
Testing
Additional specimens made and cured at
jobsite to assist in determining when forms
can be removed, when shoring can be
removed, and when structure can be put in
service
30
25/04/1433
Inspection
Details in ACI 311.1R and 311.4R
Project inspection to insure compliance with
additional HWC precautions and procedures
– Spraying forms and subgrade
– Providing sunshades, windscreens
– Fogging, etc…
Compliance verified and documented
Record air and concrete temperature (ASTM C
1064) at frequent intervals
Inspection
Record wind velocity, relative humidity,
evaporation rate, at frequent intervals
Record information on:
– All water added to mixture and corresponding
mixture time
– Time batched, time batch started and completed
– Concrete temperature at time of delivery and after
placing
– Observations of performance and appearance of
concrete as delivered and after placing in forms
31
25/04/1433
Inspection
Slump of concrete as delivered
Slump of concrete as discharged
Protection and curing
– Method
– Time of application
– Rate of application
– Visual appearance
– Duration of curing
Observations should be included in permanent
project records
32