You are on page 1of 5

QA/QC

METHOD STATEMENT

METHOD STATEMENT FOR CONCRETE SLAB CUTTING


(HALFSLAB AND HOLLOWCORE SLAB)

CLARK INTERNATIONAL AIRPORT PROJECT

PREPARED BY NOTED BY:


NAME Alfred L. Comendador Einstein O. Chiu
TITLE QA/QC M - Precast AVP - Precast
DATE 04 Jan. 2019 04 Jan. 2019

SIGNATURE

MS CODE NO.: MCCMS-5.1-1


REVISION : 00
TABLE OF CONTENTS

1.0 Title

2.0 General Description

3.0 Scope

4.0 Data

5.0 Equipment / Tools

6.0 Repair Materials

7.0 Preparation

8.0 Procedure

9.0 Cutting Sequence


TITLE

METHOD STATEMENT FOR CONCRETE SLAB CUTTING (HOLLOW CORE and Half SLAB)

GENERAL DESCRIPTION

This document outlines the procedure for rectification through cutting of concrete due to the excess length of
hollow core and half slab for Clark International Airport Project. MCC - Precast is the contractor for
manufacturing and delivery of the required precast units and responsible for compliance with this procedure .

SCOPE

This Method Statement directly addresses the non-conformance on the dimension of the hollow core and
half slab due to the revision of framing plan as per MCC-Precast Engineering Department letter dated January
03, 2019. (Subject: Rectification – CIA Hollow Core Slab and Half Slab)

DATA

Below is the list of Hollow core and Half slab need to be cut at site.

At MCC-Precast Factory

Panel Name Cut


D1HC – (307 to 318) 70 mm
D1HC – (341 to 364) 70 mm
D1HC – (387 to 398) 50 mm
D3HC – (101 to 191) 102 mm
D3HC – (194 to 195) 100 mm
D5HC – (226 to 291) 100 mm
A2HC – (91 to 95) 50 mm
A2HC – 97 50 mm
A3HC – (25 to 33) 50 mm
A3HC – (60 to 65) 50 mm

Panel Name Cut


A6HS-14 1890 mm
EQUIPMENT / TOOLS

 Diamond Blade (7’’ Diamond Cutter)


 Grinding Machine – (Makita)
 Chisel (Handy)

REPAIR MATERIALS

 Protective Paint for Rebar and PC Strand (epoxy paint)

PREPARATION

 An exclusion zone is established around the area to be sawed at CIA Project Site.
 The precast slab shall be identified
 The slab cutting length shall be identified and mark.
 A cut-line is pre-marked on both side of the slab as per specified cutting length
 Cutting tools and equipment shall be checked and tested.
 Ensure engine is warmed up and the blade is spinning at the correct speed before commencing cutting.
 Appropriate PPE should be worn.

PROCEDURE

 Work should be done at Project Site and in MCC Precast factory.


 Provide a pre-marked at both face of the slab. Be sure that correct layout marked as per specified cutting
length
 Cut Straight. Make the first cut about 50-75mm deep from the top of the slab using diamond cutter (See
cutting sequence)
 Start the cutting and chipping of concrete from top portion going down at every 50mm-75mm using
diamond cutter and handy chisel
 Never leave a running machine unattended
 If cutting was done, remove the extra concrete using hand type power chisel or small diameter grinder
 Use a handy chisel to chip off loose concrete and diamond cup wheel to get correct dimension of the slab
 Protect the exposed cut reinforcement by applying epoxy paint
CUTTING SEQUENCE

You might also like