Site Name District Operations Region PROJECT NAME

Mpemba Airtel BLANTYRE BLANTYRE ADHOC(motivation)


Golden Peacock BT BLANTYRE Blantyre ADHOC(motivation)
Ndirande Floodlights BLANTYRE Blantyre ADHOC(motivation)
Kabundi North North ADHOC(motivation)
Chosi Rumphi North ADHOC(motivation)
Chilobwe BLANTYRE Blantyre ADHOC(motivation)
Site TYPE Number of sectors Action vs Technology
New shared 3 GSM+LTE
New rooftop 3 GSM+UMTS+LTE
New rooftop 3 GSM+UMTS+LTE
Old tower replacement 3 GSM+UMTS
New build 3 GSM+UMTS
Old tower replacement 3 GSM+UMTS+LTE
Commissioning Date Remarks
30-Apr Completed
15-May In progress
20-May In progress
30-Jun In progress
30-Jun In progress
30-Jun In progress
SR Project Name Total Sites Commissioned Remaining
1 2019 Q1 New Build 32 32 0
2 2019 Q3 New Build& shared 23 5 18
3 2020 Q1 New Build and shared 15 2 13
4 2020 Q2 7 1 6
5 ADHOC Sites (Motivations) 6 1 5
Comment
Closed after mapazi commissioning
This project is combined with 2020 Q1 in terms of implementation
Civil works in progress
Land Acquisition and civil works purchase in progress
Civil works in progress