Responsibilities:
• Production in the 75 ML/day water treatment plants in
the capital city Maseru
• Electro-Mechanical Workshop responsible for repairs in
sewer and water treatment plants throughout the
country
• Development and implementation of the company’s
physical asset management strategy
• Development and implementation of the company’s
water safety plan.
• Updating of the drought water emergency plans
• Review and participation in construction of pump
stations, reservoirs and dams
• Part of the team that oversaw the construction of
Metolong dam construction (63 million cubic meters
capacity at 83 m height and 270 m width). The project
included water treatment works and downstream
conveyence system.
Assistant Engineer, Kao Diamond Mine (now storm
mountain diamonds), Lesotho