You are on page 1of 27

FIBERSPAR® LinePipe™

General Installation Guide

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 1 of 27


Table of Contents
General Installation Guide

A. Introduction to Fiberspar................... 3 G. End Terminations .............................15

1. Surface Tie-In.....................................15
B. Product information........................... 4 2. Rigid Riser..........................................15
3. Riser Chute ........................................15
1. Product Identification............................ 4
2. Connector Identification ....................... 4
3. Certified Installers ................................ 5
H. Testing ..............................................16

C. Storage & Handling............................ 5 1. Introduction.........................................16


2. Filling..................................................16
1. Packaging ............................................ 5 3. Test Procedure ...................................16
2. Handling............................................... 5 4. Test Pressures ...................................17
3. Storage ................................................ 6 5. Pipe Contraction/Expansion ...............17
4. Field Transport..................................... 6 6. Backfilling ...........................................18
7. Tracer Wire.........................................18

D. Installation Tools ............................... 7


I. Static Discharge ...............................18
1. Introduction .......................................... 7
2. Spools.................................................. 7
3. Spooling Equipment ............................. 7 J. Jacketed Pipe . ……………………..…18
4. Pulling Devices .................................... 9
5. Load Indicating System ........................ 9
6. Miscellaneous .................................... 10 K. Vibration............................................18

E. Installation Techniques ................... 10 L. Corrective Action Request...............19

1. Stationary Spool –
Surface & Buried ................................ 10 M. Tips for a Successful Installation ....20
2. Moving Spool Installations.................. 11
1. Pre-Installation Job Checkist .............20
3. Trenches............................................ 11
2. The Four Most Common Reasons
4. Pipeline Remediation
For Damage to Fiberspar LinePipe .....20
Applications ....................................... 11
5. Plow-In............................................... 12
6. Surface Installations........................... 13
Appendixes
7. Crew Size & Organization .................. 13
Fiberspar LinePipe Specifications ............23
F. Joining .............................................. 14 Fiberspar LinePipe/J Specifications..........25
Fiberspar LinePipe Bend Radii .................26
1. Introduction ........................................ 14
2. Service-End Connectors .................... 14 Fiberspar LinePipe Test Pressures ..........27
3. Pipe-to-Pipe Connectors .................... 15
Fiberspar LinePipe Shear Loop Table ......28
4. Connector Selection........................... 15

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 2 of 27


A. Introduction to Fiberspar

Fiberspar is the world's leading innovator and


manufacturer of spoolable, fiber-reinforced pipe
and tubing. The company's proprietary
technology (more than 25 US and international
patents related to spoolable products) is
incorporated into product lines used in a variety
of oil and gas field applications.

Fiberspar® LinePipeTM is used in production


gathering, injection, and disposal applications.
More than 10 million feet of LinePipe has been LinePipe inventory at plant.
installed for a wide range of customers in North
America, including almost every major operator. Fiberspar uses proprietary technology to
manufacture on a continuous, linear processing
line. All key operations are carried out in house,
including, liner extrusion, pipe fabrication,
testing and pipe jacketing. An ISO 9001-
compliant quality system with complete testing
laboratories and expert staff support new
product development and quality assurance
testing.

Today, Fiberspar is the leading designer and


manufacturer of continuous-length, spoolable
fiber-reinforced pipe used in the oil and gas
industry. And, with twenty years in the
business, Fiberspar is one of the most
experienced.
Fiberspar production lines capable of producing
10 million feet of pipe per year. More information on Fiberspar's products and
services can be found at the company's
website: www.fiberspar.com.
Fiberspar LinePipe is manufactured using an
inner thermoplastic pressure layer reinforced
with high-strength glass and/or carbon fibers
embedded in an epoxy matrix. The result is
high-pressure pipe immune to corrosion, with
few joints, and rapid deployment potential. In
2002, the manufacturing plant was moved from
Wareham, Massachusetts, to its current
location in Houston, Texas.

The Company now has Sales offices in


Houston, Texas, and Calgary, Alberta, and
Field Operational Centers in most of the active
oil and gas locations in North America, .
including Central Texas, South Texas, Rocky LinePipe ready for transport to Alberta, Canada.
Mountains, Alberta and South Saskatchewan.

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 3 of 27


B. Product Information 2. Connector Identification

The primary connectors are available in two


This manual is applicable to the installation of basic types, the Service-End Connector and the
®
FIBERSPAR LinePipeTM (FS LP) family of Pipe-to-Pipe Connector. (See figures below).
products. FS LP products are advanced These are identified with a Product
composite line pipes produced in continuous Identification Number that takes the form:
lengths of up to 5 miles. They are designed for
storage, delivery and deployment from spools. CHEXxYZz
Where:
This General Installation Guide provides
general information on application and C = Connector
installation of systems using Fiberspar
LinePipe. It is not an Installation Manual. H = Design Revision

The “FIBERSPAR LinePipe Engineering Guide” E = Series


provides engineering and design data B = B Series
applicable to the FS LP products and is C = C Series
available by application at www.fiberspar.com. D = D Series
E = E Series
1. Product Identification G = G Series

A Product Identification Number or PIN Xx = Size (Nominal Outside Diameter)


identifies FIBERSPAR® LinePipeTM. The PIN X= whole inches
takes the form: x = decimal parts of an inch

FS LP BB b/b CCCC (D) Y = End Termination:


W = Flanged Assembly
Where: L = NPT Threaded Assembly

FS = FIBERSPAR® Zz = End Termination Size


Z = Nominal Pipe Size in Inches
LP = LinePipeTM z = ANSI Flange Rating

Note: The letter “J” which designates 0 = 150#


jacketed product may follow the “LP.” 1 = 300#
3 = 900#
BB = Nominal Outside Diameter 4 = 1500#
(in whole inches)

b/b = Nominal Outside Diameter


(in fractional parts of an inch)

CCCC = Maximum Allowable Operating


Pressure (MAOP), psi

(D) = Pressure Barrier Material Code Service-End Connector Components


Current Material codes are “E” for HDPE
and “X” for PEX (cross-linked PE)

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 4 of 27


potential injury to personnel and damage to
pipe and equipment.

Pipe-to-Pipe Connector Components

3. Certified Installers

FIBERSPAR requires that a Fiberspar Certified


Installer supervise all installations of Fiberspar
LinePipe. To attain certified status, installers
are required to attend a Fiberspar training Spools of FS LP Ready for Transport
class, and work under direct supervision of a
Certified Installer for a number of installations. 2. Handling
To maintain Certified Installer status, the
installer must install Fiberspar LinePipe on a Most jobs staged from local deployment areas
frequent basis, maintain an updated manual do not require the handling and lifting of full
and attend refresher courses as required. spools at location. Specialized equipment is
Certified Installer status will lapse for any used which allows the technician to deploy the
individual who has not installed Fiberspar LinePipe directly from the transport vehicle.
LinePipe in the preceding 6 months. However, on larger projects its may be
necessary to swap spools out of the
deployment equipment directly on location. In
these cases, care must be taken because
C. Storage and Handling spools of pipe tend to be top-heavy loads and
must be handled with care to avoid overturning
1. Packaging causing harm to surrounding personnel or
damage to the pipe and/or spool.
FS LP is packaged on spools for transport,
storage and deployment. The spools are On rare occasions it will be necessary to upright
fabricated from steel or wood and often weigh the spools after unloading in order to place
more than the FS LP product which is on the them in an upright spooling frame. The
spool. preferred method for uprighting a Fiberspar
spool is to use a crane equipped with a second
Pipe is wrapped around the spool drum and in line.
layers to the desired length. The outermost
layer should be at least 1 inch below the spool CAUTION: Improper handling of spools of
flange. All pipe is hydro-tested on the spool at FS LP can result in personnel injury as well
the factory and although care is taken to as damage to the product. Ensure that the
remove water, spools of pipe may contain small lifting equipment used, including straps,
amounts of water that is not practical to slings and spreader bars are in good
remove. working condition and are rated for the load
and conditions.
CAUTION: FS LP wound on spools has
some stored energy. Ensure that the pipe
end is restrained during all operations to
avoid rapid release of this energy and

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 5 of 27


contact and damage the pipe on the outermost
layer. It is also recommended when spools are
The use of a spreader bar and slings is strongly placed on soft surfaces such as dirt or gravel
recommended when moving spools with a that they be placed on suitable support to
crane. prevent the spool flanges from sinking into the
ground. The use of 6" X 6" timbers is
recommended for this purpose. Block, or
otherwise ensure, that the spool cannot roll. Do
not store on slopes.

Spool will not


move once
properly chocked.

Handling Spools for Change Outs

In the absence of a crane, two forklifts can be


used. The bar is placed through the center hole
and a forklift is positioned on each side of the
spool. The forks are used to lift the bar raising
the spool.

When two forklifts are used to unload a truck, it If storage is to be for an extended period of
is recommended that the spool be raised and time, the pipe should be protected from
the truck driven out from under it. Movement of freezing. Spools of FS LP may contain some
the forklifts must be coordinated to avoid water from hydro testing or condensation that
accidents. can freeze and damage the pipe.

CAUTION: Attempting to move the spool by 4. Field Transport


“rolling it” is never recommended. Spools
tend to be top heavy and may tip sideways if When transported in the field for deployment,
rolling is attempted. Rolling the spool of FS the spool must be mounted in a suitable
LP may also damage the pipe that is on the spooling frame. Transport should be on a
spool. trailer that is as close to the ground as practical.
Be aware of any overhead power lines or other
3. Storage overhead obstructions that may come in contact
with the spool.
Spools of product should be stored on level flat
surfaces with no protruding objects that might

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 6 of 27


tools/equipment required for all installations.
Special installations may require additional
tools/equipment.

2. Spools

Spools are used to transport and deploy the


pipe. Spools are typically 12 ft, 14 ft or 16 ft in
diameter, and can be manufactured from steel
or wood. The core diameters of Fiberspar
spools are selected to ensure that the bending
strains are within allowable limits. Only
Fiberspar supplied spools should be used to
store, transport or deploy Fiberspar LinePipe.
Hydro testing of Fiberspar LinePipe is carried
Spool of FS LP on Trailer for Transport and out on specially reinforced spools at
Deployment. manufacturing locations. Fiberspar LinePipe
should never be subjected to pressure on a
CAUTION: Spools make top-heavy loads shipping spool.
that are easily overturned. The spool and
frame should be mounted as close to the 3. Spooling Equipment
ground as practical and the frame securely
chained to the trailer. During transport, Fiberspar has designed and manufactured
speed should be reduced and turns must be spooling equipment suitable for deploying and
negotiated with care. re-spooling Fiberspar LinePipe. Approved
equipment must be used for these operations.
Fiberspar engineers should be consulted where
5. Low Temperatures any equipment not designed by Fiberspar is to
be used for deployment. Fiberspar spooling
Fiberspar LinePipe has a minimum operating equipment safely supports the LinePipe during
temperature of minus 34 degrees C (minus 29 spooling operations, and has speed control and
degrees F). If the pipe has been stored in a powered braking to ensure that back tension is
situation where it is possible that the pipe has kept on the spooled pipe at all times.
reached lower temperatures than this, it is good
practice to ensure that the pipe is above this Fiberspar currently uses three types of spooling
temperature before uncoiling and handling. frames for field deployment of LinePipe
When at low temperature, the body of the pipe products.
represents a substantial heat sink, and it is
important to ensure that fluids pumped into a Rim Drive A-Frame. These handle the spools
cold line cannot freeze. in a vertical position. Smaller diameter spools
are typically deployed on this equipment, which
D. Installation Tools consists of an “A-frame” with an integrated drive
mechanism that controls the rate of deployment
through a hydraulically driven rubber tire in
1. Introduction
contact with one of the flanges or rims of the
spool. It is capable of handling spools from
FS LP is designed for storage, handling and
143” to 147” in diameter and pipe sizes up to
deployment from spools. The tools and
3 ½”-1500, and sufficiently low profile to allow
equipment required for any job is somewhat
deployment with a loaded reel. One or two of
dependent on the method selected for
these types of frames can be loaded on a
deployment of the FS LP. The following
double-drop trailer, transported to location and
discussion of tools considers the basic
the pipe deployed without requiring a crane on

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 7 of 27


location. Rim drive A frames are not suitable for frames can be carried on a step-deck trailer,
re-spooling operations. In Canada, modified allowing the installer to deploy up to 9,000’ of
versions of these Rim Drive units can handle FS LP 4 ½” – 1500 product without the
spools up to 14 ft in diameter, taking advantage necessity of a crane being on location.
of the increased allowable road height in some Carousels are not suitable for re-spooling
locations. operations.

Chain Drive A Frame. This frame is generally


used for larger diameter spools and for re-
spooling operations. This type of frame usually
requires a crane on location for assembly and is
not generally suitable for deployment from a
truck trailer. It is a typical “A-frame” type that
has a chain and sprocket drive mechanism
along with integrated “drive dogs” that engage
in the flange of the spool, providing a positive
drive system. The spool has to be fitted with a
shaft to be fitted into these frames.

Rim-Drive Spooling Frame

Carousel. These are typically used for larger


spools. The spool is loaded in the horizontal
position. It uses two hydraulically driven rubber
tires to control the rate of deployment and also
has two level-wind arms which contain the
Fiberspar LinePipe on the reel to support the
pipe wraps during deployment.

Chain-Drive Spooling Frame

In Canada, Fiberspar has built specialized


Horizontal Carousel Spooling Frame
trailers which are permanently fitted with two
chain drive units, on a special drop bed, which
This frame is capable of handling reels from 12’ takes advantage of local height restrictions to
up to 19’ in diameter and pipe sizes up to 4 ½”- transport two 16 ft diameter spools ready for
1500. Two of these types of deployment deployment.

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 8 of 27


a. Pulling Heads

Pulling heads are the preferred method of


attachment of FS LP to the pulling device.
Fiberspar can supply pulling heads sized and
designed for the various sizes and pressure
ratings of FS LP.

Special Drop Bed Trailers with two 16 ft Spools


in Chain Drive Units

All three styles of frames require a hydraulic


power supply for operation of the hydraulic
drive control motors and the level wind arms on
the carousel frames. The hydraulic power
supplies are either gasoline or diesel driven and
connect to the deployment frames via high-
pressure hoses and quick connect couplings.
The pulling head is attached to the end of the
FS LP by setscrews through a number of holes
4. Pulling Devices
drilled through the side of the pipe. The pulling
head is then attached to the pulling device
For most installations, a suitably powered
through a pulling eye preferably with a nylon
device is required for pulling the pipe off of the
sling or strap to avoid “shock” during the
spool. Fiberspar does not normally supply this
installation process.
device, as suitable devices, such as a backhoe,
are normally available at location. The pulling
b. Multi-Grip Pulling Assembly
device must be selected to provide sufficient
pulling force under the prevailing conditions, but
The multi-grip pulling assembly (Chinese finger)
not excessive pulling capability, to ensure that
is another device that is used to pull the FS LP.
the pipe cannot be damaged from over pulling.
Pulling capability should not exceed the
recommended maximum tensile load of the FS
LP product being installed. This maximum
recommended tensile load varies with different
FS LP designs. Shear loops or other tension
limiting devices should be used to prevent
accidental over-pulling of the pipe.

For some installations, a winch or wire-line type


of device with sufficient pulling capability is
required. If the maximum pulling capacity could
exceed the recommended maximum tensile The device slips over the pipe and tightens up
load of the FS LP being installed, the tensile on the pipe as you pull on it. It has a reinforced
load should be monitored on a load indicator to eye on the end for attachment to the pulling
ensure that the maximum tensile is not strap or cable. Fiberspar can supply suitably
exceeded. Where no load indicator is available, sized multi grip pulling assemblies.
a tension-limiting device, such as a calibrated
shear loop should be used. Fiberspar can 5. Load Indicating System
supply suitably sized calibrated shear loops.
A pulling load indicator system is recommended
during all pulls. The system should provide a

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 9 of 27


real-time indication of the tensile load being installation, reduce friction and damage
applied to the FS LP. It should also be capable when pulling round a bend, and to prevent
of maintaining a record of the maximum force any kink points. These cradles are
applied to the FS LP. A print out of force attached to a fixed or stationary point in
versus time is desirable but not mandatory. The the bend and the Fiberspar LinePipe is
system should be calibrated and rated for the then pulled around the cradles during
ultimate tensile strength of the FS LP being installation.
installed. See note 4 above where a load
indicator is not available.
In addition to the tools listed, additional tools
may be required for specific types of
6. Miscellaneous
installations and for the attachment of
connectors and fittings. Fiberspar can supply
The following tools will generally be required for
these tools.
all installations:

• Fiberspar Liner Reaming Tool. This tool E. Installation Techniques


is required for sizing the ID of the FS LP
prior to attaching the Fiberspar connector. The following is a description of the most
Also used in conjunction with this tool is a common installation techniques that are
suitable power device. Fiberspar encountered in the oil and gas industry.
recommends a ½”-drive right angle drill.
• Cutting Mean. A tool is required for 1. Stationary Spool - Surface & Buried
cutting the FS LP. A SawsAll or hacksaw
is recommended. The blade should be In a stationary spool installation the spool and
bimetallic, 14 to 24 toothed or abrasive. spooling frame serves as an anchor point. The
As Fiberspar LinePipe cuts relatively FS LP is deployed by pulling it from the
easily, care must be exercised to avoid stationary spool. This is the normal method for
damaging adjacent pipe. installation for applications in areas with soil
that is not excessively rocky.
• Tie Down. A method for restraining any
FS LP remaining on the spool is required.
The pipe on the spool must be restrained
at all times. The preferred method is to
either use a metal clamp that is bolted to
the spool flange, or to cut the pipe at an
angle and drill two holes through the
exposed half of the pipe into the flange
wall, and fit two bolts to hold the pipe. For CAUTION: Since the FS LP will be pulled off
temporary restraint, for example when the stationary reel when using this installation
moving the spool on location, a strap or method, care should be exercised to avoid
sling can be used. dragging the pipe over anything that will create
• Hand Tools. Miscellaneous hand tools excessive wear or damage to the OD of the
are required. pipe.
• Pipe Cradles. In some installations that
For surface or buried lines, a truck, backhoe or
require the Fiberspar LinePipe to “bend”
other piece of construction equipment is used to
around corners, it may be necessary to
pull the pipe into the trench. Ensure that the
use “pipe cradles” to facilitate the
pulling device is properly sized, but not
installation. The pipe cradles are used in
oversized, for the product being installed.
the bends to prevent the Fiberspar
LinePipe from exceeding the minimum
recommended bending radius during

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 10 of 27


2. Moving Spool Installations working in trenches before being qualified to
work on trench installations of Fiberspar
When the soil is excessively rocky or abrasive, products. No Fiberspar installer should enter a
it is sometimes possible to move the spooling trench that is not properly prepared or deemed
frame/spool to install the FS LP. This approach unsafe.
reduces the abrasion damage to the pipe.
However, it may involve moving a trailer with Trenches must be prepared for accepting the
the spooling frame/spool and pipe mounted on pipe. Preparation involves ensuring that the
it under off-road conditions. If the access is too bottom is reasonably smooth and level.
limited for a large truck, another possibility is to Bedding, if required, should be in place.
transfer the pipe and spooling frame to a trailer
pulled by a pick up or tracked vehicle. For narrow trenches slightly wider than the
pipe, the FS LP must be deployed alongside
the trench and lowered into the trench manually
after any necessary connections have been
made. See handling instructions on how the
pipe should be supported during this operation.
FS LP can be pulled directly into trenches when
they are wide enough for personnel to perform
joint make-up in the trench.
If the spool is to be moved to affect installation,
Fiberspar LinePipe can be installed in a
it is first necessary to connect and anchor the
continuous length even where the trench is not
pipe end. Connecting is accomplished using
straight, but all bends should have as large a
the appropriate joining system. Anchoring is
radius as possible and certainly not less than
accomplished by installing a thrust block or
the minimum bend radius quoted in the pipe
anchor post and clamping or otherwise securing
data sheet for each size of pipe.
the pipe in place. The anchor must be strong
enough to resist loads up to the recommended
The installer should inspect the installed pipe
tensile load of the FS LP being installed.
before testing or covering to ensure that it is not
lying on any sharp surfaces such as large
The equipment required for moving spool
rocks, or in contact with other pipes. Where
deployment is the same as for stationary spool
there are pipe crossings, the Fiberspar pipe
deployment.
should if possible pass under the other pipe and
good padding or sandbags placed between the
CAUTION: While this method of installation can
two pipes to ensure that there is no possible
be both rapid and avoid damage to the
direct contact when settlement takes place.
Fiberspar Pipe, it should only be carried out
Direct contact can result in rapid wear where
where the access for the moving vehicle is
there is even minor movement due to
good, flat and secure. The spool of pipe
pulsations, fluid movement or vibration.
represents a top-heavy load that is prone to
overturning. This type of installation should be
Any road or river crossings in trenched
used only with experienced drivers and should
installations are installed in a similar manner to
be done slowly and with caution. An
pull through installations – see below.
overturning load can result in injury to
personnel and damage to equipment and the
4. Pipeline Remediation Applications
FS LP.
Pipeline remediation involves pulling an FS LP
3. Trenches
pipe inside an existing pipeline to effect repairs
to that existing line. The installation requires
All certified installers should have attended a
generally the same tools as for a surface or
recognized safety course on preparation and
buried stationary spool installation except that

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 11 of 27


only the ends of the pipe that will be repaired An injector, such as a coiled tubing injector, can
are uncovered. In addition, a pigging operation be used to push the FS LP into the pipeline,
and pulling unit are also required for this while it is simultaneously pulled. In a push-pull
method of installation. operation the units must work together to avoid
buckling or over tensioning the FS LP.
When installing FS LP in a pipeline remediation
application, a wireline, from a winch or wireline An additional bell hole can be used to divide the
unit, is normally pumped through the existing length into two or more pulls. A pipe-to-pipe
pipeline and used to pull the FS LP through. connector joins the two lengths in the bell hole.
Only a single wireline can be used for a given
run of pipe. The winch/wireline should be Connector Make-up. In most installations, the
capable of pulling to the recommended tensile FS LP should be left 1.5 feet longer than would
load of the FS LP. A plastic or rubber guide normally be done with conventional piping to
bushing is required at the entrance of the allow for contraction after pressurization due to
parent pipe to prevent damage to the FS LP. relaxing of tensile force during the installation
process.

5. Plow-In

Fiberspar LinePipe can be plowed in using a


high capacity plow. The plow used must have
sufficient capacity to bury the FS LP to the
required depth and a shoe with an installation
radius that is equal to or greater than the
minimum-bending radius of the FS LP.

Soil Conditions – The buried condition of the pipe


A 20-foot length of the FS LP being used can never be inspected with a plow-in installation,
should be pulled through the existing line to so these installations must be restricted to
ensure that there are no obstructions in the line predictable and good soil conditions. Poor soil
before initiating the installation. It is also conditions to be avoided include rocky ground,
recommended that a sizing pig be pumped frozen ground and severe elevation changes. In
through the parent line prior to pulling the FS general, ground would be considered unsuitable
LP in place. for plow-in if an additional pulling force is required
to move the plow, the plow cannot maintain
CAUTION: When installing FS LP in a reasonably consistent plow-in speed and is
pipeline remediation application, the stop/starting, large rocks are being pushed to the
condition of the existing line should be surface, or the chute or guide is being sharply
determined. If the corrosion is excessive it moved either laterally or vertically due to
may be necessary to utilize centralizers or encountering obstructions.
sacrificial wear pads to prevent pipe
damage from occurring. Fiberspar
recommends jacketed pipe for many pull
through applications (see section on
Jacketed pipe).

If the tension limitations of the FS LP or winch


will be exceeded, there are two methods for
making the installation:

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 12 of 27


Guides and Chute – the design of guides and
chute on the plow must have no sharp edges that
could contact the pipe or expose the pipe to
kinking or a bend radius less than the design bend
radius of Fiberspar Line Pipe.

Supervision – Although good planning and job


selection can avoid most problems, there should
always be a Fiberspar certified installer present
during plow–in deployment.

6. Surface Installations

Techniques for surface installation of Fiberspar


LinePipe are very similar to trenched
installation, but some special consideration
Plow-In Operation with FS LP Laid Out in the should be given to pipe protection. Jacketed
Right-of-Way pipe will normally be used for surface
installation for extra protection. The pipe should
Deployment Method - The straight line not be installed on rocky ground or on pipe
deployment method (as shown above) shall supports at intervals as often used for steel pipe
always be used, where the pipe is laid out on the surface installation. The pipe should be
proposed line of installation and in line with the supported on smooth ground. Vehicles should
deployment guide, passing straight over the top of not be driven over Fiberspar LinePipe, so
the plow without twisting or lateral strain. Always crossing points may have to be provided. Since
check in advance that the plow is capable of this the pipe will not be restrained during hydro test,
method of the deployment. Laying the pipe on it will possibly shrink in length during the test.
one side of the plow and deploying by creating a Fiberspar engineers can advise on the amount
moving loop that is not vertical puts twist on the of shrinkage, but care will have to be taken to
pipe, and this method must not be used in the ensure that the pipe cannot move and tighten
future. The orientation and location of the spool against pinch or kink points.
and feeding of the pipe should minimize bending
of the pipe and eliminate bending that reverses It can be difficult to move the unrestrained pipe
the direction of curvature. around planned bends in the right of way, and
pipe rollers and anchor points may have to be
used to route the pipe. Fiberspar field
supervision should be consulted in advance for
advice on the route and equipment required if a
surface installation is planned.

7. Crew Size & Organization

A Fiberspar Certified installer should be present


to supervise overall installation operation,
provide specific training to local helpers, and fit
all connectors. The Fiberspar Certified Installer
should be present during the hydraulic test.

Crew size will be dependent on the specific


installation, skill level of the work force, as well
as industry practice, but typically the Fiberspar
Certified Installer will require assistance from a

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 13 of 27


backhoe or similar to pull the pipe, and one consider the application and the connection
additional helper to assist with handling. means to be used. The assembly procedure
may vary slightly depending upon the type of
In all operations, crew sizes will be dictated by end connection involved.
terrain, environmental and other conditions.

F. Joining
1. Introduction

Only Fiberspar Certified Installers will install


fittings for service.
Service-End Connector Components
The FS LP Compression Slip Connector is a
In summary the attachment procedure for a
mechanical fitting that attaches to the pipe by
Service End involves the following general
application of compression forces. Two general
steps:
types of connectors are used, Service-End and
Pipe-to-Pipe.
• The pipe end is cut square.
2. Service-End Connectors • The FS Reaming Tool is used to size the
inside diameter of the pressure barrier.
• Service-End Connectors are used at the
• A chamfer is cut on the exposed end of
end of a pipe run to connect the pipe to
the pressure barrier.
another system or another fitting. (See
figure below.) • The slip nut and slip are positioned on the
end of the pipe.
• The Service-End Connector is available
with a variety of end configurations that • The Service-End is fitted with “O” rings
are commonly used in pipeline and lightly lubricated and inserted in the
applications. Fiberspar standard pipe end.
configuration is an ANSI RF Flange.
• The Service-End and slip nut are
Other configurations supplied on request
threaded together and the threads
are RTJ flange, NPT Pipe thread, hammer
tightened.
unions, or other configurations specific to
end-user specifications.
CAUTION: In attaching Compression Slip
Forces are typically applied through wedge
Connectors to the FS LP or the system, the
loading of a slip between two body halves. The
pipe must not be rotated or subjected to
Fiberspar LinePipe Engineering Guide provides
torque. “O” rings should be installed and
the required formulas to calculate axial forces
lubricated just prior to final assembly to
generated in a pipeline with Fiberspar LinePipe
avoid damage.
based on changes in pressure or temperature.

The effect of internal pressure and changes in


temperature on axial forces in the Fiberspar
LinePipe shall be taken into account when
making up fittings.

In preparing for attachment to another system


or fitting, the needs of the customer and system
must be considered and the proper end
configuration ordered. Planning should

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 14 of 27


3. Pipe-to-Pipe Connectors 2. Rigid Riser

The Pipe-to-Pipe Compression Slip Connector In this configuration the pipe is terminated sub-
is used to join two lengths of FS LP together surface to a rigid riser. The riser can be coated,
(see figure below). Attachment is the same as and the Fiberspar connector is often a weld
attachment of the Service-End Connector neck rather than flanged.
except there are two pipe ends to be prepared
and the connector has two slips and two slip
nuts.

Pipe-to-Pipe Connector Components

4. Connector Selection

In order to ensure that the proper connector is


3. Riser Chute
used on the LinePipe product, measurements
of the ID and OD of the pipe are used to
In special cases where the riser (as in Section
determine which connector components are
G.2 above) would have to be a special material
installed. Components are then selected based
(for example in CO2 floods), an alternative is to
on the range they are designed to fit and how
fabricate a riser chute through which the pipe is
the LinePipe measurements fit into that range.
brought to surface.

G. End Terminations
There are two common methods for terminating
Fiberspar LinePipe.

1. Surface Tie-In

In this configuration the pipe is brought to the


surface in a gradual bend and tied in with a
connection.

The bell hole has to be prepared with a suitable


bed shape to ensure that the pipe is not
exceeding its allowable bend radius.

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 15 of 27


CAUTION: Entrapped air will cause testing
H. Testing and Backfilling problems and may result in over
pressurizing the system. Use care to ensure
1. Introduction all of the air is removed.

All Fiberspar Linepipe is tested to 1.5 times 3. Test Procedure


rated operating pressure before being shipped,
and following installation procedures properly, a
first time successful field test should be the Fill pipe in the open ditch with water taking
routine result. However the field test is the last reasonable steps to remove air or gas.
line of defense, the point where anything that Raise pressure slowly (less than 20% rated
slips through the net should be caught before it pressure per minute) to around 50% system
becomes a damaging service failure. When rated pressure in the open ditch, and check for
field test procedures are adhered to and a leaks. The purpose of this test is to find any
successful test achieved, service failure is very obvious connector leaks, or gross damage
rare. before backfilling.
The correct procedure for testing involves two Reduce pressure to around 200 psi and back fill
separate steps. The pipe should be tested first the ditch. See backfilling guidelines.
in the open ditch to a relatively low pressure to
find any obvious leaks or damage. The ditch When backfilled, raise pressure slowly (max
should then be backfilled before final testing at 20% rated pressure per minute) to 50% of full
full test pressure. There are two reasons for agreed test pressure and hold for 15 - 30
this: minutes. Check for leaks. Then raise pressure
slowly to full test pressure and hold.

• Backfilling is one of the most common A Fiberspar representative will be present


sources of pipe damage and would not be during the test if requested.
detected if the pipe is tested only before Following these steps will guarantee a safe test,
backfilling. demonstrate whether leaks are due to a pipe
• Fiberspar LinePipe will contract in length problem or back fill problem, and prevent
at pressures above normal rated problems from shrinkage stress which takes
pressure, and backfilling will prevent any place when pressure exceeds pipe rated
movement. pressure.
Complex piping systems should be broken into
2. Filling smaller runs for testing when practical. The
following guidelines and warnings must be
followed carefully to avoid personal injury
The system should be filled by pumping a pig and/or damage to equipment.
(poly or squeegee) in front of the fluid to help
force the air out of the system. In systems
containing tees and branches, it may not be CAUTION: Testing with fluids under
suitable to use a pig, as the pig may get caught pressure can be hazardous. Personnel
in one of the side branches. Fluid should enter injury and/or equipment damage is possible.
the system at the lowest point and air must be Exercise care and follow safety precautions.
vented from the highest point or points. Allow Never attempt to tighten a connector while
fluid to flow through the vents until there is no pressurized.
evidence of air coming from the system. When
all air is removed, seal the vents and prepare Testing with air or gas is extremely
for testing. dangerous and should not normally be
done. Gas is compressible and the stored
energy is much higher than with fluids. If a

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 16 of 27


gas test is proposed, consult with Fiberspar Test pressure should be held for a minimum of
Technical Management. 2 hours, preferably 4 hours, while the line is
checked for leaks. The customer and/or
applicable regulations may require longer
4. Test Pressures
testing periods. Test periods as long as 24
hours are not uncommon.
The recommended test pressure is 1.2 to 1.5
times the rated operating pressure of the
5. Pipe Contraction / Expansion
system, with a maximum of 1.5 times the rated
operating pressure of the Fiberspar LinePipe.
Fiberspar LinePipe behaves differently with
respect to most other pipeline products with
CAUTION: Prior to pressurizing the line it respect to axial contraction or expansion.
must be at least partially covered and high- Fiberspar LinePipe is designed so that there is
pressure fittings should be blocked. virtually no contraction or expansion or the pipe
in the axial direction at the rated operating
pressure. Below the rated operating pressure
Increase pressure at a rate not exceeding 20% there is slight initial axial expansion as the
of the pipe rated pressure per minute to 50% of pressure is increased, but this axial expansion
the desired test pressure, hold and walk the line diminishes as the pressure nears rated
looking for evidence of leaks. Pay particular pressure, becoming virtually zero at around
attention to all joints. If there is no evidence of rated pressure. However, this expansion
pressure loss or leaks, increase at a rate not tendency is very small, with very small axial
exceeding 20% of the pipe rated pressure per forces, and can usually be ignored as the
minute and hold at the desired test pressure. weight of the pipe when filled with water is more
Overpressure up to 200 psi is acceptable until than sufficient to prevent any actual any pipe
pressure stabilizes. With pressure stabilized, movement.
start the clock and monitor the pressure. If there
When the pipe pressure is raised above rated
is any unexplained pressure drop, walk the line
and look for evidence of leaks. operating pressure (normally only for test
purposes) the pipe will try to shrink in length.
These forces are relatively small and backfilling
NOTE: the pipe will normally provide enough
restraining force to prevent actual movement,
FS LP expands slightly during initial but if the pipe has sections not backfilled e.g.
pressurization. It is therefore recommended close to risers or connections, precautions have
that the pipe be allowed to “stabilize” at to be taken to provide support in these areas to
pressure for a period of time prior to beginning take any contraction loads that may be passed
the actual test. This stabilization period is to risers or to isolate other parts of the system.
usually about 30 minutes in lines of up to about
5,000 ft in length, but can be longer in lines of Particular care must be taken if there are long
much greater length. It is usually fairly obvious unrestrained sections, such as in a non-
when the pipe stabilizes, and generally slow backfilled ditch, an above ground installation, or
pressure leaks during this time will be due to a pull-through or river crossing. As well as
stabilization and not pipe leaks. Having exerting force on other parts of the system, the
excessive air in the line will also lengthen this Fiberspar LinePipe pipe will tend to tighten
stabilization period. Temperature changes around any bends or restraints and can be
cause the test fluid to expand or contract damaged, so provision has to be made for this.
resulting in changes in pressure. Ambient Fiberspar engineers can calculate the amount
temperature should be tracked to provide of contraction and the contraction forces and
compensation on pressure graphs. provide advice on how to offset it.

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 17 of 27


Caution. Connectors should be installed in I. Static Discharge
straight sections of the pipe well away from
any bends, and the pipe should be Fiberspar LinePipe is an electrical insulator,
supported, usually by backfilling around the and in applications that involve transport of non-
bend area. No levering or forcing of the polar fluids for example: dry gas, liquid fuels or
pipe should be required to line up with the pure hydrocarbons, especially at high velocities,
connector. a static charge may be generated on pipe
surfaces. If it is required to repair, purge the
6. Backfilling line, make a new connection, etc., grounding
and static control procedures should be
employed during the intervention. Static
Before backfilling, the Fiberspar LinePipe electric discharge can ignite a flammable gas or
should be inspected to ensure that there is no a combustible atmosphere. Where a flammable
visible damage and the pipe is bedded on gas or combustible mixture may be
smooth soil so that the weight of backfill will not encountered and static electric charges may be
press the pipe down on to a point load present, observe all Company (operator,
underneath. Care should be taken with contractor, etc.) procedures for static electricity
backfilling, particularly in shading the first 12 safety and control, including procedures for
inches of cover. The first 12 inches of cover discharging static electricity and personnel
should not contain any large rocks, and the pipe protection.
should be covered gently, taking care not to
contact the pipe with any mechanical In Fiberspar LinePipe applications involving
equipment. transport of wet gas, or liquid or multiphase flow
containing water, no significant static charge is
Large rocks, large pieces of frozen soil or tree generated on pipe surfaces.
trunks can be used as infill once a reasonable
cover over the pipe is achieved, but should not
be dropped into the ditch during the backfill
process.
J. Jacketed Pipe
Where Fiberspar LinePipe emerges from a Fiberspar LinePipe is sometimes installed in
conductor pipe or conduit, the pipe should be soil conditions which are not favorable for
packed off at the exit point, using ‘linkseal’ or glass-reinforced epoxy pipe. For these
similar soft packing material. At the transition applications Fiberspar has developed a
the pipe must be supported centrally with the jacketed version of the standard LinePipe
conductor pipe or conduit so that no shear load product. This product is similar to design and
will be placed on the pipe when the ditch is performance of the standard LinePipe except
backfilled, by placing sacks of ‘Sacrete’, sand that it has an additional extruded jacket on the
bags or similar materials under the pipe, then OD. This jacket provides protection against
backfilling carefully with frequent tamping to impact and abrasion damage that can occur in
ensure consolidation. unfavorable soil conditions. This jacketed
product also provides added protection to
LinePipe, which is used in a pull-through
7. Tracer Wire
application. The jacket provides a layer of
protection between the FRE and the parent
Tracer wire or tape should be used to allow pipe.
easy location of the pipe in the future.
Regulations in some areas (usually areas
where ground lightning strikes are common) K. Vibration
dictate that the tracer wire should be located in
the ditch about 6 inches above the pipe, and Applications which use Positive Displacement
continuous contact with the pipe should be Pumps (e.g. Tri-Plex pumps) may require
avoided. additional steps to prevent pipe movement or

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 18 of 27


pulsing which can result in abrasion damage.
This may include additional pump dampening,
flexible discharge connections, or the use of
Fiberspar Jacketed LinePipe. Fiberspar
Engineering will provide application specific
advice where vibration is a concern.

L. Field Incident Reporting


Fiberspar has a system for the proper reporting
of issues and incidents concerning the LinePipe
product, service, installations, or other areas
concerning the product. Any person involved
with Fiberspar LinePipe has the authority to
raise a Corrective Action Request (CAR). This
requires only a verbal or informal note to the
Engineering Department, who will raise the
formal paperwork. This will trigger an
investigation of the problem, determine the root
cause and provide a recommendation for
improvement going forward, and other
appropriate actions such as changes to
documents and work instructions.
Serious incidents such as a failure on test or in
service require immediate notification of the
Fiberspar District Manager. The District
Manager then initiates a process which leads to
an investigation that will normally result in a
formal report.
Health and Safety related incidents must follow
Fiberspar accident or near miss reporting
procedures, and since most field incidents will
occur on customer property, should also follow
the customer specified safety incident reporting
procedures.

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 19 of 27


2. The Four Most Common Reasons for
M. Tips for a Successful LinePipe Damage to Fiberspar LinePipe
Installation
1. Complete a Pre-Installation Job a. LinePipe is damaged in the course of
Check List being moved after unspooling.

• Deploying LinePipe directly into the ditch


minimizes the likelihood of damage during
field operations. However, this is not
always possible due to access or
scheduling. In these cases, the pipe is
deployed along the right of way for later
movement into the ditch and additional
steps have to be taken to prevent
damage.
• The following are best practices and
hazards to avoid when additional handling
of LinePipe is necessary.
• If LinePipe is to be deployed and then
moved into proper position following
deployment, it is important to provide
enough slack in the areas where
movement is required.
• For example, if the LinePipe is deployed
around the inside of a field bend and must
be moved to a trench in the center of the
bend, the pipe requires slack to make up
the additional linear distance through the
bend.
• Do not attempt to move LinePipe that has
insufficient slack by using a chain or sling
tied on at one point. This will result in a
point load that will damage the pipe. The
proper method is to pull slack into the
point where the pipe is to be moved and
then to move it into place.
• Slack can be pulled into the line by
attaching a sling at a point where the pipe
has no bend and pulling on the sling in a
direction parallel to the pipe.
• If the LinePipe is further than 20 feet from
the trench, move the pipe in multiple
passes.
• Anytime LinePipe is to be moved it is also
recommended that a Fiberspar Certified
Installer is present.

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 20 of 27


b. Damage from Construction Equipment • The ditch should also be filled in a
controlled manner that does not introduce
any lateral or shearing loads on the pipe.
• The most common cause is from a
backhoe or other excavation equipment • Consult Fiberspar District Manager for
used to move the pipe, the backfill, or specific advice on backfill.
other excavation operations.
• This can be avoided through care and d. Misalignment of the LinePipe,
diligence but additional steps can be Connectors, and Trench Bottom
taken to minimize the likelihood of this
Particular attention should be paid to the
occurring.
following issues.
• When the LinePipe is laid in the right of
• Fiberspar LinePipe connectors are proven
way for future trenching it should be
to be extremely reliable when correctly
located in a safe spot away from traffic
installed. Proper alignment of the pipe
and other operations and should be
and connectors is critical for successful
properly marked or flagged.
installation.
• In cases when the pipe is accidentally
• At risers and connectors it is important
contacted by heavy equipment it is
that the LinePipe is not installed with a
imperative that the location of the contact
bend at the back of the connector. The
is marked and brought to the attention of
transition in stiffness between the
the Fiberspar Certified Installer for
LinePipe and the metal connector can
assessment.
cause significant point stress on the pipe
• Contractors should be made aware that it if it is installed in or close to a bend.
is relatively easy to repair a point of
• The trench bottom should be level and the
known damage when compared to finding
pipe and riser properly supported at the
the damage as a result of failure on test or
point where it enters the connector and
in service.
attaches to the riser. This may require
sandbags or a driven pile.
c. Improper Backfill
• The LinePipe must also be properly
aligned and supported at the entrance and
• The backfill that comes in contact with the exit of steel casings or bores. If
LinePipe should be loose dirt with no misaligned, the weight of the backfill
heavy or sharp objects. causes a shearing load on the pipe
against the edge of the casing. (see
• The trench bottom should also be smooth
Section H.6.)
with no sharp objects beneath the pipe.
• The pipe should first be shaded with loose
dirt for the first 1-2 feet of cover. Large
rocks or objects can then be placed on
top.
• Where local soil conditions make it difficult
to control backfill quality, additional steps
should be taken such as grading,
imported padding, or jacketing of pipe.
Consult Fiberspar representative for
guidance.
• When soil conditions are frozen, extra
care must be taken to not set frozen
lumps directly onto the pipe

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 21 of 27


APPENDIXES

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 22 of 27


FIBERSPAR LINEPIPE SPECIFICATIONS
Fiberspar LinePipe (FS LP) is intended for corrosive gathering and injection applications including general and sour
produced fluids and gases. FS LP is available with high-density polyethylene (HDPE) or cross-linked polyethylene
(PEX) pressure barriers with temperature ratings to 140ºF and 180º respectively.
Recommended Recommended
Maximum Nominal Ultimate Maximum
Nominal Wt/Ft Operating Pressure Burst Pressure Tensile Load
Product Name ID (in.) OD (in.) in Air (lb) (psi)** (psi @ 140ºF)*** (lb @ RT)

750 Series
FS LP 2 ½" 750* 2.00 2.54 1.05 750 4,100 3,480
FS LP 3" 750* 2.51 3.09 1.38 750 3,300 4,400
FS LP 3 ½" 750* 2.93 3.58 1.82 750 3,300 5,960
FS LP 4" 750* 3.48 4.16 2.26 750 3,200 7,960
FS LP 4 ½" 750* 3.99 4.73 2.87 750 3,200 10,440
FS LP 5" 750* 4.50 5.34 3.69 750 3,300 13,880
FS LP 6" 750* 4.97 5.86 4.36 750 3,300 16,840
1,000 Series
FS LP 2 ½" 1,000* 2.03 2.39 0.80 1,000 4,400 3,880
FS LP 3" 1,000* 2.54 2.98 1.24 1,000 4,500 6,040
FS LP 3 ½" 1,000* 3.01 3.54 1.76 1,000 4,500 8,720
FS LP 4" 1,000* 3.52 4.14 2.41 1,000 4,500 11,920
FS LP 4 ½" 1,000* 4.03 4.74 3.16 1,000 4,500 15,640
1,500 Series
FS LP 2 ½" 1,500* 2.03 2.48 1.06 1,500 6,000 5,480
FS LP 3" 1,500* 2.54 3.04 1.42 1,500 4,800 6,920
FS LP 3 ½" 1,500* 2.96 3.57 2.02 1,500 5,100 9,960
FS LP 4" 1,500* 3.47 4.18 2.76 1,500 5,100 13,680
FS LP 4 ½" 1,500* 3.98 4.79 3.61 1,500 5,100 17,840
FS LP 5" 1,500* 4.50 5.41 4.55 1,500 4,900 22,280
2,500 Series
FS LP 1 ¼" 2,500* 1.02 1.33 0.40 2,500 8,200 2,120
FS LP 1 ¾" 2,500* 1.52 1.99 0.89 2,500 8,200 4,720
FS LP 2 ½" 2,500* 2.03 2.66 1.58 2,500 8,200 8,440
FS LP 3" 2,500* 2.54 3.32 2.45 2,500 8,200 13,120
FS LP 3 ½" 2,500* 3.05 3.98 3.52 2,500 8,200 18,840
*Represents thermoplastic barrier material.
**Pressure ratings are based on minimum 20-year service life using ASTM D2992 long-term test procedures. Recommended
maximum operating pressure is Fiberspar recommendation for general oilfield water, low-vapor pressure hydrocarbon and
multiphase service conditions at the maximum rated temperature. Consult Fiberspar for a recommended maximum pressure
rating for other service conditions.
***Value varies slightly depending on pressure barrier used (HDPE or PEX). For an exact value for a specific product, please
refer to the detailed specification sheet.
E = High-density polyethylene (HDPE) rated from -29ºF to 140ºF
X = Cross-linked polyethylene (PEX) rated from -29ºF to 180ºF
All products are hydrotested to 1.5 times maximum recommended operating pressure. Material selection is based on the desired
operating temperature and chemical compatibility of FS LP constituents with fluids.
Fiberspar pipe is covered by one or more of the following U.S. Patents: pat. 5,921,285, pat. 5,908,049; pat. 5,913,337; pat.
6,004,639; pat. 6,016,845; pat. 6,148,866; pat. 6,286,558; pat. 6,357,485; pat. 6,361,299; pat. RE 35,081, pat. 6,604,550; pat.
5,176,180; and one or more of the following Canadian patents: pat. 2,076,391, pat. 2,233,295 and pat. 2,282,358.

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 23 of 27


FIBERSPAR LINEPIPE/J SPECIFICATIONS
FS LPJ is available with high-density polyethylene (HDPE) or cross-linked polyethylene (PEX) pressure barriers with
temperature ratings to 140ºF and 180ºF respectively
Recommended
Maximum Operating Nominal Ultimate Recommended
Nominal Wt/Ft in Pressure** Burst Pressure Maximum Tensile
Product Name ID (in.) OD (in.) Air (lb) (psi) (psi @ 140ºF) Load (lb @ RT)

1,000 Series

FS LPJ 2 ½" 1,000* 2.03 2.59 1.13 1,000 4,500 4,000

FS LPJ 3" 1,000* 2.54 3.22 1.71 1,000 4,300 6,000

FS LPJ 3 ½" 1,000* 3.01 3.83 2.45 1,000 4,500 8,720

FS LPJ 4" 1,000* 3.52 4.44 3.25 1,000 4,500 11,920

FS LPJ 4 ½" 1,000* 4.03 5.04 4.11 1,000 4,500 15,640

1,500 Series

FS LPJ 2 ½" 1,500* 2.03 2.68 1.39 1,500 6,000 5,480

FS LPJ 3" 1,500* 2.54 3.29 1.93 1,500 4,900 6,960

FS LPJ 3 ½" 1,500* 2.96 3.87 2.72 1,500 5,100 9,960

FS LPJ 4" 1,500* 3.47 4.48 3.60 1,500 5,100 13,680

FS LPJ 4 ½" 1,500* 3.98 5.09 4.57 1,500 5,100 17,840

FS LPJ 5" 1,500* 4.50 5.71 5.63 1,500 4,900 22,280

2,500 Series

FS LPJ 2 ½" 2,500* 2.03 2.87 1.96 2,500 8,200 8,480

FS LPJ 3" 2,500* 2.54 3.59 3.05 2,500 8,200 13,200

FS LPJ 3 ½" 2,500* 3.05 4.28 4.30 2,500 8,200 18,800

*Represents thermoplastic barrier material.


**Pressure ratings are based on minimum 20-year service life using ASTM D2992 long-term test procedures. Recommended
maximum operating pressure is Fiberspar recommendation for general oilfield water, low-vapor pressure hydrocarbon and multi-
phase service conditions at the maximum rated temperature. Consult Fiberspar for a recommended maximum pressure rating for
other service conditions.
E = High-density polyethylene (HDPE) rated from -34°C to 60°C (-29°F to 140°F)
X = Cross-linked polyethylene (PEX) rated from -34°C to 82°C (-29°F to 180°F)
All products are hydrotested to 1.5 times maximum recommended operating pressure. Material selection is based on the desired
operating temperature and chemical compatibility of FS LP constituents with fluids.
Fiberspar pipe is covered by one or more of the following U.S. Patents: pat. 5,921,285, pat. 5,908,049; pat. 5,913,337; pat.
6,004,639; pat. 6,016,845; pat. 6,148,866; pat. 6,286,558; pat. 6,357,485; pat. 6,361,299; pat. RE 35,081, pat. 6,604,550; pat.
5,176,180; and one or more of the following Canadian patents: pat. 2,076,391, pat. 2,233,295 and pat. 2,282,358.

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 24 of 27


FIBERSPAR LINEPIPE Allowable Bend Radii
When installing FS LP LinePipe always maintain the largest possible bend radius that the installation
allows. However, where conditions require a tight bend, never exceed the minimum allowable bend
radius listed be low.
Minimum Allowable Bend Radius Minimum Allowable Spooling
Product Identity for Installation (in) Diameter (in)

750 Series
FS LP 2 1/2" 750* 39 78

FS LP 3" 750* 48 96
FS LP 3 1/2 " 750* 56 112

FS LP 4" 750* 66 132

FS LP 4 1/2 " 750* 76 152

1, 000 Series
FS LP 2 1/2" 1,000* 40 68

FS LP 3" 1,000* 50 86
FS LP 3 1/2 " 1,000* 59 102

FS LP 4" 1,000* 69 118

FS LP 4 1/2 " 1,000* 79 136

1,500 Series
FS LP 2 1/2" 1,500* 41 70

FS LP 3" 1,500* 51 88

FS LP 3 1/2" 1,500* 60 104

FS LP 4" 1,500* 70 120

FS LP 4 1/2" 1,500* 80 138

2,500 Series
FS LP 1 1/4" 2,500* 22 38

FS LP 1 3/4" 2,500* 33 56
FS LP 2 1/2" 2,500* 44 76

FS LP 3" 2,500* 55 94

FS LP 3 1/2" 2,500* 66 114

*Represents thermoplastic barrier material.


specific product, please refer to the detailed specification sheet.

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 25 of 27


FIBERSPAR LINEPIPE RECOMMENDED
TEST PRESSURES
This table provides recommended test pressures to be used on LinePipe products after installation.

Product Identity Minimum Recommended (psi) Maximium Allowable (psi)

750 Series
FS LP 2 1/2" 750* 900 1,12 5

FS LP 3" 750* 900 1,125


FS LP 3 1/2 " 750* 900 1,125

FS LP 4" 750* 900 1,125

FS LP 4 1/2 " 750* 900 1,125

1,000 Series
FS LP 2 1/2" 1,000* 1,200 1,500

FS LP 3" 1,000* 1,200 1,500


FS LP 3 1/2 " 1,000* 1,200 1,500

FS LP 4" 1,000* 1,200 1,500


FS LP 4 1/2 " 1,000* 1,200 1,500

1,500 Series
FS LP 2 1/2" 1,500* 1,800 2,250
FS LP 3" 1,500* 1,800 2,250
FS LP 3 1/2" 1,500* 1,800 2,250
FS LP 4" 1,500* 1,800 2,250
FS LP 4 1/2" 1,500* 1,800 2,250

2,500 Series
FS LP 1 1/4" 2,500* 3,000 3,750

FS LP 1 3/4" 2,500* 3,000 3,750


FS LP 2 1/2" 2,500* 3,000 3,750
FS LP 3" 2,500* 3,000 3,750
FS LP 3 1/2" 2,500* 3,000 3,750

*Represents thermoplastic barrier material.

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 26 of 27


FIBERSPAR LINEPIPE Shear Loop Table
This table provides information on sizing proper shear loops to ensure maximum tensile limits of the
LinePipe are not exceed during installation.

Max. Average
Recommended Max. Allowable Shear Breaking
Tensile Load Installation Load Loop Strength
Product Identity (lbs) (lbs) OD (in) Type (lbs)

750 Series
FS LP 2 1/2" 750* 3,480 4,350 5/32 AC 2,781
FS LP 3" 750* 4,400 5,500 3/16 AC 4,261

FS LP 3 1/2 " 750* 5,960 7,450 _ AC 6,783


FS LP 4" 750* 7,960 9,950 _ AC 6,78 3
FS LP 4 1/2 " 750* 10,440 13,050 5/16 AC 10,041

1,000 Series
FS LP 2 1/2" 1,000* 3,880 4,850 3/16 AC 4,261
FS LP 3" 1,000* 6,040 7,550 _ AC 6,783
FS LP 3 1/2 " 1,000* 8,720 10,900 _ AC 6,783
FS LP 4" 1,000* 11,920 14,900 5/16 AC 10,041

FS LP 4 1 /2 " 1,000* 15,640 19,550 3/8 626 IWRC 13,525

1,500 Series
FS LP 2 1/2" 1,500* 5,480 6,850 3/16 AC 4,261

FS LP 3" 1,500* 6,920 8,650 _ AC 6,783


FS LP 3 1/2" 1,500* 9,960 12,450 5/16 AC 10,041

FS LP 4" 1,500* 13,680 17,100 3/8 626 IWRC 13,525


FS LP 4 1/2" 1,500* 17,840 22,300 3/8 626 IWRC 13,525

2,500 Series
FS LP 1 1/4" 2,500* 2,120 2,650 1/8 AC 1,881
FS LP 1 3/4" 2,500* 4,720 5,900 3/16 AC 4,261

FS LP 2 1/2" 2,500* 8,440 10,550 _ AC 6,783


FS LP 3" 2,500* 13,120 16,400 5/16 AC 10,041

FS LP 3 1/2 " 2,500* 18,840 23,550 7/16 626 IWRC 17,856

To use this chart:


1. Locate the size of Fiberspar LinePipe to be installed.
2. Locate the size and type of Shear Loop to be used.

Manual GIG01 rev 032807  2007 Fiberspar LinePipe LLC Page 27 of 27

You might also like