Professional Documents
Culture Documents
Training
Report
Chandrapur Super
Thermal Power Station
MAHAGENCO
(CSTPS)
By-
GIRISH M MADAVI
NBN Sinhgad School of Engineering, Pune
Dept. of Electrical Engineering
(07/12/2016 to 04/01/2017 )
Industrial Training Report 2016
➢ Table of Contents
5.2 Turbine 32
5.3 Generator 38
5.4 Condenser 46
1|Page
Industrial Training Report 2016
1. OVERVIEW
The Mahanirmiti or Mahagenco (Maharashtra State Power
Generation Company Limited – (MSPGCL) formerly known as MSEB (
Maharashtra State Electricity Board) is the major power generating
company in the state of Maharashtra, Western India. With a total
generation of 10,737 MW, it is the second largest power producing
company in India. The power generated by Mahagenco is supplied
to the State of Maharashtra. It was a part of Maharashtra State
Electricity Board (MSEB) until 06th June 2005 MSEB is trifurcated in 3
companies as follows-
2|Page
Industrial Training Report 2016
3|Page
Industrial Training Report 2016
• Capacity
Total 9 3340
4|Page
Industrial Training Report 2016
With the total capacity of 3340MW, the plant is largest power plant in
the Maharashtra and formely second largest in 1997 in world. It
accounts to more than 35% of total Maharashtra needs. The plant
gets water supply from Erai Dam when in normal conditions. In the
summer of 2010 due to less water in Erai, the plant also got water
supply from Chargaon Dam.
5|Page
Industrial Training Report 2016
❖ Water treatment.
❖ Coal analysis.
❖ Oil tests.
❖ Flue gas analysis.
6|Page
Industrial Training Report 2016
Flash mixture
Clariflocculator
Water sump
7|Page
Industrial Training Report 2016
One day reserve tank is used to store sufficient water storage, which
will last long nearly one day. Sometimes water supply from dam is
interrupted due to certain interrupts. Therefore to continue plant
operation without any interrupts. Water from one day reserve is
taken out. Water is stored in this tank, due these suspended
particles, heavy impurities, silica particles settled down here.
Besides this, one day reserve tank is used as a water source during
any emergency.
Flash mixture
Alum & lime is added in water. Effect of adding alum & lime is
explain as follows-
Addition of lime
8|Page
Industrial Training Report 2016
Clariflocculator-
9|Page
Industrial Training Report 2016
Rapid sand filters contains relatively coarse sand and other granular
media like bolder to remove particles and impurities that have been
trapped in a floc through the use of flocculation chemicals—
typically salts of aluminium or iron. Water and flocs flows through
the filter medium under gravity or under pumped pressure and the
flocculated material is trapped in the sand matrix. Mixing,
flocculation and sedimentation processes are typical treatment
stages that precede filtration. Chemical additives, such as
coagulants, are often used in conjunction with the filtration system.
Water sump-
Water sump is a water storage tank in which pretreated water is
stored. From thank water is sent for post treatment.
Post treatment is different for both-
• Demineralized water (D.M. water)
• Soften water
Demineralized water-
DM water is demineralized water . Dissolved impurities and dissolved
gases in water. Sometimes water is hard, temporary hardness or
permanent hardness and which is badly affects the boiler which
helps formation of scales in sides the boiler.
In D.M. water plant , water is passed through activated carbon filter
for absorbing dissolved carbon dioxide. For removing temporary
hardness and permanent hardness ion exchanging process used. By
Ion - exchange process from which the minerals have been
removed and get Demineralized water.
Demineralized water have following qualities-
❖ Neutral P.H (6.5-7.5).
❖ Conductivity of water (<10µs/cm).
11 | P a g e
Industrial Training Report 2016
screening
settling
Chemical dosing
coagulation
Screening-
During screening process all the suspended particles are removed in
this process.
Settling-
Water is stored in one day reserve tank for one day. During this
heavy particles are settled down.
Chemical Dosing- In chemical dosing alum & lime is added in
water.
Coagulation-
Coagulation is a process is a joining small particle together to form
large particles. Due to chemical dosing, floc is produced.
Post-treatment of Water-
12 | P a g e
Industrial Training Report 2016
De-gaser
13 | P a g e
Industrial Training Report 2016
De-gaser tank
Working Principle-
In pressure sand filter raw water flows down wards through the filter
bed and as the suspended matter- which has usually been treated
14 | P a g e
Industrial Training Report 2016
The filter is now taken out of service and cleaning of the filter is
effected by flow reversal. To assist in cleaning the bed, the
backwash operation is often preceded by air agitation through the
under drain system. The process of air scouring agitates the sand with
a scrubbing action, which loosens the intercepted particles. The filter
is now ready to be put back into service.
15 | P a g e
Industrial Training Report 2016
Degasser-
Degasser is a device in which dissolved gases from water is removed.
It also removes small bubbles trappeped in water layer.
16 | P a g e
Industrial Training Report 2016
Degasser tank-
In this tank water from the degasser is stored. this water is send to
strong base anion bed.
17 | P a g e
Industrial Training Report 2016
Water
Vessel Impurities Regenerative capacity
element (M3)
Gelatinous Backwash by 8500
P.S.F. material filtered water
18 | P a g e
Industrial Training Report 2016
19 | P a g e
Industrial Training Report 2016
20 | P a g e
Industrial Training Report 2016
Random samples are taken out from various mines and above
analysis are done on that coal sample. According to it various
grades are give to the coal. In WCL mines ‘F.’ grade coal is seen.
1unit=Kwh
Transportation of coal-
Transportation
21 | P a g e
Industrial Training Report 2016
22 | P a g e
Industrial Training Report 2016
23 | P a g e
Industrial Training Report 2016
24 | P a g e
Industrial Training Report 2016
heat the air blown into the furnace and warm the feedwater supply.
Such watertube boilers in thermal power station are also
called steam generating units.
25 | P a g e
Industrial Training Report 2016
In CSTPS,
26 | P a g e
Industrial Training Report 2016
Economizer-
A feedwater economizer reduces steam boiler fuel requirements by
transferring heat from the flue gas to incoming feedwater. Boiler flue
gases are often rejected to the stack at temperatures higher than
the temperature of the generated steam.
Fans in boiler-
27 | P a g e
Industrial Training Report 2016
Cycles of boiler-
Coal mill
28 | P a g e
Industrial Training Report 2016
F.D.Fan
boiler
Boiler
Air heater
Electrostatic precipitator
stack
Boiler Maintenance-
Blowdowns-
Boiler blowdown is removal of water from the boiler. It is done in
order to remove the amount of solids in the
water, and is performed as either bottom (sludge) blowdown, or
continuous (surface) blowdown. The blowdown frequency and
duration is primarily determined by the boiler water analysis. The
water quality will vary greatly
based on boiler type and size, amount of condensate return,
and boiler water treatment program.
• Fly ash.
• Bottom ash.
30 | P a g e
Industrial Training Report 2016
Fly ash is light in weight, and it flue with flue gases. It may deposite on
the water tube surface inside the boiler. Due which less heat is
absorbed by the water tube & hence efficiency of the boiler is
lowered down. Hence it is necessary to clean the boiler water tube
surface.
It is used to clean to boiler walls & water tube surface near to boiler
walls.
Two soot blower of 10m are used from both side of boiler.
31 | P a g e
Industrial Training Report 2016
5.2 Turbine
❖ Impulse turbine.
❖ Reaction turbine.
• Type of compounding.
• Type of blading.
• Division of flow.
• Type of steam flow.
• Type of exhausting condition.
The Turbine contained one row of stationary blade & one row of
rotating blades alternatively. The fixed blades are carefully shaped
to direct the flow of steam against the moving blades at an angle
and a velocity that will maximize the conversion of the steam's heat
energy into the kinetic energy of rotary motion. Because the steam's
32 | P a g e
Industrial Training Report 2016
The steam from the boiler is initially provided to high pressure turbine
(H.P. turbine). Steam is expanded inside H.P. turbine .H.P. gives the
starting torque & operating speed to the turbine rotor. The
expanded steam from the H.P. turbine again brought into the boiler
for heating. After rising the temperature of steam, it is fed to the
intermediate pressure turbine (I.P.).then this steam is supplied to the
low pressure turbine (L.P.). The function of I.P. turbine & L.P. turbine is
to provide torque to the rotor.
33 | P a g e
Industrial Training Report 2016
• Hydraulically operated.
• Operate live steam
Control valves used to control the flow of steam in boiler. During light
load period, by controlling flow of steam we can generate limited
electricity. Control valves are mounted on casing of H.P. turbine at
the middle bearing side, it is common for H.P. & I.P turbine.
34 | P a g e
Industrial Training Report 2016
Cycles of turbine
Water sump
35 | P a g e
Industrial Training Report 2016
Condenser
Hot well
De aerator
36 | P a g e
Industrial Training Report 2016
economizer
Boiler drum
37 | P a g e
Industrial Training Report 2016
5.3 Generator
Stator Construction-
Stator winding-
38 | P a g e
Industrial Training Report 2016
END WINDING:
In the end winding, the bars are arranged close to each other.
Lower as well as upper layers of bars are braced with terelyne cord
with binding ring as well as with adjacent bars. Bus bars are
connected to bring out the three phases & six neutrals. These bus
bars are connected with terminal bushings. Both are water cooled,
connection is made by brazing the two lugs properly.
TERMINAL BUSHING :
Three phases and six neutral terminals are brought
out from the stator frame through bushings, which are capable of
withstanding high voltage, and provided with gastight joints. The
bushings are bolted to the bottom plate of the terminal box, with
their mounting flanges. The terminal box that is welded underneath
the stator frame at exciter end is made of nonmagnetic
Steel to avoid admissible temperature rise. The conductor of the
bushing is made of high conductivity copper tube. A copper pipe is
connected to circulate water for cooling. The terminal bar
conductor is housed in porcelain insulator which can be mounted
on the terminal box by means of ring.
The bushing is connected to terminal bus bar by means of flexible
copper leads for making the electrical connections conveniently.
Rotor Construction
In rotor construction following are the important parts of rotor, which
require very careful operation during its construction.
➢ Rotor winding.
➢ Rotor shaft.
39 | P a g e
Industrial Training Report 2016
Rotor winding –
Rotor winding is mounted on the rotor shaft. The field winding consists
of several coils inserted into the longitudinal slots of the rotor body.
The coils are wound around the poles so that one north magnetic
pole and one south magnetic pole are obtained on shaft. Rotor
winding is excited by the excitation voltage provided by excitation
system.
Rotor winding conductor are made up of hard drawn
silver bearing copper. Apart from low electrical resistance this grade
exhibits high creep resistance so that coil deformations due to
thermal cycling due to start and stop operation are minimum.
Insulation winding is made up of Layer of glass laminates insulates
the Individual turns from each other. This laminate is built by glass
prepped strips on the turn of copper and baked under pressure and
temperature.
Due to rotation & flow of current in winding heat is generated. if
excessive heat is generated, it may damage the winding insulation
& weaken the rotor. Hence winding cooling is necessary. It can be
done by hydrogen cooling. Hydrogen gas can be rich up to deepest
layer of winding hence efficient cooling is done.
Rotor shaft-
The rotor shaft is long forging measuring more than 9
meters in length and slightly more than one meter in diameter. The
main constituents of the steel are chromium, molybdenum. Nickel,
and vanadium. The shaft and body are forged integral to each
other by drop forging process.
On 2/3 of its circumference approximately, the rotor
body is provided with longitudinal slots to accommodate field
windings. The slots pitch is selected in such a way that two solid poles
displaced by 180 are obtained.
D.C exciter is also mounted on the generator shaft.
Fans-
Two single stage axial flow propeller type fans circulate the
generator cooling gas. Fitted on either sides of rotor body
Bearings-
40 | P a g e
Industrial Training Report 2016
Shaft Seal –
The locations where the rotor shaft passes through the stator casing,
are provided with radial seal rings. The seal ring is guided in the seal
body, which is bolted on to the end shield and insulated to prevent
the flow of shaft currents. The seal ring is lined with babbit on the
shaft journal side. The gap between the seal ring and the shaft is
sealed with seal oil. The seal oil is supplied to the sealing gap from
the seal body via radial holes and an annular groove in the seal ring.
To ensure effective sealing, the seal oil pressure in the annular gap is
maintained at a higher level than the gas pressure within the
generator casing.
Generator
Generating transformer
National grid
41 | P a g e
Industrial Training Report 2016
Cooling-
• Hydrogen Cooling-
42 | P a g e
Industrial Training Report 2016
➢ Exciter
43 | P a g e
Industrial Training Report 2016
➢ Generator Protection-
44 | P a g e
Industrial Training Report 2016
❖ Electrical protection.
➢ Unbalanced load.
➢ Stator winding.
45 | P a g e
Industrial Training Report 2016
5.4 Condenser
Condenser is used to condense the steam out from the L.P. turbine.
Cooled water is circulating inside the water tube of condenser. Heat
of the steam is transferred to cooled water inside water tube. Hence,
due to this steam gets condense. Condensate is collected in hot
well, which is just below the condenser. The heated water inside the
water tube is sent to the cooling tower in which temperature of this
water is decreased to the ambient temperature.
Shell- The shell is the condenser's outermost body and contains the
heat exchanger tubes. The shell is fabricated from carbon
steelplates and is stiffened as needed to provide rigidity for the
shell. At the bottom of the shell, where the condensate collects, an
outlet is installed. In some designs, a hotwell is provided. Condensate
46 | P a g e
Industrial Training Report 2016
In CSTPS, there are total 3 C.E. pumps are installed per condenser
unit in 210MW unit. Out of these 2 C.E. pumps are running &1 is stand
by at a time.
Cooling Tower-
the water from the water tube of condenser. Water in water tube
take heat from the steam from the turbine.
48 | P a g e
Industrial Training Report 2016
Component Function
49 | P a g e
Industrial Training Report 2016
Transformer insulation-
• Excellent flexibility.
• Heat resistant.
• Moisture resistant.
Transformer core & both winding are immersed in oil filled up in oil
tank. This transformer oil should have following properties-
Breather-
Conservator –
51 | P a g e
Industrial Training Report 2016
Buchholz Relay-
52 | P a g e
Industrial Training Report 2016
Fall of oil level means lowering the position of float and thereby tilting
the mercury switch. The contacts of this mercury switch are closed
and an alarm circuit energized. Sometime due to oil leakage on the
main tank air bubbles may be accumulated in the upper part the
Buchholz Container which may also cause fall of oil level in it and
alarm circuit will be energized. By collecting the accumulated gases
from the gas release pockets on the top of the relay and by
analyzing them one can predict the type of fault in the transformer.
53 | P a g e
Industrial Training Report 2016
Circuit Breaker-
• Bulk oil
• Minimum oil
• Air blast
• Vacuum
• SF6 ( sulfur hexafluoride)
• CO2
Isolator-
Circuit breaker always trip the circuit but open contacts of breaker
cannot be visible physically from outside of the breaker and that is
why it is recommended not to touch any electrical circuit just by
switching off the circuit breaker. So for better safety there must be
some arrangement so that one can see open condition of the
section of the circuit before touching it. Isolator is a mechanical
switch which isolates a part of circuit from system as when required.
Electrical isolators separate a part of the system from rest for safe
maintenance works.
54 | P a g e
Industrial Training Report 2016
When electricity is taken from generator itself, then CSTPS does not
need to pay for electricity required for power plant auxiliaries.
Station transformer-
56 | P a g e
Industrial Training Report 2016
6. Electrostatic Precipitator-
Stack- stack is vertical pipe through which the flue gases are
exhausted to atmosphere from boiler.
57 | P a g e
Industrial Training Report 2016
System Description
The ash handling system handles the ash by bottom ash handling
system, coarse ash handling system, fly ash handling system, ash
disposal system up to the ash disposal area and water recovery
system from ash pond and Bottom ash overflow. Description is as
follows:
Bottom ash resulting from the combustion of coal in the boiler shall
fall into the over ground, refractory lined, water impounded,
maintained level, double V-Section type/ W type steel- fabricated
bottom ash hopper having a hold up volume to store bottom ash
58 | P a g e
Industrial Training Report 2016
Under each surge hopper ash vessels shall be connected with Oil
free screw compressor for conveying the fly ash from Intermediate
Surge Hopper to silo. Total fly ash generated from each unit will be
conveyed through streams operating simultaneously and in
parallel.
Bottom Ash slurry, Fly ash slurry and the Coarse Ash slurry shall be
pumped from the common ash slurry sump up to the dyke area
which is located at a distance from Slurry pump house.
59 | P a g e
Industrial Training Report 2016
60 | P a g e
Industrial Training Report 2016
❖ Overview
61 | P a g e
Industrial Training Report 2016
❖ PV Technology Classification
62 | P a g e
Industrial Training Report 2016
63 | P a g e
Industrial Training Report 2016
64 | P a g e
Industrial Training Report 2016
65 | P a g e
Industrial Training Report 2016
❖ 1 MWp Plant
❖ 2 MWp
• Thin Film Type
66 | P a g e
Industrial Training Report 2016
• Crystalline Type
67 | P a g e
Industrial Training Report 2016
68 | P a g e