Professional Documents
Culture Documents
Authorized licensed use limited to: Abdul Shaik. Downloaded on October 10, 2009 at 03:57 from IEEE Xplore. Restrictions apply.
2108 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 24, NO. 4, OCTOBER 2009
Authorized licensed use limited to: Abdul Shaik. Downloaded on October 10, 2009 at 03:57 from IEEE Xplore. Restrictions apply.
BRENNA et al.: NEW PROPOSAL FOR PQ AND CUSTOM POWER IMPROVEMENT: OPEN UPQC 2109
the mains 95% of the time, as established by the IEEE Std 1159
“IEEE Recommended Practice for Monitoring Electric Power
Quality” and European EN50160; therefore, the storage system
must not discharge itself. Outside of this range, active power
can be used to compensate the disturbances, in the same way as
the usual series compensation devices [6], [7], when a storage
system is present.
The shunt units consist of an ac/dc power converter, similar to
the one used in the series unit, connected to an energy storage
system and a set of static switches (SS) [17]. The shunt unit,
depending on the state of the network voltage, can supply either
the entire load, or a part of the load.
There are two different modes of OPEN UPQC operation:
• compensator: when the PCC voltage is within its operation
limits, the SS are closed, the series unit works as a three-
phase voltage generator and the shunt units work as current
generators;
• back-up: when the PCC voltage is outside of its operation
limits, the SS are open, decoupling the network and the
load-compensator system. Each sensitive load is supplied
by its shunt unit, which acts as a sinusoidal voltage gen-
erator, using the energy stored in the storage system as an
energy source.
Authorized licensed use limited to: Abdul Shaik. Downloaded on October 10, 2009 at 03:57 from IEEE Xplore. Restrictions apply.
2110 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 24, NO. 4, OCTOBER 2009
(2)
Therefore, the angle can oscillate between the upper
and lower limits and , obtained when
and respectively, in the area highlighted Fig. 5. Compensation limits of the OPEN UPQC: with nonactive power ex-
in Fig. 4. The angle can be calculated by the equation shown at change only (light gray) and with also active power exchange (dark gray) by the
shunt units.
the bottom of the page.
The current phasor can move along the black dotted line,
varying the reactive power of the shunt units. In case (a1) the OPEN UPQC to stabilize the voltage at the PCC, maxi-
in particular, it is possible to obtain a power factor equal to mizing the power factor in normal operation conditions and in-
1 in the section in low voltage situations, because the line creasing its compensation limits outside of normal operation.
intercepts the black dotted line. In case (a2), the Obviously, in the case of large disturbances in that the se-
power factor is always less than 1. ries unit cannot compensate, each shunt unit can supply the load
The quantities and can be obtained with (4) in back-up mode.
and (5), as shown at the bottom of the page.
Assuming that , the range am- B. Nonactive and and Active Power Exchange
plitude can be obtained with (6) In this case, the series converter produces only nonactive
power, but the shunt units can exchange active and nonactive
(6) power with the mains. This condition could be represented as
an active network into which dispersed generations are inserted.
It can be seen that the compensating range amplitude Fig. 5 depicts the new phasor diagram of the OPEN UPQC
depends on the value that the series under the above operating conditions.
unit can inject, and on the nonactive power . The nonactive In order to avoid active power injections by the series unit,
power is susceptible to exchanges by the shunt units (length the voltage and the mains current have to be in quadrature
of the black dotted line, proportional to the loads apparent with each other. In Fig. 5, the light grey areas indicate the field in
power) and to the power factors of the equivalent loads and which can lay without active power exchanges by the shunt
. units, and the dark gray areas indicate the possible values of
In normal operation mode, the compensation strategy can be with active power exchanges by shunt units. In this case, the
implemented in various ways. For example, power factor maxi- compensating range amplitude is greater than
mization in the s section (corresponding to minimization of the without active power exchanges, but it is important to note that
current ) is a compensation strategy that can be implemented the difference is small. The phasor current can move inside of
by coordinating the series unit and the shunt ones. Therefore, the gray dotted circle, varying the active and nonactive power
communication between all the units is required. The simplest of the shunt units (movement on the black dotted line regards
solution is to employ a slow communication system that allows only nonactive power exchange).
(3)
(4)
(5)
Authorized licensed use limited to: Abdul Shaik. Downloaded on October 10, 2009 at 03:57 from IEEE Xplore. Restrictions apply.
BRENNA et al.: NEW PROPOSAL FOR PQ AND CUSTOM POWER IMPROVEMENT: OPEN UPQC 2111
Authorized licensed use limited to: Abdul Shaik. Downloaded on October 10, 2009 at 03:57 from IEEE Xplore. Restrictions apply.
2112 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 24, NO. 4, OCTOBER 2009
TABLE I
MV/LV TRANSFORMER PARAMETERS
Fig. 7. Voltage control loop of the series unit and nonactive power control loop
of the shunt units in the OPEN UPQC system.
TABLE II
The constant is obtained by a PI controller that keeps LV CABLE PARAMETERS
the voltage at the output of the series unit equal to the
rated value , as reported in the block diagram of Fig. 7.
The second control loop acts to minimize the angle
between the voltage and the current downstream of the
MV/LV transformer, in order to maximize the power factor ab-
sorption in the section. In this case, the PI controller produces
a signal , which varies from 0 to 1, and is equal to the ratio
between the desired nonactive power injectable by the shunt
units and the maximum injectable nonactive power. This signal
is sent to all shunt units by the communication system. Thus,
the injected nonactive power of the th shunt unit is equal
to
(12) The protected loads are grouped into the equivalent load ,
so all of the shunt units are represented by means of an equiv-
where is the unit’s rated power. The total nonactive power alent unit. In the same way, all of the unprotected loads are
injected by all the shunt units is grouped in the equivalent load .
All of the parameters of the three-phase MV/LV transformer
used for the simulations are reported in Table I.
(13)
The LV cables used for the following analysis, with different
power factors and loads and , are reported in Table II.
Obviously, this compensation strategy, which is useful for its In each analysis, the correct 200-m cable is chosen as a func-
fast series unit response, requires nonactive power injection by tion of the current needed to supply the equivalent load with a
the shunt units to be capable of achieving a wide compensation voltage drop of less than 3%, without considering the OPEN
range. To enhance the entire system’s performance, the power UPQC. In this way, it is possible to neglect power loss and the
losses and the voltage drops in the LV lines generally must in- voltage drop on the LV grid.
crease. However, if the power factor at the is kept high In this study, all of the converters are represented as ideal
( 0.8), these increments are negligible. Moreover, this incre- controlled voltage or current sources. Moreover, the series unit
ment can be reduced by sending a different signal to each is not equipped with a storage system. For these reasons, the
shunt unit. This allows the closest shunt units to be used to inject OPEN UPQC limits are evaluated mainly in the normal oper-
more nonactive power, avoiding useless nonactive power flows. ation mode in the following. Therefore, the series unit cannot
exchange active power with the mains.
The following figures and tables report the power factor
V. TEST NETWORK AND EVALUATION OF OPERATION LIMITS
and the mains current in the section as functions
Fig. 8 shows a simplified 400-kVA LV grid, used to validate of the network voltage . Each diagram is represented for a
the OPEN UPQC. fixed load power factor and , and is parametric in . This
Authorized licensed use limited to: Abdul Shaik. Downloaded on October 10, 2009 at 03:57 from IEEE Xplore. Restrictions apply.
BRENNA et al.: NEW PROPOSAL FOR PQ AND CUSTOM POWER IMPROVEMENT: OPEN UPQC 2113
Fig. 9. Power factors of the system and maximum line currents in case 1, for Fig. 10. Power factors of the system and maximum line currents in case 2 for
different values. The maximum voltage of the series unit is equal to 0.6 p.u. different values. The maximum voltage of the series unit is equal to 0.6 p.u.
(14) (16)
(15) The operation limits given by (16) and (17) were obtained by
The reference current is expressed in per unit (p.u.), as the using (3) and (15).
ratio between the power reference and the voltage refer- The figures reveal that:
ence. 1) the OPEN UPQC is well-adapted when the power factor
Since the network cables are correctly designed and their of the load is low. Fig. 9 shows the interval that can be
parameters are constant, the voltage drop variation when the compensated by exchanging only nonactive power when
OPEN UPQC is present can be neglected under maximum load the power factor of the load is equal to 0.8. In this case,
conditions when the load power factor is equal to 0.9 and it is the OPEN UPQC produces excellent voltage stabilization,
connected at the end of the line. especially when the parameter is greater than 0.4;
The operation limits reported in Figs. 9 and 10, which allow 2) the OPEN UPQC is not well-adapted when the power
the voltage to be fixed at the nominal value, were obtained factor of the load is high. Fig. 10 shows the interval
by assuming the above hypothesis and that the maximum in- that can be compensated by exchanging only nonactive
jectable voltage by the series unit is equal to 0.6 p.u.. power when the power factor of the load is equal to
The following results for the proposed solution were obtained 1. In this case, the OPEN UPQC does not produce good
by converting the vector diagrams of Fig. 4 into geometrical voltage stabilization, because it is too limited. It is possible
equations. to obtain voltage stabilization in normal operation mode
Authorized licensed use limited to: Abdul Shaik. Downloaded on October 10, 2009 at 03:57 from IEEE Xplore. Restrictions apply.
2114 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 24, NO. 4, OCTOBER 2009
range (between 0.9 p.u. and 1.1 p.u.) only with a high
value.
From Figs. 9 and 10, it is possible to estimate the power of
the series unit, given the maximum current value. This value disturbances and network interruptions, while the ones that be-
is equal to the product between the maximum injectable voltage long to set only require general improvement of the power
(equal to 0.6 p.u.) and the maximum line current (equal to 1.1 quality.
p.u. when and as shown in Fig. 9). There- Several solutions are available for compensating each load
fore, with slight over-sizing of the series unit, good stabilization . In the following description, only two possible solutions are
of the mains voltage is possible. The usual working conditions considered. The first solution consists of the installation of an
present an interesting case, when the power factor of load is UPS for each end user, while the second one is the installation
between 0.9 and 1, and the mains voltage is inside of the con- of a shunt unit for each load.
tractual limits (normal operation). The distribution power losses Instead, in order to obtain general power quality improvement
should be estimated, in order to understand the energy cost as- for all loads, it is possible to rebuild the LV distribution system
sociated with this solution. to increase the short circuit level in the load connection point
Under these conditions, it is always possible to compensate or to install a series unit in the MV/LV substation. Therefore,
the voltage , without considering the power factor in section three different methods for improving the power quality have
, if is greater than or equal to 0.5, as reported in Table III. been considered:
In the case of smaller spread among the shunt units • installation of a UPS for each end user. In this case, it is
, it is always possible to compensate for the voltage by not possible to improve the power quality of the distribu-
decreasing the power factor in the section. However, the power tion network. However, it is possible to compensate for all
factor will always be greater than 0.8. When the power voltage disturbances for the end users;
factor of the load is equal to one, the power factor in the • revamping of all of the LV distribution cables. In this case,
section is always close to one, and the compensation limits it is not possible to compensate for all voltage disturbances;
previously mentioned can be maintained. • installation of an OPEN UPQC. In this case, it is possible
The mains voltage limits reported in Table III change to those to compensate for most of the voltage disturbances.
reported in Table IV when it is important to keep the mains The last solution consists of the installation of a series unit
power factor between 0.9 and 1. sized for 66% of the total power loads supplied (264 kVA), while
each shunt unit has an assumed size of 5 kVA. Moreover, each
VI. COST EVALUATION UPS is assumed to have the same power, and the input stage of
each UPS is composed of PFC rectifiers.
To evaluate the costs of power quality improvement and the It is important to clarify that the storage systems cost for
economic convenience of the proposed solution, an analysis of UPS and OPEN UPQC solutions in this analysis is not consid-
the 400-kVA LV distribution network has been carried out. ered, because it primarily depends on the technologies and au-
It was supposed that the line represents an equivalent line tonomies required. The revamping cost considered here can be
in which all of the sensitive loads that make up the OPEN found in the economical analysis carried out in [17].
UPQC are connected, while the line represents an equiva- The total cost for each solution is reported in Fig. 11. They
lent line that supplies only the nonsensitive loads . Therefore, include only the devices and various materials; the installation
each load that belongs to the set needs to be protected against cost is assumed to be 50% of the device cost.
Authorized licensed use limited to: Abdul Shaik. Downloaded on October 10, 2009 at 03:57 from IEEE Xplore. Restrictions apply.
BRENNA et al.: NEW PROPOSAL FOR PQ AND CUSTOM POWER IMPROVEMENT: OPEN UPQC 2115
TABLE V
OPEN UPQC UNITS ACTIONS
Fig. 11. Comparison between installation costs of a new line, of the OPEN
UPQC and of the UPS, as functions of the compensated sensitive loads power. availability of electrical distribution operators for an infield test
will be required.
Authorized licensed use limited to: Abdul Shaik. Downloaded on October 10, 2009 at 03:57 from IEEE Xplore. Restrictions apply.
2116 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 24, NO. 4, OCTOBER 2009
[14] M. Buschmann, G. Linhofer, P. Maibach, and O. Suter, “Voltage source Roberto Faranda (M’06) received the Ph.D. degree in electrical engineering
converter based power quality solutions,” in Proc. Asia Pacific Regional from the Politecnico di Milano, Milan, Italy, in 1998.
Power Quality Seminar, Putrajaya, Malaysia, Mar. 28–31, 2005. He is an Assistant Professor with the Department of Energy, Politecnico di
[15] F. Blaabjerg, M. Newman, H. Nielsen, and J. G. Nielsen, “Control and Milano. His areas of research include power electronics, power system har-
testing of a dynamic voltage restorer (DVR) at medium voltage level,” monics, power quality, power system analysis, and distributed generation.
IEEE Trans. Power Electron., vol. 19, no. 3, pp. 806–813, May 2004. Dr. Faranda is a member of the Italian Standard Authority (CEI), the Italian
[16] K. N. Choma and M. Etezadi-Amoli, “The application of a Electrical Association (AEI), and the Italian National Research Council (CNR)
DSTATCOM to an industrial facility,” in Proc. IEEE Power Eng. Group of the Electrical Power System.
Soc. Winter Meeting, Jan. 27–31, 2002, vol. 2, pp. 725–728.
[17] A. Agustoni, E. Borioli, M. Brenna, G. Simioli, E. Tironi, and G.
Ubezio, “LV DC distribution network with distributed energy re-
sources: Analysis of possible structures,” presented at the 18th Int. Enrico Tironi received the M.S. degree in electrical engineering from the Po-
Conf. Electricity Distribution CIRED 2005, Turin, Italy, Jun. 6–9, litecnico di Milano, Milan, Italy, in 1972.
2005. He then joined the Dipartimento di Elettrotecnica, Politecnico di Milano,
[18] R. Faranda, F. Castelli Dezza, I. Mazzucco, P. Redi, and E. Tironi, where he is a Full Professor. His areas of research include power electronics,
“An interface converter for DG/storage system able to improve power power quality, and distributed generation.
quality of the load,” presented at the IEEE Power Eng. Soc., Montreal, Dr. Tironi is a member of the Italian Standard Authority (CEI), the Italian
QC, Canada, Jun. 18–22, 2006. Electrical Association (AEI), and the Italian National Research Council (CNR)
group of the Electrical Power System.
Morris Brenna (M’06) received the M.S. and Ph.D. degrees in electrical engi-
neering from the Politecnico di Milano, Milan, Italy, in 1999 and 2003, respec-
tively.
Currently, he is an Assistant Professor with the Department of Energy, Po-
litecnico di Milano. His research interests include power electronics, distributed
generation, traction systems, and electromagnetic compatibility.
Dr. Brenna is a member of the Italian Electrical Association (AEIT) and
Italian Railways Engineering Association (CIFI).
Authorized licensed use limited to: Abdul Shaik. Downloaded on October 10, 2009 at 03:57 from IEEE Xplore. Restrictions apply.