Professional Documents
Culture Documents
Prepared by:
University of Alberta
Prepared For:
1
1 Table of Contents
2 1. INTRODUCTION ..................................................................................................................................... - 4 -
3 1.1 Research Background...................................................................................................................... - 4 -
4 1.2 Literature Review ............................................................................................................................ - 5 -
5 2. EXECUTIVE SUMMARY .......................................................................................................................... - 7 -
6 2.1 Problem Definition .......................................................................................................................... - 7 -
7 2.2 Project Information ......................................................................................................................... - 7 -
8 2.3 Methodology................................................................................................................................... - 7 -
9 2.4 Data Collected ................................................................................................................................. - 7 -
10 2.5 Assumptions Made ......................................................................................................................... - 8 -
11 2.6 Findings ........................................................................................................................................... - 8 -
12 3. PROJECT SELECTION ............................................................................................................................ - 14 -
13 4. ENGINEERING DESIGNS OF THE THREE PILE SYSTEMS ....................................................................... - 16 -
14 5. PILE INSTALLATION OPERATIONS OF THE THREE PILE SYSTEMS ........................................................ - 18 -
15 5.1 Helical Pile Installation Process..................................................................................................... - 18 -
16 5.2 Driven Pile Installation Process ..................................................................................................... - 20 -
17 5.3 CIP Piles Installation Process ......................................................................................................... - 22 -
18 6. DATA COLLECTION .............................................................................................................................. - 24 -
19 6.1 Factorized Activity Duration ......................................................................................................... - 24 -
20 6.2 Cost Rate ....................................................................................................................................... - 25 -
21 6.3 Resource Requirement ................................................................................................................. - 26 -
22 7. SIMULATION MODEL CONSTRUCTION................................................................................................ - 27 -
23 7.1 Simulation Engine ......................................................................................................................... - 27 -
24 7.2 Non-productive Time and Performance Index ............................................................................. - 27 -
25 7.2.1 PI Value for Helical Pile .......................................................................................................... - 27 -
26 7.2.2 PI Value for Driven Pile .......................................................................................................... - 28 -
27 7.2.3 PI Value for CIP Pile ................................................................................................................ - 28 -
28 7.3 Simulation Model and Simulation Results .................................................................................... - 29 -
29 7.3.1. Simulation Model for Helical Pile Installation ....................................................................... - 29 -
30 7.3.2. Simulation Model for Driven Pile Installation ....................................................................... - 30 -
-1-
31 7.3.3 Simulation Model for CIP Pile Installation ............................................................................. - 30 -
32 8. COST ESTIMATION .............................................................................................................................. - 31 -
33 8.1 Cost Estimation for Helical Pile ..................................................................................................... - 31 -
34 8.1.1 Material Cost for Helical Pile .................................................................................................. - 31 -
35 8.1.2 Labor and Equipment Charge-out Rate for Helical Pile ......................................................... - 31 -
36 8.1.3 Shipping Cost for Helical Pile.................................................................................................. - 32 -
37 8.1.4 Project Total Duration and Separate Activity Durations for Helical Pile Installation............. - 33 -
38 8.1.5 Detailed Cost Estimation of Duration Related Cost for Helical Pile ....................................... - 34 -
39 8.1.6 Total Cost for Helical Pile ....................................................................................................... - 35 -
40 8.2 Cost Estimation for Driven Pile ..................................................................................................... - 35 -
41 8.2.1 Material Cost for Driven Pile .................................................................................................. - 35 -
42 8.2.2 Labor and Equipment Charge-out Rate for Driven Pile ......................................................... - 36 -
43 8.2.3 Shipping Cost for Driven Pile .................................................................................................. - 37 -
44 8.2.4 Project Total Duration for Driven Pile Installation ................................................................. - 38 -
45 8.2.5 Detailed Cost Estimation of Duration Related Cost for Driven Pile ....................................... - 39 -
46 8.2.6 Total Cost for Driven Pile ....................................................................................................... - 40 -
47 8.3 Cost Estimation for CIP Pile ........................................................................................................... - 41 -
48 8.3.1 Basic Instructions ................................................................................................................... - 41 -
49 8.3.2 Material Cost for CIP Pile ....................................................................................................... - 41 -
50 8.3.3 Labor and Equipment Charge-out Rate for CIP Pile ............................................................... - 43 -
51 8.2.4 Shipping Cost for CIP Pile ....................................................................................................... - 44 -
52 8.3.5 Project Total Duration for CIP Pile Installation ...................................................................... - 46 -
53 8.3.6 Detailed Cost Estimation of Duration Related Cost for CIP Pile............................................. - 46 -
54 8.3.7 Total Cost for CIP Pile ............................................................................................................. - 47 -
55 9. COST COMPARISON AND RISK ANALYSIS ............................................................................................ - 49 -
56 9.1 Cost Comparison with Key Performance Index (KPI) .................................................................... - 49 -
57 9.2 Contingency Analysis .................................................................................................................... - 51 -
58 9.2.1 Contingency Analysis for helical Pile ...................................................................................... - 51 -
59 9.2.2 Contingency Analysis for Driven Pile...................................................................................... - 52 -
60 9.2.3 Contingency Analysis for CIP Pile ........................................................................................... - 54 -
-2-
61 10. CROSS VALIDATION ........................................................................................................................... - 56 -
62 10.1 Productivity Cross Checking ........................................................................................................ - 56 -
63 10.2 Performance Index (PI) Cross Checking ...................................................................................... - 57 -
64 10.3 Bid Price Cross Checking ............................................................................................................. - 57 -
65 10.3.1 Bid Price Cross Checking for Helical Pile .............................................................................. - 57 -
66 10.3.2 Bid Price Cross Checking for Driven Pile .............................................................................. - 58 -
67 10.3.3 Bid Price Cross Checking for CIP Pile .................................................................................... - 58 -
68 CONCLUSION........................................................................................................................................... - 59 -
69 12. FOLLOW-UP IN NEAR FUTURE .......................................................................................................... - 60 -
70 11.1 Statistics Based Cost Estimation ................................................................................................. - 60 -
71 11.2 Installation Speed Investigation based on Data Logger .............................................................. - 60 -
72 11.3 Contingency Analysis .................................................................................................................. - 60 -
73 11.4 Onsite Mobilization Investigation ............................................................................................... - 60 -
74 ACKNOWLEDGEMENTS ........................................................................................................................... - 61 -
75 REFERENCE .............................................................................................................................................. - 61 -
76 Appendix A: Questionnaire for Helical Pile ............................................................................................. - 63 -
77 Appendix B: Questionnaire for Driven Pile ............................................................................................. - 66 -
78 Appendix C: Questionnaire for CIP Pile................................................................................................... - 70 -
79 Appendix D: Site Layout and Pile Distribution ............................................................................................ 74
80 Appendix E: Design Loads ........................................................................................................................... 75
81 Appendix F: Screw Pile Installation Approval Procedure ............................................................................ 76
82 Appendix G: Simulation Model for Three Pile Systems .............................................................................. 77
83
84
-3-
85 1. INTRODUCTION
-4-
115
116 (1) Helical Pile (2) Driven Pile (3) CIP Pile
118 Almita is interested in collaborating with Dr. Ming Lu’s team (PI, NSERC Engage Grant,
119 Associate Professor at the University of Alberta) to look into the cost and schedule performances
120 for each of the three foundation systems, keeping technical performance constant. A PhD student
121 at U of A (Eason Chaojue Yi), who has suitable engineering background and necessary skills,
122 has been assigned as leading researcher to work out this project under direct supervision of PI
123 and engineers and managers at Almita. Another PhD student at U of A (Cherry Chaoyu Zheng)
124 together with a research assistant (Tareq Hasan) worked closely with Eason as a team to provide
125 consistent support in running this project.
136 In general, the final choice of the type of pile for any job is dictated by the following factors: (1)
137 structural details (type, location) and loadings; (2) subsurface conditions, (3) probable
138 performance of the foundation, (4) knowledge of the site and its environment; (5) pile materials
139 and durability; (6) safety, and (7) economy (Peck et al, 1974; Tomlinson & Woodward, 2008).
140 As per AASHTO (2012), a potential foundation solution may appear to be the most economical
141 from purely a design perspective, but may not be the most economical if limitations on
142 construction activities are fully considered. However, the availability of local engineering and
143 construction expertise, availability of materials and equipment, environmental limitations, costs
-5-
144 for both materials, materials handling and crew installation (including associated substructure
145 costs such as pile cap or sub-superstructure connections) need to be considered in a
146 comprehensive comparison.
147
-6-
148 2. EXECUTIVE SUMMARY
-7-
185 collection methods such as telephone interview, site interview and online benchmarking database
186 complements in building the final database. The collected data basically includes: (1) cost data
187 for material, labor, equipment and various other indirect costs; (2) duration for each defined
188 activity decomposed from the whole installation process of each pile system and (3) resources
189 required (type and quantity), i.e. crews (labor, equipment). All the data were compiled and
190 analyzed in Excel Sheet.
-8-
Bid Price (Helical Pile)
906.6K
1
887.1K
0.9
884.3K
0.8
881.8K
0.7
879.4K
Percentiles
0.6
877.9K
0.5
876.4K
0.4
875.1K
0.3
873.3K
0.2
871.0K
0.1
863.0K
0
863041 867886 872731 877576 882421 887266 892111 896956 901801 906646
Total Costs($)
219
220 Fig2 (1). Bid Price Range for Helical Pile
221
0.6
1.083M
0.5
1.081M
0.4
1.079M
0.3
1.077M
0.2
1.075M
0.1
1.06
0 M
1060037 1070037 1080037 1090037 1100037 1110037 1120037
Total Costs($)
222
223 Fig2 (2). Bid Price Range for Driven Pile
-9-
Bid Price (CIP Pile) 1.424M
1
1.352M
0.9
1.336M
0.8
1.315M
0.7
1.305M
Percentiles
0.6 1.293M
0.5
1.282M
0.4
1.272M
0.3
1.267M
0.2
1.261M
0.1
1.245M
0
1245558 1265558 1285558 1305558 1325558 1345558 1365558 1385558 1405558
Total Cost($)
224
225 Fig2 (3). Bid Price Range for CIP Pile
226 Fig2 . Bid Price Range of Three Pile Systems
227
0.6
28.4D
0.5
28.3D
0.4
28.2D
0.3
28.1D
0.2
27.9D
0.1
27.3D
0
27.3 27.7 28.1 28.5 28.9 29.3 29.7 30.1 30.5
Total Project Duration (days)
228
229 Fig3 (1). Installation Time Range for Helical Pile
230
- 10 -
Installation Time (Driven Pile)
33.8D
1
32.1D
0.9
31.8D
0.8
31.7D
0.7
31.6D
Percentiles
0.6
31.4D
0.5
31.4D
0.4
31.2D
0.3
31.1D
0.2
31.0D
0.1
30.0D
0
30.0 30.5 31.0 31.5 32.0 32.5 33.0 33.5
Total Project Duration (days)
231
232 Fig3 (2). Installation Time Range for Driven Pile
233
234
0.6
52.3D
0.5
51.7D
0.4
51.3D
0.3
51.0D
0.2
50.7D
0.1 49.9D
0
49.9 50.9 51.9 52.9 53.9 54.9 55.9 56.9 57.9 58.9
- 11 -
239
240 Fig4. Bid Price Comparison of Three Pile Systems
- 12 -
START
NO
YES
1. LOADS
GENERALIZE 2. STRUCTURE LAYOUT REPORT TO CHIEF
“ENGINEERING 3. LATERAL LOADS ENGINEER FOR APPLICABLE?
SCENARIOS” 4. UNDERGROUND WATER TABLE EXAMINATION
5. SOIL PROFILE
YES
DESIGN DATABASE
NO
GENERALIZE
OPERATION STEPS AND
“ENGINEERING SURVEY AND SITE VISIT APPLICABLE?
DRAWINGS
SCENARIOS”
YES
OPERATION
DATABASE
QUESTIONNAIRE
SURVEY
NO
DATABASE
SUFFICIENT?
YES
YES REFER TO
MISSING
BENCHMARKING
IMPORTANT
DATABASE OR OTHER
DATA?
OPEN SOURCES
NO
OUTPUT: INSTALLATION
TIME AND
PRODUCTIVITY
THREE-STEPPED
VALIDATION
NO
OUTPUTS MEET
EXPECTATIONS?
YES
END
241
242 Fig5. Flowchart of the Proposed Methodology
- 13 -
243 3. PROJECT SELECTION
244 Project scenario is selected from the project database containing four major categories of
245 foundation system engineering: (1) distributed foundation engineering (e.g. foundations for
246 power transmission towers); (2) centralized foundation engineering (e.g. oil sands upgrader
247 foundation); (3) remote site location with limited access to construction materials and means
248 (such as concrete plant, trucks, haul roads) and (4) urban site location with easy access to
249 construction materials and means.
250
251 The defined project has the flexibility to apply any design option in the predefined three pile
252 systems. Through brainstorming with Almita engineers, the project scenario was finalized as a
253 power substation project, shown in Figure 6.
254
255
256 Fig6. Power Substation project in Alberta
257
258 (1) Steel Pile (driven or helix depend on soil) (2) Helical Piles (Group)
- 14 -
259
260 (3) Concrete Piles (with pier)
261 Fig7. Three Pile Systems for Power Substation
262
- 15 -
263 4. ENGINEERING DESIGNS OF THE THREE PILE SYSTEMS
264 The design of the three pile systems was done by Almita engineers with full design
265 specifications as follows:
266 (1) Location
267 The site is located 10 km East of High River City, 70km south from Calgary, 360km from
268 Edmonton.
269
270 Fig8. Site Location
271 (2) Soil Type
272 The soil is mostly Glacial Till, stratified as such:
273 Layer 1 – 0-2.0m Sand or Glacial Till Friction Angle = 26 degrees
274 Layer 2 – 2.0-4.5m Glacial Till Shear Strength = 45 kPa
275 Layer 3 – 4.5-20.0 m Glacial Till Shear Strength = 105 kPa
276
277 (3) Site Layout and Pile Distribution (See details in Appendix D)
278 The site is a rectangular area at 181m x 135m. A total of 336 pile spots are distributed on site.
279
280 (4) Loads (See details in Appendix E)
281 Loads include vertical loads, horizontal loads and moment on each pile spot, which are designed
282 by structural engineers and summarized in Appendix E. The pile configuration designs for three
283 pile systems are dependent on the load table.
284
285 (5) Underground water table
286 Ground Water: 2.0m
287 (6) Weather
288 Summer, temperate with clear skies, no frozen zones.
289 (7) Engineering Design
290 On the basis of soil profile (soil properties, depths of different layers), structural loads, limits on
291 total and differential settlements, underground water table, and time constraints on construction
292 (freeze and thaw effect), the engineering designs for three pile systems are professionally
293 specified in Table 2, Table 3 and Table 4, as follows:
294
295
- 16 -
296 Table 2. Engineering Design for Helical Piles
Pile Type Pile Geometry Qty Notes
- 17 -
302 5. PILE INSTALLATION OPERATIONS OF THE THREE PILE SYSTEMS
- 18 -
1. Excavator drive insertion 2. The Swamper assists in 3. The excavator screw in the
and connection to the pile verticality measurement pile to the designated depth.
and aligns the pile to
location horizontally.
4. The swamper unbolts the 5 Welder completes pile 6. Excavator drives insertion
pile from the excavator. head cutoff of the extension section.
7. Welder then fully welds 8. The excavator installs 9. The swamper unbolts the
the extension section to the the extension section to the extension section
lead. required design depth or
torque, whichever is
achieved first.
- 19 -
346 5.2 Driven Pile Installation Process
347
348 (1) Material and tooling is positioned near driving rig for safe and efficient connection and
349 hoisting. Ensure positive hook-up (slings with shackles or clamps, double wrapped slings with
350 pipe tabs, etc.)
351 (2) Swamper to identify pile location by identifying pile pin and communicating the location to
352 the driving rig operator to record.
353 (3) Rig up pipe pile using a positive hook-up.
354 (4) Hoist the pile into the leads/hammer.
355 (5) Leadman aligns pile inside the helmet and lowers the helmet around the pile.
356 (6) While lowering one line at a time, both the pile and hammer lines are lowered until the
357 weight of the hammer is resting on the pile and the pile tip is resting on the ground, ensure top of
358 pile doesn't leave confines of the helmet.
359 (7) The leads and pile are checked for plumb and location before the full weight of the hammer is
360 placed on the pile.
361 (8) Pile driving commences, driving the pile to the required depth ensuring that hammer is
362 operating at the required energy.
363 (9) Remove the rigging from the pile once driving has stopped.
364 (10) Complete the rough pile cut off or prepare to splice the pile to facilitate further driving
365
366 If splice:
367
368 (11) Swamper to direct the loader to location and set the splice section within reach of the
369 hoisting crane.
370 (12) Rig up pipe pile using a positive hook-up
371 (13) Hoist the pile section to the vertical position and swing the pipe over the recently installed
372 bottom section.
373 (14) The welder and swamper align the splice with the bottom section and tacks the pile in place.
374 (15) Once tacking is complete the crane rigging can be disconnected from the pile and the
375 welding can be completed.
376 (16) Continue to drive the pile until the refusal criteria (when the energy of the hammer blow no
377 longer causes penetration.) is met or you reach practical refusal.
378
379 If cut off:.
380
381 Cut off happens after (10) or (16):
382 (17) Surveyor to mark pile cut off elevation on piles.
383 (18) 150mm above the final pile cut off elevation.
384 (19) Ensure the cut off section is mechanically supported and lowered to the ground for any
385 sections that cannot be safely lowered to the ground by hand.
386 (20) Surveyor to complete the pile as-built.
387 (21) Clean up the area and move to the next location.
388
- 20 -
1. Rig up pipe pile using a 2. Hoist the pile into the 3. Leadman aligns pile in
positive hook-up. leads/hammer. position and swamper checks for
plumb and location before the
full weight of the hammer is
placed on the pile.
4. Drive the pile to the required 5. Rig up splice section using 6. Hoist the splicel section to the
depth then remove the rigging. a positive hook-up vertical position and swing the
pipe over the recently installed
bottom section.
7. The welder and swamper 8. Once tacking is complete 9. Continue to drive the pile
align the splice with the the crane rigging can be until the refusal criteria is met or
bottom section and tacks the disconnected from the pile reach practical refusal.
pile in place. and the welding can be
completed
10. Surveyor to mark pile cut 11. Clean up the area and
off elevation on piles and move to the next location
welder completes the pile cut
off
- 21 -
389 Fig10: Driven Pile Installation Procedure
- 22 -
5. Extract the casing with the rotary drive
6. Finishing
during concreting (with the oscillator)
- 23 -
409 6. DATA COLLECTION
410 Questionnaire was customized to collect data from contractors who are specialists in construction
411 and design of the three pile systems, respectively. The questionnaire was used to collect the
412 piling process cycle time, productivity, cost rate, resource requirement and qualitative data for
413 certain project settings. Reviewers were asked to provide information based on the given project
414 setting based on their experiences of encountering similar scenarios in the past. Accordingly,
415 each questionnaire represents a full set of information. In addition to the questionnaire, direct
416 data collection--site interviews and site visits to fill data forms was also used to collect
417 supplementary data. Including questionnaire collected on site, a total of 30 questionnaires were
418 issued (10 for each pile system). The number of replies was 12 out of 30 questionnaires with a
419 reply percent of 40%. Among the 12 replies, 8 replies were collected for helical piles, 2 were
420 collected for driven pile, and 2 were collected for CIP pile. Though limited feedback were
421 collected for driven pile and CIP pile, the field engineers who helped fill in the questionnaire are
422 of over 15 years field installation experience and the data were more reliable than a larger sample
423 size buy representing replies from novices or less experienced engineers.
- 24 -
450
454 According to standard pile installation crew make-up and the defined project settings and
455 descriptions (e.g. location, project size, season and etc.), cost rate tables containing labor,
456 equipment and material were made and integrated into questionnaire (for helical pile, provided
457 directly by Almita), shown in Appendix B and Appendix C. Note all the cost rates are charge-out
458 rate. Respondents are free to add and delete items listed in the table by their experience and
459 expertise. For confidentiality concerns, charge-out rate collected might be normalized prior to
460 publication of this report.
461 2. RSMeans
462 RSMeans is North America’s leading supplier of construction cost information services.
463 RSMeans offers reliable cost data that is locally relevant, accurate and up-to-date. For costs
464 missing because of sensitive issue or other reasons, the U of A research team searched and
465 obtained reliable data from this open commercial cost information service (average contractor,
466 average job conditions).
467 3. Interview
- 25 -
468 For miscellaneous cost data that are neither included in the questionnaire nor available in
469 RSMeans, telephone interview of Alberta industry partners of the research team was conducted.
478
- 26 -
479 7. SIMULATION MODEL CONSTRUCTION
506 The PI values are calculated as 0.880, 0.873, 0.856 for helical piles, driven piles and CIP piles
507 respectively as shown below.
508 7.2.1 PI Value for Helical Pile
509 For helical piles, the mean value of daily output from simulation model denotes the most likely
510 case scenario that would happen in real world installation. Similarly, the maximum value of daily
511 output from simulation model denotes the expected (or ideal) case scenario. Therefore, by
512 calculating the quotient of mean value over maximum value of daily output (i.e. mean over ideal),
513 the PI value could be calculated.
- 27 -
514 The average value and maximum value of daily output from simulation model is 15.832
515 piles/day and 18 piles/day as shown in Figure 13. Then, by adopting Eq.(1), the PI value from
516 simulation model is calculated as 15.832/ 18 = 0.880.
517
518 Fig13. Productivity Result from Simulation (Helical Pile)
519 7.2.2 PI Value for Driven Pile
520 For driven piles, the PI value could be calculated as above helical pile PI calculation process.
521 The average value and maximum value of daily output from simulation model is 13.092
522 piles/day and 15 piles/day as shown in Figure 14. Then, the PI value from simulation model is
523 calculated as 13.092 / 15 = 0.873.
524
525 Fig14. Productivity Result from Simulation (Driven Pile)
526 7.2.3 PI Value for CIP Pile
527 For CIP piles, the PI value could be calculated as above helical pile PI calculation process. The
528 average value and maximum value of daily output from simulation model is 6.849 piles/day and
- 28 -
529 8 piles/day as shown in Figure 15. Then, the PI value from simulation model is calculated as
530 6.849 / 8 = 0.856.
531
532 Fig15. Productivity Result from Simulation (CIP Pile)
- 29 -
555 7.3.2. Simulation Model for Driven Pile Installation
556 Similar to helical pile, the simulation was broken into three main components, rig-up, installation
557 of design pile pieces, and installation of slice.
558
559 The rig up component symbolized that only after rig up is completed could the installation
560 process start. The secondary component is main component modeled to install the main section
561 defined in the operation process chapter together with onsite contingencies added with the
562 consent of field engineers. The third component in this experiment was the installation of slice to
563 locations where slices were required by engineers. In order to determine the average daily output
564 of driven pile installation in defined project scenario, the simulation simulates installation
565 process for 1000 times. The Symphony model is depicted in Figure 12.
566
567 Note: (1) the loader starts to deliver piles to while equipment starts rigging up. The pile delivery
568 proceeds concurrently with pile installation. (2) Once driven to designated depth and
569 disconnected, the crane will move on to next spot for installation while welders finish pile cut-off
570 procedure and surveyor finishes survey. (3) if capacity check or pre-drill is required, it will
571 happen concurrently with installation process.
572 7.3.3 Simulation Model for CIP Pile Installation
573 Due to the character of CIP pile installation, the simulation was broken into two main
574 components, rig-up and pile installation.
575
576 The rig up component symbolized that only after rig up is completed could the installation
577 process starts. The “pile installation” component is main component modeled to install CIP pile
578 defined in the operation process chapter together with onsite contingencies added with the
579 consent of field engineers.
580 Note, the installation process of CIP pile is relatively “linear” without much concurrent work.
581 The drill machine will not be available for next pile until the casing is withdrawn by casing
582 oscillator. Thus, the installation time for CIP pile is much longer than helical pile and driven pile.
583
- 30 -
584 8. COST ESTIMATION
585 8.1 Cost Estimation for Helical Pile
586 8.1.1 Material Cost for Helical Pile
587 The Unit prices of each kind of pile configuration are provided by Almita. By simply multiplying
588 the unit price and designed quantity takeoff of respective pile type and then sum them up, the
589 total material cost can be obtained.
590
591 Table 6: Pile Material Cost
Pile Type Pile Geometry Quantity Unit Price Total
8 5/8”(.322) x 20’
P1 72 $ 570 $ 41,040
[3/4” x 20”] QTY. 72
10 3/4”(.365) x 25’
P2 182 $ 990 $ 180,180
[3/4” x 24”] QTY. 182
12 3/4”(0.375) x 25’
P3 30 $ 1,260 $ 37,800
[1” x 30”] QTY. 30
16”(.375) x 20’ [1” x
P4 20 $ 1,300 $ 26,000
30”] QTY. 20
20”(.375) x 30’ [1” x
P5 8 $ 2,123 $ 16,984
30” x 30”] QTY. 8
12 3/4”(.375) x 30’ [1”
P6 96 $ 1,730 $ 166,080
x 30” x 30”] QTY. 96
408 $468,084
592 8.1.2 Labor and Equipment Charge-out Rate for Helical Pile
593 The charge-out rate of labor and equipment is important for the duration-dependent cost
594 estimation, and they are all provided by Almita.
595
596 Table 7: Personnel Charge-out Rate
Category Qty Rate (hourly) Notes
Construction Manager
1 $147
(w/ truck)
Supervisor (w/ truck) 1 $147
Install Equip.
1 $93
Operator
Loader Operator 1 $77
Swamper 2 $62
Welder 2 $100
Survey Crew 1 $316 Third Party on a 5/2 shift
Pre drill 1 $777 When pre-drill needed
Field QA/QC 1 $62
597
- 31 -
598 NOTE:
599 (1) Above Charge-out rates are Hourly rates based on 10/5 Shift
600 (2) Orientation = $65.00/man/hour, Assume every onsite crew must undergo 3 hours
601 orientation.
602 (3) Survey Crew is assumed to conduct the survey (Torque, elevation, location deviation and
603 etc.) at beginning and finishing of piling installation process, so their working hours are
604 averaged to 2 hours per day for cost estimation purposes.
605 (4) No third party welders involved.
- 32 -
617 (4) Trip numbers are estimated as 72/96+182/55+30/43+20/42+8/23+96/33= 8.48 round to 9
618 trips
619
620 Thus total transportation fee is estimated as 9 x $205/h x 10 h = $ 18,450
621 8.1.4 Project Total Duration and Separate Activity Durations for Helical Pile Installation
622 The duration of the total project duration from the simulation model is estimated as 259 hours
623 given the PI of 0.88 (13670 min/0.880 = 15534 min = 258.9 hours). Consider full working days
624 and it would be 260 hours. Convert to work days based on 10/5 shift is 26 days. Since different
625 sizes of installation machine are used for different pile type (i.e. 70K 25 Ft Reach for P1-P4;
626 156K 33 Ft Reach for P5 and P6), the installation duration for different types of Reach is
627 characterized separately as shown in Figure 18. The installation duration for 70K 25 Ft Reach is
628 estimated as 180 hours (9563 min/0.880 = 10,667 min = 180.11 hours). The installation duration
629 for 156K 33 Ft Reach is estimated as 80 hours (4215 min/0.880 = 4789.77 min = 79.82 hours).
630
631 (1) Total Project Duration: Most likely 26 d, Ideal Scenario 25 d, Worst Scenario 29 d.
632
633
634 (2) Installation Duration for 70K 25 Ft Reach (3) Installation Duration for 156K 33 Ft Reach
635 Most likely 18 d, Ideal Scenario 17 d, Worst Most likely 8 d, Ideal Scenario 7 d, Worst
636 Scenario 20 d. Scenario 9 d.
637 Fig16. Helical Pile Installation Durations
- 33 -
638 8.1.5 Detailed Cost Estimation of Duration Related Cost for Helical Pile
639
- 34 -
648 8.1.6 Total Cost for Helical Pile
649 The total cost for Installation of helical piles can be simply calculated by summing up each
650 cost components as below:
662 Note:
663 (1) Use $0.5 per pound for pipe pricing (provided by Keller Foundation).
- 35 -
664 (2) Metal calculator, which is a simple on-line calculator for various configurations of metal, is
665 used for pile weight calculation, shown in Figure 17.
666
668 8.2.2 Labor and Equipment Charge-out Rate for Driven Pile
669 The charge-out rate of labor and equipment is important for the duration related cost estimation,
670 and they are all collected from experienced field engineers largely by Questionnaire together
671 with site interview, telephone interview and online benchmarking open source.
- 36 -
674 NOTE:
675 (1) Above Charge-out rates are Hourly rates based on 10/5 Shift
676 (2) Orientation = $65.00/man/hour, Assume every onsite crew must undergo 3 hours
677 orientation.
678 (3) Survey Crew is assumed to conduct the survey at beginning and finishing of piling
679 installation process, so their working hours are averaged to 2 hours per day for cost
680 estimation purposes.
681 (4) No third party welders involved.
- 37 -
20 0.375 10.5 8 22
20 0.5 8.5 16 21
12.75 0.5 16.5 72 17
689
690 Note:
691 (1) Driven piles are mostly manufactured in China or SEA, and shipped via sea cans to
692 Vancouver BC.
694 (3) Use 53 ft Step Deck Tri-axle Trailer (Load Capacity is 60,000 lb, 53’ in length, 8 1/2’ in
695 width)
696 (4) The total duration for transportation trip is 14 hours x 2 (round trip)+ 1 hour loading + 1 hour
697 unloading + 2 hour rest time + 2 hour contingency = 34 hours
- 38 -
705
706 Fig18. Driven Pile Installation Duration: Most likely 33 d, Ideal Scenario 28 d, Worst Scenario
707 41 d.
708 8.2.5 Detailed Cost Estimation of Duration Related Cost for Driven Pile
709 Personnel Costs:
- 39 -
Hydraulic Hammer: 290 hr @ $45.75/hr = $13,268
Helmet: 290 hr @ $27/hr = $7,830
Loader (Volvo L120): 290 hr @ $123.75/hr = $35,888
Crew Truck: 290 hr @ $23.15/hr x 2 = $12,644
Manlift: 290 hr @$45/hr = $13,050
Total cost = $207,785
711
- 40 -
Other Overhead Cost = $54,098
Total: = $1,089,585
- 41 -
745 (2) Rebar cage be tied up by 10M rebar rings (15M for “1000 mm w/ 20 30M bars”) at the
746 space of 1’. The price for 10M rebar is $0.45/ft and 15M @ $0.695/ft.
747 (3) The cost of concrete is $250/m3 for the summer time including transportation.
748 (4) The iron labors rate is $79.55/hr (RSmeans 2014 Calgary) and 3 ironman are employed
749 to manufacture the rebar cage at onsite shop.
750 Thus, Total cost for “400 mm with 5 20M Bars; 6m” is:
752 Total cost for “500 mm with 8 20M Bars; 6m” is:
754 Total cost for “500 mm with 8 20M Bars; 8m” is:
- 42 -
Total cost = $694.65
757 Total cost for “600 mm w/ 11 20M Bars; 11m” is:
763 8.3.3 Labor and Equipment Charge-out Rate for CIP Pile
764 The charge-out rate of labor and equipment is important for the duration related cost estimation,
765 and they are all collected from experienced field engineers largely by Questionnaire together
766 with site interview, telephone interview and online benchmarking open source.
- 43 -
Rigger 1 65
Swamper 1 62
Foreman 1 105
Manufacture rebar cage
Iron man 3 80
onsite
Concrete Testing&Inspection 1 120 From Almita’s rate
768 NOTE:
769 (1) Above Charge-out rates are Hourly rates based on 10/5 Shift
770 (2) Orientation = $65.00/man/hour, Assume every onsite crew must undergo 3 hours
771 orientation.
772 (3) Survey Crew is assumed to conduct the survey at beginning and finishing of piling
773 installation process, so their working hours are averaged to 2 hours per day for cost
774 estimation purposes.
775 (4) No third party welders involved.
- 44 -
700 mm w/ 14 20M bars; 6m 14 x 16 x 6m x 2.355 kg/m = 3165.12 kg
1000 mm w/ 20 30M bars; 13m 20 x 24 x 13m x 5.495kg/m = 34288.8 kg
Total = 74201 kg
784
788 Note:
791 (3) Use 53 ft Step Deck Tri-axle Trailer (Load Capacity is 60,000 lb, 53’ in length, 8 1/2’ in
792 width)
793 (4) The total duration for transportation trip is 1 hours x 2 (round trip)+ 1 hour loading + 1 hour
794 unloading + 0.5 hour rest time + 0.5 h contingency= 5 hours
795 (5) Linear mass density of 20M rebar is 2.355 kg/m, 30M rebar is 5.495kg/m, 10M rebar is
796 0.6985kg/m, and 15M rebar is 1.570kg/m.
- 45 -
797 8.3.5 Project Total Duration for CIP Pile Installation
798 The duration of the total project duration from the simulation model is estimated as 460 hours,
799 applying PI of 0.856 (23581 min/0.856 = 27547.89 min = 459.13 hours). Converting to days
800 based on 10/5 shift is 46 days.
801
802 Fig19. CIP Pile Installation Duration: Most likely 46 d, Ideal Scenario 44 d, Worst Scenario 52 d.
803 8.3.6 Detailed Cost Estimation of Duration Related Cost for CIP Pile
804 Personnel Costs:
- 46 -
Skid Steer Operator: 460 hr @ $65/hr = $29,900
Swamper: 460 hr @ $62/hr = $28,520
Rigger: 460 hr @ $65/hr = $29,900
Pump Truck Operator: 460 hr @ $82/hr = $37,720
Survey Crew: 46 d x 2 hr/d @ $370/hr = $34,040
Concrete Testing&Inspection 460 hr @ $120/hr = $55,200
Iron man: 552 hr @ $80/hr x 3 = $132,480
Total cost = $508,300
807 Equipment Costs:
818
- 47 -
819 Sum Total:
821
- 48 -
822 9. COST COMPARISON AND RISK ANALYSIS
835 Being the lowest in total cost, helical pile system has the highest material cost for the reason that
836 the piles are made of steel and the quantity required for helical pile in this particular project is the
837 most among the three. However, due to the more efficient installation method, helical pile has
838 the lowest installation time, thus arriving at the lowest costs combining labor and equipment.
839 Unlike driven piles that require shipping from Vancouver BC, helical pile has its own
840 manufacturing shops in Ponoka, thus significantly reducing the shipping cost compared with
841 driven piles. The material cost for driven pile is similar with that of helical pile but different in
842 labor and equipment. On one hand, the project lasts 3 workdays longer than helical piles. On the
843 other hand, the equipment requirement for driven pile is more than helical pile. Having
844 summarized that, driven pile system has the higher cost than helical pile. As for CIP piles,
845 though cheapest in material cost because concrete cost rate is much lower than steel, this pile
846 system has the longest duration in installation which leads to highest in labor and equipment
847 costs. It consumes much more time than helical pile because the installation process for CIP pile
848 is relatively straight that the drill machine (with oscillator attached) can have access to next pile
849 spot only after the casing is withdrawn. In addition, CIP pile cannot be installed on rainy days
850 which also add standby time. Therefore, as is analyzed and outputted, for this power substation
851 project, CIP pile has no advantage over other two pile systems both in cost and time.
852 To offer more insight into cost comparison, the cost per pile and cost per meter are calculated as
853 shown in Table 19, further visualized in Figure 20 and Figure 21. As expected that helical pile
854 has the lowest cost rate in both “cost per pile” and “cost per meter”, then we can conclude that
- 49 -
855 helical pile is the most suitable pile system in regards to both cost and schedule in constructing
856 this large-sized power substation project as per the defined engineering settings.
Helical Pile
2,000.00
Driven Pile
1,000.00
CIP Pile
0.00
Helical Pile Driven Pile CIP Pile
- 50 -
863 9.2 Contingency Analysis
864 How to estimate contingency is part of an overall risk management strategy. It is a financial
865 reserve to cater for perceived risks and uncertainties (Baccarini 2004). In the construction
866 domain, it is not uncommon that project cost overruns (Ali 2003). Therefore, cost contingency
867 should be included in the total budget so that the budget can represent the total financial
868 commitment for the owner. If the contingency is too high it might lose competitiveness in the bid
869 pool; if too low it may put the contractor at adverse situations (e.g. financial loss). Knowing that
870 the estimation of cost contingency and its adequacy is of vital importance to construction
871 projects, the contingency is calculated and shown in this research for reference. Contingency of
872 the estimated project duration is also given alongside (by factoring in simulation-produced
873 average, simulated PI, and estimated standby time).
- 51 -
Bid Price (Helical Pile)
906.6K
1
887.1K
0.9
884.3K
0.8
881.8K
0.7
879.4K
Percentiles
0.6
877.9K
0.5
0.4 876.4K
875.1K
0.3
873.3K
0.2
871.0K
0.1
863.0K
0
863041 867886 872731 877576 882421 887266 892111 896956 901801 906646
Total Costs($)
883
0.6
28.4D
0.5
28.3D
0.4
28.2D
0.3
28.1D
0.2
27.9D
0.1
27.3D
0
27.3 27.7 28.1 28.5 28.9 29.3 29.7 30.1 30.5
- 52 -
894 Table 21: Range Calculation for Driven Pile
0.873 PI Converted to standby Total Total
Percentiles Values(min)
added days days days Cost($)
0 14300 16380.3 27.3 2.7 30.0 1060037
0.10 14760 16907.2 28.2 2.8 31.0 1075443
0.20 14815 16970.2 28.3 2.8 31.1 1077285
0.30 14878 17042.4 28.4 2.8 31.2 1079394
0.40 14929 17100.8 28.5 2.9 31.4 1081102
0.50 14975 17153.5 28.6 2.9 31.4 1082643
0.60 15028 17214.2 28.7 2.9 31.6 1084418
0.70 15081 17274.9 28.8 2.9 31.7 1086193
0.80 15141 17343.6 28.9 2.9 31.8 1088202
0.90 15265 17485.7 29.1 2.9 32.1 1092355
1.00 16100 18442.2 30.7 3.1 33.8 1120319
895
0.6
1.083M
0.5
1.081M
0.4
1.079M
0.3
1.077M
0.2
1.075M
0.1
1.06M
0
1060037 1070037 1080037 1090037 1100037 1110037 1120037
Total Costs($)
896
- 53 -
Installation Time (Driven Pile)
33.8D
1
32.1D
0.9
31.8D
0.8
31.7D
0.7
31.6D
Percentiles
0.6
31.4D
0.5
31.4D
0.4
31.2D
0.3
31.1D
0.2
31.0D
0.1
30.0D
0
30.0 30.5 31.0 31.5 32.0 32.5 33.0 33.5
- 54 -
Bid Price (CIP Pile) 1.424M
1
1.352M
0.9
1.336M
0.8
1.315M
0.7
1.305M
Percentiles
0.6 1.293M
0.5
1.282M
0.4
1.272M
0.3
1.267M
0.2
1.261M
0.1
1.245M
0
1245558 1265558 1285558 1305558 1325558 1345558 1365558 1385558 1405558
Total Cost($)
909
0.6
52.3D
0.5
51.7D
0.4
51.3D
0.3
51.0D
0.2
50.7D
0.1 49.9D
0
49.9 50.9 51.9 52.9 53.9 54.9 55.9 56.9 57.9 58.9
- 55 -
915 10. CROSS VALIDATION
916 Validation is crucial to prove the effectiveness in outputting high quality results from the simulation
917 models. A three-step validation process has been conducted in this research: (1) Productivity cross
918 checking; (2) Performance Index cross checking; and (3) Bid price cross checking. The validation steps
919 are illustrated with detailed process in subsequent sections.
- 56 -
950 10.2 Performance Index (PI) Cross Checking
951 With the help of experienced domain experts, PIs valued at 0.70, 0.75 and 0.80 were estimated to
952 CIP pile, Driven Pile and Helical pile respectively for cross checking purpose. This session is to
953 cross check the PI value derived from domain experts’ knowledge and simulation output.
954 In reality, the PI value equals to the realistic (average) daily output over the ideal (maximum)
955 daily output. The PI for respective pile system calculated in session 7.2 is compared with
956 collected PIs, as shown below:
957 Table 24: Validation for Three Pile Systems by Performance Index
Pile Type Helical Driven CIP
PI (outputted from simulation model) 0.880 0.873 0.856
PI (collected from domain experts) 0.8 0.75 0.70
VF 0.91 0.86 0.82
Quality Good Fair Fair
958
959 Using the validation factor (VF) concept in previous session, the VFs for helical pile and driven
960 pile are 0.91, which is relatively good. For Driven pile and CIP pile, the VF is 0.86 and 0.81,
961 which is fair. The PIs results from simulation model are concisely higher (i.e. helical: 0.88 vs.
962 0.8; driven: 0.873 vs. 0.75; CIP: 0.856 vs. 0.70) than those values estimated by experts,
963 indicating further room for improvement on input data and model sufficiency. The simulated PI
964 values for respective pile systems are more optimistic on productivity performance likely
965 because some factors have not been considered in the model yet while others not being
966 sufficiently represented due to limited data available (e.g. resource transit, interruptions due to
967 equipment, weather, labor, material, and management delays). However, current simulated PI
968 values is close to expected benchmarks and deemed applicable in follow-up cost estimation,
969 schedule comparison analysis.
- 57 -
979 10.3.2 Bid Price Cross Checking for Driven Pile
980 According to two cost estimating experts from local construction contractors, the estimated total
981 bid price is $1,040,000 and $1,020,000, respectively, including mobilization, labor, equipment,
982 materials and markup. Note that the price excludes subcontractors such as survey, weld testing,
983 material inspection, and predrilling. As such, the simulation-produced average total price from
984 this study, which is $1,089,585 is very close to experts’ estimation.
995 The bid price comparison together with the estimates given by experts are summarized in Figure
996 28. Note this figure is also shown in Executive Summary.
997
- 58 -
1000 CONCLUSION
1001 This research has introduced a comprehensive cost and contingency estimating method based on
1002 simulation for cost comparison among three typical pile systems in Alberta, Canada. By fully
1003 engaging Almita engineers, the “project scenarios” and “design scenarios” were designed by
1004 considering three different foundation systems: helical pile, driven pile and CIP pile.
1005 Experience-based exquisitely devised questionnaires in regarding to three pile systems were
1006 distributed to and collected from field engineers in respective pile construction domains. The
1007 collected data from questionnaire feedback were addressed and analyzed in scientific techniques
1008 with theoretical foundations introduced in the report. A SYMPHONY engine driven simulation
1009 system was adopted and three simulation models in regard to the three pile installation processes
1010 were established. Then the addressed questionnaire collected data were coded into respective
1011 model as inputs. By running simulation model in a Monte Carlo fashion, total project duration,
1012 daily output and other important results can be outputted. Finally, by summing up collected cost
1013 rate, required resources, performance index, and outputted duration, the cost and contingency
1014 estimation of each pile system and further the cost comparison of the three pile systems were
1015 done accordingly. It is concluded that helical pile system could save both budget and time in
1016 comparison with the other two in typical power substation project.
1017 To assist in Amita in comparing the economic benefits of the three pile systems in a more
1018 comprehensive and inclusive fashion, further improvements of the research reported will be
1019 worthy to be pursued, as follows:
1020 (1) The data in this research are mostly collected from experience of experts. Though it can own
1021 certain reliability when relatively large database is acquired, it is still has the shortcomings of
1022 expert system such as cognitive bias, estimation accuracy, expert experience and etc. As the cost
1023 estimation cannot be detached from the cost data and duration, it is foreseen that there is a need
1024 to improve the reliability of the mentioned in order to achieve more accurate and convincing
1025 comparison results.
1026 (2) The performance indexes assigned to simulation model accounting for the non-productive
1027 time have some discrepancy from results estimated directly by field engineers. Since the
1028 situation may vary from site to site, it is urgent to develop an analytical method to scientifically
1029 measure this pivotal index to further improve estimation accuracy.
1030 (3) The scope of this cost comparison is established on the basis of defined project scenarios and
1031 designed scenarios. It is projected that a more complete “project scenario database” and
1032 “engineering scenario” database could be integrated to make the comparison more
1033 comprehensive.
1034
- 59 -
1035 12. FOLLOW-UP IN NEAR FUTURE
- 60 -
1071
1072 ACKNOWLEDGEMENTS
1073 This project is substantially funded by a NSERC Engage grant in partnership with Almita Piling
1074 Ltd. (Engage Grant 479602 2015 entitled "Cost Analyses of Pile Foundation Systems based on
1075 Engineering Design and Construction Method")
1076 We express our sincere gratitude to Bill Baillie, Baocheng Li, David Watmough and Mohamed
1077 Abdelaziz from Amita Piling Inc., who provided unreserved help and insightful inputs
1078 throughout this research.
1079 We also sincerely thank Mike Garland, Patrick Long, David Baker, Paul Patenaude, Steve
1080 Burroughs from Amita Piling Inc.; Jason Lim, Justin Bekkers from Keller Foundations; and
1081 Doug Zieber, DeLorey Shane from Jacobs Canada Inc., who are site managers and
1082 superintendents with years of valuable installation experience, for sharing field experiences in
1083 pile installation and providing valuable insight information, and data in this research.
1084 Tim McLaughlin, Estimator, Ledcor Contractors Ltd., is acknowledged for his kind help in
1085 providing professional estimations for cross-checking purposes.
1086 REFERENCE
1087 [1] American Association of State Highway and Transportation Officials (AASHTO 2012),
1088 AASHTO LRFD Bridge Design Specifications, Customary U.S. Units (6th Edition), 2012.
1089
1090 [2] AbouRizk, S.M., Halpin, D. W., and Wilson J. R. 1991. “Visual interactive fitting of beta
1091 distributions.” Journal of Construction Engineering and Management, ASCE, 117(4): 589-
1092 605.
1093
1094 [3] Fente J, Schexnayder C, Knutson K. 2000. “Defining a probability distribution function for
1095 construction simulation [J]”. Journal of construction engineering and management, 126(3):
1096 234-241.
1097
1098 [4] Peck R.B., Hanson W.E., Thornburn T.H., Foundation Engineering, Text book, 2nd Edition,
1099 John Wiley & Sons, Inc. ISBN: 978-0-471-67585-3, 1974.
1100
1101 [5] Samtani N. C.Nowatzki E. A., Soils and Foundations Reference Manual – Volume II,
1102 Publication No. FHWA NHI-06-089, U.S. Department of Transportation, Federal Highway
1103 Administration December, 2006.
1104
1105 [6] Tomlinson M, Woodward J., Pile Design and Construction Practice, Text book, 5th Edition,
1106 Taylor & Francis, 2 Park Square, Milton Park, Abingdon, Oxon OX14 4RN, USA, 2008.
- 61 -
1107
1108 [7] Zayed, Tarek M., and Daniel W. Halpin. 2004. "Simulation as a tool for pile productivity
1109 assessment." Journal of construction engineering and management 130.3: 394-404.
1110
1111 [8] Zayed, Tarek M., and Daniel W. Halpin. 2001. "Construction I: Simulation of Bored Pile
1112 Construction." In Proceedings of the 33nd conference on Winter simulation, pp. 1495-1503.
1113 IEEE Computer Society.
1114
1115 [9] Baccarini, David. 2004. Estimating project cost contingency - a model and exploration of
1116 research questions, in Khosrowshahi, Farzad (ed), ARCOM 20th Annual Conference,
1117 September 2004, pp. 105-113. Heriot-Watt University, Edinburgh: Association of
1118 Researchers in Construction Management.
1119
1120 [10] Ali, Touran, “Probabilistic cost estimating with subjective correlations,” J. Constr. Eng.
1121 Manag., vol. 119, no. 1, pp. 58–71, 2003
1122
1123 [11] ONLINEMETALS.COM, Version 2014, 1848 Westlake Ave N, Suite A, Seattle, WA
1124 98109. http://www.onlinemetals.com/calculator.cfm
1125
- 62 -
1126 Appendix A: Questionnaire for Helical Pile
1127 Dear Almita engineers,
1128 Thank you very much for your time on this questionnaire!
1129 Helical piles are widely used in Alberta as an alternative for traditional deep foundation engineering
1130 systems such as concrete cast-in-place (CIP) piles and driven steel piles. However, the installation of a
1131 helical pile is complicated from various aspects, by which exert great challenge for the project estimators
1132 to evaluate cost, duration and productivity. With a lack of research in this field, this study attempts to
1133 propose a scientific model from perspective of operations and logistics in construction with the
1134 application of simulation method to calculate operation productivity and duration. To proceed this
1135 research, firstly, U of A research team defined particular project scenario and engineering scenarios. Then
1136 a breakdown process has been conducted to factor the installation process. A total of 10 activities related
1137 to the particularly-designed helical pile foundation project were defined through breakdown procedure.
1138 We expect your kind offer us the duration data of each activity defined based on your experience and
1139 expertise. I promise a strict confidentiality for your information and the feedback information, and I
1140 ensure that this questionnaire will not be used for any other purposes except academic research.
1141 Thanks again for your kind support and cooperation. If you have any questions about the
1142 questionnaire content, you can feel free to contact. At the same time, I also look forward to more
1143 communication and interaction with you about the helical pile construction know-how.
1144
1145
1146
1147
1148
1149
1150
1151
1152
1153 Questionnaire maker: Chaojue Yi (Eason)
- 63 -
1165 A. Project Information
1166
1167 The following are the designed project settings for your information.
1168 Project Location: 10 km East of High River Project Type: Power Substation
Helix Helix
Pile Type Shaft Diameter Pile length Helix Spacing
Number Diameter
P1 8 5/8” 20’ 1 N/A 20’’
P2 10 3/4” 25’ 1 N/A 24’’
P3 12 3/4” 25’ 1 N/A 30’’
P4 16” 20’ 1 N/A 30’’
P5 20” 30’ 2 2.4’ 30’’
P6 12 3/4” 30’ 2 2.4’ 30’’
1172
1173
1174
1175
1176
1177
- 64 -
1178 B. Basic Information
1179 1、Your company’s classification:
1187 The following are the 10 defined activities. Please try to estimate the minimum, most probable, and
1188 maximum time that each activity can be accomplished according to factors as such: site layout,
1189 underground unknown condition, mechanical problem, rework, design changes, weather, experience
1190 (human factor), onsite management and etc.
Times(minutes)
Activity
Most
Minimum Maximum
Probable
1.Equipment Rig up
2.Screw pile pickup/delivery
Distance of 0-100m
Distance of 100-200m
Distance of 200-300m
3. Bolt
4. Level up and locate pile in position
P1: 8 5/8” x 20’ [3/4” x 20”]
P2: 10 3/4”x 25’ [3/4” x 24”]
5. Screw in P3: 12 3/4” x 25’ [1” x 30”]
Lead P4: 16” x 20’ [1” x 30”]
Section P5: 20”x 30’ [1” x 30” x 30”]
P6: 12 3/4” x 30’ [1” x 30” x
30”]
6. Unbolt
7. Record man recorded torque readings
8. Screw in extension section (10’)
9. Welder completes the pile cut off
Cap Plate (4pinholes)
10. Cap
Cap Plate (8pinholes)
installation
Cap Plate (12pinholes)
What is the daily output? (piles/day)
1191
- 65 -
1192 Appendix B: Questionnaire for Driven Pile
1193 Dear engineers,
1194
1195 Thank you very much for your time on this questionnaire!
1196
1197 Driven piles are widely used in Alberta as a traditional deep foundation engineering system. However, the
1198 installation of a driven pile is complicated from various aspects, by which exert great challenge for the
1199 project estimators to evaluate cost, duration and productivity. With a lack of research in this field, this
1200 study attempts to propose a scientific model from perspective of operations and logistics in construction
1201 with the application of simulation method to calculate operation productivity and duration. To proceed
1202 this research, firstly, U of A research team defined particular project scenario and engineering scenarios.
1203 Then a breakdown process has been conducted to factor the installation process. A total of 8 activities
1204 related to the particularly-designed driven pile foundation project were defined through breakdown
1205 procedure.
1206
1207
1208 We expect your kind offer us the duration data of each activity defined based on your experience and
1209 expertise. I promise a strict confidentiality for your information and the feedback information, and I
1210 ensure that this questionnaire will not be used for any other purposes except academic research.
1211
1212
1213 Thanks again for your kind support and cooperation. If you have any questions about the
1214 questionnaire content, you can feel free to contact. At the same time, I also look forward to more
1215 communication and interaction with you about the driven pile construction know-how.
1216
1217
1218
1219
1220
1221
1222
1223
1224
1225 Questionnaire maker: Chaojue Yi (Eason)
1226 Contact Info: chaojue@ualberta.ca
1227
1228
1229
1230
1231
1232
1233
1234
1235
1236
1237
1238
1239
- 66 -
1240 A. Project Information
1241 The following are the designed project settings for your information.
1242
1243 Project Location: 10 km East of High River Project Type: Power Substation
1244
1245 Piling Machine Type: EX Piling Machine Power: 40k – 150k
1246
1247 Soil Type: Glacial Till (Cohesive) Season: Summer
1248
1249 Frost Depth: 2.0m Ground Water: 2.0m
1250
Shaft Diameter Pile length
Pile Type
(inch) (m)
P1 10.695 8.5
P2 12.75 8.5
P3 12.75 12.5
P4 16 8.5
P5 20 10.5
P6 20 8.5
P7 12.75 16.5
1251
1252 Note: The pile length is the order length, the embedment depth is Pile length – 1.5m
1253
1254
1255
- 67 -
1256 B. Basic Information
1257 1、Your company’s classification:
- 68 -
and welder completes the pile cut off
What is the daily output? (piles/day)
1270 D. Resource Requirement Table.
1271 Please help identify the common quantity of each resource needed in this project (384 piles to be
1272 constructed, middle-sized power substation), feel free to add missing resources.
1273
Resource Quantity Hourly Rate
(approximate)
Supervisor (w/ truck)
Install Equip. Operator
Loader Operator
Rigger
Welder
Lead Hand
Survey Crew
Field QA/QC
100 Ton Crane (Driven)
Loader
Crew Truck
Manlift
……
1274
1275
- 69 -
1276 Appendix C: Questionnaire for CIP Pile
1277 Dear engineers:
1278 Thank you very much for your time on this questionnaire!
1279 CIP piles are widely used in Alberta as a traditional deep foundation engineering system. However, the
1280 installation of a CIP pile is complicated from various aspects, by which exert great challenge for the
1281 project estimators to evaluate cost, duration and productivity. With a lack of research in this field, this
1282 study attempts to propose a scientific model from perspective of operations and logistics in construction
1283 with the application of simulation method to calculate operation productivity and duration. To proceed
1284 this research, firstly, U of A research team defined particular project scenario and engineering scenarios.
1285 Then a breakdown process has been conducted to factor the installation process. A total of 8 activities
1286 related to the particularly-designed CIP pile foundation project were defined through breakdown
1287 procedure.
1288 We expect your kind offer us the duration data of each activity defined based on your experience and
1289 expertise. I promise a strict confidentiality for your information and the feedback information, and I
1290 ensure that this questionnaire will not be used for any other purposes except academic research.
1291 Thanks again for your kind support and cooperation. If you have any questions about the
1292 questionnaire content, you can feel free to contact. At the same time, I also look forward to more
1293 communication and interaction with you about the CIP pile construction know-how.
1294
1295
1296
1297
1298
1299
1300
1301
1302
1303 Questionnaire maker: Chaojue Yi (Eason)
- 70 -
1317 A. Project Information
1318 The following are the designed project settings for your information
1319 Project Location: 10 km East of High River Project Type: Power Substation
1326
1327
1328
- 71 -
1329 B. Basic Information
1330 1、Your company’s classification:
- 72 -
What is the daily output? (piles/day)
- 73 -
Appendix D: Site Layout and Pile Distribution
74
Appendix E: Design Loads
75
Appendix F: Screw Pile Installation Approval Procedure
INSTALL START
NO NO
NO ENGINEER TO ENGINEER TO
PROPOSE NEW PILE PROPOSE NEW PILE
TYPE THROUGH RFI TYPE THROUGH RFI
YES MIN YES YES
VERTICAL
EVALUATE EMBEDMENT
CAPACITY
PRE-DRILL REACHED AFTER
CHECK
PRE-DRILL
RFI
RFI
DISPOSITION
NO DISPOSITION
NO
NO
EVALUATE RFI
RFI
REMOVING DISPOSITION
DISPOSITION
TOP HELIX
ALMITA
ALMITA
ENGINEER TO PROPOSE ENGINEERING
ENGINEERING
REMEDIAL/APPROPRIATE APPROVAL
APPROVAL
SOLUTION THROUGH RFI
REMOVE TOP HELIX. RE-INSTALL PILE
AS PER NEW INSTALLATION CRITERIA TO
BE SPECIFIED BY ENGINEER. RE-START END
END
PILE APPROVAL PROCEDURE
RFI
DISPOSITION
WORK TO BE
DONE AS PER
RFI DISPOSITION
ALMITA
ENGINEERING
APPROVAL
END
76
Appendix G: Simulation Model for Three Pile Systems
77
Fig G.2. Symphony model for Driven Pile Installation Process
78
Fig G.3. Symphony model for CIP Pile Installation Process
79