Quick Access To run this report, use one of the following access options:
Option 1: Menu Path
Logistics Project management Information system Costs/rev/payments Report
selection, then Costs:Planned/Actual/Variance
From the reporting tree, choose the following report:
Costs:Planned/Actual/Variance
Option 2: Transaction Code
In the Command field, enter transaction PS91 and choose Enter. Then, select the
report listed as Costs: Planned/Actual/Variance.
Purpose This report lists the planned and actual costs by project structure object. It also
compares the variance and displays the variance amount in both absolute and
percentage terms.
Prerequisites You must enter a value for the Controlling Area the first time you run this report.
You will need to change the Controlling area again only if it changes for subsequent
reports. After you enter Controlling area, you see the Database profile. The Database
profile determines what information from the Project System will be viewed.
Integration In this report, you can use value categories to find all costs (planned or actual)
based on the type of cost. Value categories are defined during configuration and
consist of cost elements or cost element groups. Using value categories, you can
list costs for a given project object, such as a Work Breakdown Structure element
(WBS) and by the cost element groups instead of each cost element. Examples of
cost element groups include:
Labor costs
Material costs
Overhead costs
Other costs
You can also list the cost by transaction currency instead of by project currency,
delimit cost by year or period, and drill down to the transaction that created the
cost.
Version reporting
Subproject reporting
Reporting of planned costs using a version other than the default version
Next Steps This report includes data from cost planning and actual cost postings to WBS
elements and network activities.
Guided Tour
Quick Access To run this report, use one of the following access options:
Option 1: Menu Path
Logistics Project management Information system Costs/rev/payments Report
selection
Costs Plan-based By cost elements Act/plan/variance abs.% var
From the reporting tree, choose the following report:
Plan-based By cost elements Act/plan/variance abs.% var.
Option 2: Transaction Code
In the Command field, enter transaction PS91 and choose Enter. Then, from the
reporting tree, choose Plan-based By cost elements Act/plan/variance abs.% var.
Purpose This report lists the planned and actual costs (by project cost object) for each cost
element. It also compares the variance and displays the variance amount in both
absolute and percentage terms.
Prerequisites You must enter a value for the Controlling Area the first time you run this report.
You will need to change the Controlling area again only if it changes for subsequent
reports. After you enter Controlling area, you see the Database profile. The Database
profile determines what information from the Project System will be viewed.
Integration This report only lists the cost for the object not the structure, as described in the
previous report.
In this report, you can drill down to the line-item detail of a given cost element and
find all costs for the project object entered in the selection screen. If the project is
used in the selection screen, all costs listed are for the entire project by cost
element.
Next Steps This report includes data from cost planning and actual cost postings to WBS
elements and network activities.
Guided Tour
Quick Access To run this report, use one of the following access options:
Option 1: Menu Path
Logistics Project management Information system Costs/rev/payments Report
selection
Option 2: Program Name
Choose System Services Reporting and enter RKP8928 in the Program field.
Then, choose Execute to run the report.
Note: The report shown here is a custom report which was created with reference
to other functions in the Project Systems module. It is included here for illustration
purposes only.
Purpose This report lists project costs and compares them to the budget. It includes
commitments and remaining order plan costs.
Prerequisites You must enter a value in the Controlling Area the first time you run this report.
You will need to change the Controlling area again only if it changes for subsequent
reports. After you enter Controlling area, you see the Database profile. The Database
profile determines what information from the Project System will be viewed.
Integration In this report, you can use value categories to find all (planned or actual) costs
based on the type of cost. Value categories are defined during configuration and
consist of cost elements or cost element groups. Using value categories, you can
list costs for a given project object, such as a Work Breakdown Schedule element
(WBS), by the cost element groups instead of each cost element. Examples of cost
element groups might include:
Labor costs
Material costs
Overhead costs
Other costs
You can also list the cost by transaction currency instead of by project currency,
delimit cost by year or period, and drill down to the transaction that created the
cost.
Network
Subproject
Project version
Cost plan version
Next Steps This report includes data from cost planning and actual cost postings to WBS
elements and network activities.
Guided Tour
Example: Display a simple listing of costs, commitments, and budget for a project.