You are on page 1of 1

Sl.

No Pre Commissioning and Installation Response


Step - 1
Raw Water inlet plumbing line to Filter Feed Pump & Backwash pump and Strainer Available, But Cosmos
1
Pipe size to be confirmed assistance required to mark the
2 PSF Backwash and Rinse drain line connection and pipe line size confirmation connecting point. ( Had a Con
Call with Mr. Venkatesh and will
3 PSF bottom strainer availability and fixing to be confirmed be completed by today. )

4 PSF media availability and loading to be confirmed Will be completed by Today.

5 RO membrane availability and storage to be confirmed Available

6 RO Product plumbing line and size to be confirmed Completed

7 RO Reject plumbing line and size to be confirmed Completed

8 RO Panel incoming power cable size to be confirmed 50 Sq. MM 4 Core.

9 RO panel Earthing pit and earthing to be confirmed Completed

10 Clarifier Chemical Treatment Process to be given As per Design


Pre Commissioning chemicals Antiscalent,SMBS,Hydrochloric Acid,Sodium
11 Available
Hypo Chloride & Sodium Carbonate to be arranged
12 Air Conditioner fixing to be confirmed Completed

13 Raw and RO water tank level switch fixing to be confirmed Completed

14 500 KL Fresh water TDS, Hardness and pH to be confirmed Will be confirmed


15 PSF Inlet water quality parameter limit to be confirmed Will be confirmed
Check all Required equipments as per P&IDs and Confirm (All Electro-
16 Will be confirmed
Mechanical & Instrumentation)
17 Load the Membrane / PSF Media Filling Will be confirmed
Step - 2
Check all the leakages from thr RO, HPP Pump, Reject Pump, PSF Vessel Etc., &
18 After Completing Step - 1
Attend the leakage before Commisionning
Check the Power load by switching on the Installed Pumps/Motors & Confirm
19 After Completing Step - 1
with the design
Check all level sensors, Pressure Guages, Flow Meter, Online Instruments etc..
20 After Completing Step - 1
And Confirm as per Design
Flow from Each Pump to be checked Including all doing pumps tool & Match
21 After Completing Step - 1
with the design considered ( This is Must )
Check The leakages from pipes, Joints, Valves and Mainly from Denfoss Devise
22 After Completing Step - 1
and Confirm the Readiness without any leakages ( This is Must )
Check The Electrical Load taken by the Plant after Switching on all the Pumps
23 After Completing Step - 1
for 15 Minutes ( This is must )
Main Check Poiints are from PLC, So get the confirmatiom on all sett logics
24 based on the process requirements ( This is must before actual commissioning After Completing Step - 1
)
25 Check the main logic set for Energy Saver of Denfoss Pump including the VFD After Completing Step - 1

26 Check the Inlet feed Water Parameters mainly, Temperature, TDS & TSS. After Completing Step - 1

You might also like