Professional Documents
Culture Documents
Architectural Works
Architectural Works
MATERIAL COSTING
DIRECT
STRUCTURE qty unit MATERIALS QTY UNIT PRICE COST DIRECT COST
PRICE
1.44 sq.m CHB 6" 18.00 pcs 35.00 31.25 630.00 562.50
1.44 sq.m Cement 0.83 bags 230.00 205.36 191.27 170.78
1.44 sq.m Sand 0.11 cu.m 700.00 625.00 77.62 69.30
1.44 sq.m tie.wire 0.06 kg 40.00 35.71 2.42 2.16
Exterior wall 1.44 sq.m rebar 2.96 kg 35.00 31.25 103.57 92.48
1.44 sq.m Alignmentkey 16.20 pcs 7.00 6.25 113.40 101.25
1.44 sq.m Delivery charge 18.00 pcs 10.50 9.38 189.00 168.75
1.44 sq.m CHB 4" 18.00 pcs 32.00 28.57 576.00 514.29
1.44 sq.m Cement 0.65 bags 230.00 205.36 149.04 133.07
1.44 sq.m Sand 0.09 cu.m 700.00 625.00 60.48 54.00
1.44 sq.m tie.wire 0.06 kg 40.00 35.71 2.42 2.16
Interior wall 1.44 sq.m rebar 2.96 kg 35.00 31.25 103.57 92.48
1.44 sq.m Alignmentkey 16.20 pcs 7.00 6.25 113.40 101.25
1.44 sq.m Delivery charge 18.00 pcs 8.15 7.28 146.70 130.98
- - -
- - -
- - -
DIRECT
DIRECT COST Cost / unit
Cost / unit
562.50 437.50 390.63
170.78 132.83 118.59
69.30 53.90 48.13
2.16 1.68 1.50
92.48 71.93 64.22
101.25 78.75 70.31
168.75 131.25 117.19
907.83 810.56
514.29 400.00 357.14
133.07 103.50 92.41
54.00 42.00 37.50
2.16 1.68 1.50
92.48 71.93 64.22
101.25 78.75 70.31
130.98 101.88 90.96
799.73 714.04
139.73 108.68 97.03
23.63 18.38 16.41
- 127.05 113.44
52.90 41.14 36.73
- 41.14 36.73
257.14 200.00 178.57
58.44 45.45 40.58
- 245.45 219.16
-
-
-
Masonry Material Quantification
Consider 1.2x1.2 Wall
Direct Material
Description QTY Unit Cost/unit Cost
6" Smart Blocks 18 pcs 30.36 546.43
4.4388 kg 24.11 107.01
10mm rebar (6pcs @400 spacing)
Alignment key 18 pcs 7.50 135.00
Cement for filler 0.8316 bags 196.43 163.35
Direct Material
Description QTY Unit Cost/unit Cost
Diamond Render
Cost per bag 680 Php per bag
Coverage Area 3.3 sq.m / bag
Total Cost 206.06 Php / sq.m
Plaster Works
Cost per bag Cement 230 Php per bag
Cost per Cu.m. of Sand 700 Php per Cu.m
Skimcoat
Cost per bag 360 Php per bag
Qty per sq.m (2 Coats) 0.12 bag
FRONT ELEV:
GROUND FLOOR: 25.00 x 3.00 = 75.00 - 21.30 x 1 Floor 53.70 sq.m
Fire Wall
6.80 x = 52.57 - - x 2 Item 105.14 sq.m
4.20 x = 45.08 - - x 1 Item 45.08 sq.m
6.80 x = 49.28 - - x 1 Item 49.28 sq.m
x = - - - x 1 Floor - sq.m
FRONT ELEV:
25.00 x 3.50 = 87.50 - 7.20 x 1 Floors 80.30 sq.m
Rear ELEV:
25.00 x 2.48 = 62.00 - 8.70 x 1 Floors 53.30 sq.m
1.80 x 3.00 = 5.40 - - x 1 Floors 5.40 sq.m
Dry Wall
Dry Wall 4.25 x 2.50 = 10.63 - 3.36 x 5 Unit 36.33 sq.m
4.05 x 2.50 = 10.13 - x 5 Unit 50.63 sq.m
End Unit metal furring
Ground Floor Vert. Horiz.
length pcs length pcs
External 2.00 x 2.78 = 5.55 2.00 5 2.78 3
Living 2.70 x 2.78 = 7.51 2.70 5 2.78 5
Dining 5.45 x 2.08 = 11.34 5.45 3 2.08 9
2nd Floor
External 0.75 x 4.69 = 3.52 0.75 7 4.69 1
0.60 x 5.75 = 3.45 0.60 9 5.75 1
0.60 x 2.17 = 1.30 0.60 3 2.17 1
0.60 x 2.23 = 1.34 0.60 3 2.23 1
Balcony x = - - 1 - 1
Master Bedroom 2.78 x 3.90 = 10.84 2.78 7 3.90 5
Bedroom 2 2.17 x 2.78 = 6.03 2.17 5 2.78 3
T&B 1.15 x 2.13 = 2.45 1.15 3 2.13 1
stairs 0.90 x 4.15 = 3.74 0.90 7 4.15 1
1.23 x 1.53 = 1.88 1.23 3 1.53 3
x = - - 1 - 1
stairs x = - - 1 - 1
x = - - 1 - 1
58.94
x 2 x
117.88
al furring Inner Unit metal fur
Ground Floor Vert.
total Length
length
External 2.00 x 2.70 = 5.40 2.00
Living 2.70 x 2.78 = 7.49 2.70
Dining 5.45 x 2.08 = 11.34 5.45
2nd Floor
9.94 External 4.05 x 0.75 = 3.04 4.05
11.15 x = - -
3.97 x = - -
4.03 x = - -
0.00 Balcony x = - -
38.96 Master Bedroom 3.85 x 2.68 = 10.32 3.85
19.19 Bedroom 2 2.63 x 2.18 = 5.73 2.63
5.58 T&B 2.13 x 1.15 = 2.45 2.13
10.45 stairs 1.00 x 4.10 = 4.10 1.00
8.28 x = - -
0.00 x = - -
0.00 stairs x = - -
0.00 x = - -
111.55 49.87
2 x 3
223.10 149.60
71.4
15,929.34
metal furring
Vert. Horiz.
total Length
pcs length pcs
5 2.70 3
5 2.78 5
3 2.08 9
1 0.75 7 9.30
1 - 1 0.00
1 - 1 0.00
1 - 1 0.00
1 - 1 0.00
5 2.68 7 38.01
3 2.18 5 18.79
1 1.15 3 5.58
7 4.10 1 11.10
1 - 1 0.00
1 - 1 0.00
1 - 1 0.00
1 - 1 0.00
82.78
x 3
248.34
71.4
17,731.48
CONCRETING WORKS
Height / Length / No. of Area Volume Surface
Description Base
Depth Height Item (sq.m) (cu.m) Area
Excavation
Footing 0 0
TB 0 0
WF-1 0.5 0.6 98.8 0.3 29.64
29.64
Fill & Complaction
Footing
WF-1 7.90
7.90
Gravel Bedding
WF-1 0.5 0.1 98.8 4.94
SOG 0.1 103.69 10.369
15.31
Concreting
Footing
F1 0 0
WF-1 0.5 0.2 98.8 0.1 9.88
9.88
Column
C1 0 0
0 0
-
Beam
B1 0 0
0 0
-
Ground floor
Close Area 0.15 103.69 15.5535
ServiceArea 0.1 11.5 1.15
Lanai 0.15 12 1.8
Carport 0.15 67.5 10.125
Porch 0.15 15.32 2.298
2nd Floor
Close Area 0.1 108.86 10.886
Ledge 0.1 17.75 1.775
12.66
NoActual
of barsLength/Weight
per Commercial Length / Weight
Length item Commercial
Description Dia. No. of PCS/ Usable Total
item Total Total No of 1Bar Waste Weight
Length
Top Bot Top Bot Length Weight bars
Footing
F-1 0 0.00 0 0.00
TB-1 0 0.00 0.00
Stirrups 0 0.00 0.00
0 0.00 0.00
WF-1 (horizontal) 10 98.8 3 1 296.4 182.73 0 0 0.00
WF-1 (Vertical) 10 1 165 1 165 101.72 0 0 0.00
284.45 0.00
Masonry Extra bars
Rebar @ Openings 12 38.25 1 1 38.25 33.96 10.5 4 0 10.5 37.29
Rebar Bet. 1st and 2nd flr. 10 1.8 247 1 444.6 274.10 9 50 5 0 277.43
Hook @ corners 10 1.2 21 34 856.8 528.22 6 143 5 0 528.96
836.27 843.67
Column
C-1 0 0.00 0.00
0 0.00 0.00
Ties 0 0.00 0.00
0.00 0.00
Beam
B-1 0 0.00 0.00
Stirrups 0 0.00 0.00
B-2 0 0.00 0.00
Stirrups 0 0.00 0.00
B-3 0 0.00 0.00
Stirrups 0 0.00 0.00
B-4 0 0.00 0.00
Stirrups 0 0.00 0.00
B-5 0 0.00 0.00
NoActual
of barsLength/Weight
per Commercial Length / Weight
Length item Commercial
Description Dia. No. of PCS/ Usable Total
item Total Total No of 1Bar Waste Weight
Length
Top Bot Top Bot Length Weight bars
Stirrups 0 0.00 0.00
B-6 0 0.00 0.00
Stirrups 0 0.00 0.00
B-7 0 0.00 0.00
Stirrups 0 0.00 0.00
B-8 0 0.00 0.00
Stirrups 0 0.00 0.00
0.00 0.00
Suspended Slab
Continous // to Long Span 0 0.00 0.00
0 0.00 0.00
Continous // to Short Span 0 0.00 0.00
0 0.00 0.00
Extra // to Long Span 0 0.00 0.00
0 0.00 0.00
Extra // to Short Span 0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
16mm dia. Support 0 0.00 0.00
0 0.00 0.00
0 0.00 0.00
Extra at Cantiliver 6 0.00 0.00
3 0.00 0.00
0.00 0.00
30.26 deg. Inclination
Length Pcs
C- purlins 5.3 15 = 79.5
1.6 10 = 16
2.4 3= 7.2
102.7
136.37 sq.m
COST COMPUTATION:
MATERIAL COSTING
DIRECT
STRUCTURE qty unit MATERIALS QTY UNIT PRICE COST DIRECT COST
PRICE
1.44 sq.m CHB 6" 18.00 pcs 35.00 31.25 630.00 562.50
1.44 sq.m Cement 0.83 bags 230.00 205.36 191.27 170.78
1.44 sq.m Sand 0.11 cu.m 700.00 625.00 77.62 69.30
1.44 sq.m tie.wire 0.06 kg 40.00 35.71 2.42 2.16
Exterior wall 1.44 sq.m rebar 2.96 kg 35.00 31.25 103.57 92.48
1.44 sq.m Alignmentkey 16.20 pcs 7.00 6.25 113.40 101.25
1.44 sq.m Delivery charge 18.00 pcs 10.50 9.38 189.00 168.75
1.44 sq.m CHB 4" 18.00 pcs 32.00 28.57 576.00 514.29
1.44 sq.m Cement 0.65 bags 230.00 205.36 149.04 133.07
1.44 sq.m Sand 0.09 cu.m 700.00 625.00 60.48 54.00
1.44 sq.m tie.wire 0.06 kg 40.00 35.71 2.42 2.16
Interior wall 1.44 sq.m rebar 2.96 kg 35.00 31.25 103.57 92.48
1.44 sq.m Alignmentkey 16.20 pcs 7.00 6.25 113.40 101.25
1.44 sq.m Delivery charge 18.00 pcs 8.15 7.28 146.70 130.98
- - -
- - -
- - -
DIRECT No. of Total Labor
DIRECT COST Cost / unit Man Hour Rate
Cost / unit Workers Cost
562.50 437.50 390.63
170.78 132.83 118.59
69.30 53.90 48.13
2.16 1.68 1.50
92.48 71.93 64.22
101.25 78.75 70.31
168.75 131.25 117.19
907.83 810.56
514.29 400.00 357.14
133.07 103.50 92.41
54.00 42.00 37.50
2.16 1.68 1.50
92.48 71.93 64.22
101.25 78.75 70.31
130.98 101.88 90.96
799.73 714.04
106.46 82.80 73.93
18.00 14.00 12.50
- 96.80 86.43
52.90 41.14 36.73
- 41.14 36.73
257.14 200.00 178.57
58.44 45.45 40.58
- 245.45 219.16
-
-
-
Description
Labor Skilled Coverage Rate / Unit
Work Descriptiom Unit Rate / Unit
450 500 / day (LESS 12%)
Earth Works
a.)Lay-Out and Staking 3.00 1.00 100.00 sq.m 19.00 16.96
b.)Excavation Work 1 1 cu.m 450.00 401.79
c Fill & Compaction 1 9.76 cu.m 47.00 41.96
d Gravel Bedding 1 6 cu.m 75.00 66.96
-
Concrete Works - -
Slab on Grade 1 1 1.6 cu.m 594.00 530.36
Column 1 1 6.8 cu.m 140.00 125.00
Beams 1 1 5.2 cu.m 183.00 163.39
Suspended Slab 1 1 4.8 cu.m 198.00 176.79
- -
Formworks - -
Fabrication 1 1 14.88 sq.m 64.00 57.14
Stripping:
Beams 2 15.6 sq.m 58.00 51.79
Column 2 18.8 sq.m 48.00 42.86
Slab 2 14.8 sq.m 61.00 54.46
Reinforcement
Fabrication 2 150 kg 7.00 6.25
Installation 1 1 111 kg 9.00 8.04
Steel Deck 1 2 15 sq.m 97.00 86.61
Metal Works
Structural Steel 1 1 160 kg 6.00 5.36
Fabrication of anchor bolts 1 1 80 kg 12.00 10.71
Installation of anchor bolts 1 1 24 kg 40.00 35.71
Fabrication of embbeded Items 1 1 56 kg 17.00 15.18
Painting Works
Any Pain 1 1 27.84 sq.m 35.00 31.25
Varnish 1 1 18.56 sq.m 52.00 46.43
Structural Steel frame 1 1 160 lm 6.00 5.36
Tinsmithing
Corr. G.I. Sheet (Lifting) 4 40 sq.m 45.00 40.18
Corr. G.I. Sheet (Installation) 1 2 40 sq.m 37.00 33.04
Gutter (Cut & Shape) 1 52.16 lm 10.00 8.93
Downspout (out & Shape) 1 52.16 lm 10.00 8.93
Downspout (Installation) 1 1 52.16 lm 19.00 16.96
Installation of Inulation Material 1 1 40 sq.m 24.00 21.43
Block Laying
4" CHB ordinary 1 1 12 sq.m 80.00 71.43
6" CHB ordinary 1 1 10 sq.m 95.00 84.82
8" CHB ordinary 1 1 8 sq.m 119.00 106.25
Tile Works
Glaze Tile 1 1.52 sq.m 329.00 293.75
Unglaze Tile 1 1.84 sq.m 272.00 242.86
Vinyl floor tiles 1 2 sq.m 250.00 223.21
Ceiling Works
Frame Work 1 2 20 sq.m 73.00 65.18
Facia 1 1 20 sq.m 48.00 42.86
Ceiling Works 1 2 15 sq.m 97.00 86.61
Sealant
Sealant application 1 90 lm 6.00 5.36
block laying 53
rebar 30.6
grouting 95
Catch Basin Cost Computation
Stair Railings