I PEK. PENDAHULUAN
1 Analisa 1 M2 19.30 1,160.00 22,388.00 19.30 0.00 22,388.00 22,388.00
Pembersihan Lokasi
2 Analisa 1 M Pengukuran 17.60 5,194.71 91,426.88 17.60 54,318.88 37,108.00 91,426.88
dan Pemasangan
Bowplank
113,814.88 54,318.88 59,496.00 113,814.88
II PEK. PONDASI
1 Analisa 1 M3 Galian 2.30 25,200.00 57,960.00 2.30 0.00 57,960.00 57,960.00
Tanah Pondasi
2 1 M3 Pasir Bawah 0.35 50,137.14 17,548.00 0.35 14,700.00 2,848.00 17,548.00
Pondasi/Lantai
3 Analisa 1 M3 Lantai 0.35 435,640.00 152,474.00 0.35 109,550.00 42,924.00 152,474.00
Kerja 1 PC : 3 PS : 5
KR
4 Analisa 1 M3 Beton Cor 0.30 1,704,865.64 511,459.69 0.30 333,211.69 178,248.00 511,459.69
Pondasi
5 Analisa 1 M3 Beton Cor 0.03 2,446,974.52 78,303.18 0.03 54,383.18 23,920.00 78,303.18
Kolom Pedestal
6 1 M2 Pasang Batu Bata 3.40 95,104.00 323,353.60 3.40 255,081.60 68,272.00 323,353.60
1 ROLAG
7 1 M2 Plesteran 1 : 4 9.50 18,476.00 175,522.00 9.50 80,142.00 95,380.00 175,522.00
1,316,620.48 847,068.48 469,552.00 1,316,620.48
IV PEK. DINDING
1 1 M2 Pasang Batu Bata 31.30 45,055.00 1,410,221.50 31.30 1,095,969.50 314,252.00 1,410,221.50
1:2
2 1 M2 Plesteran 1 : 4 62.60 18,476.00 1,156,597.60 62.60 528,093.60 628,504.00 1,156,597.60
3 1 M2 Acian 84.40 5,030.00 424,532.00 84.40 149,388.00 275,144.00 424,532.00
2,991,351.10 1,773,451.10 1,217,900.00 2,991,351.10
V PEK. LANTAI
1 1 M3 Urug Tanah 1.10 61,120.00 67,232.00 1.10 49,500.00 17,732.00 67,232.00
Dipadatkan
2 1 M3 Pasir Bawah 0.22 50,109.09 11,024.00 0.22 9,240.00 1,784.00 11,024.00
Lantai
3 Analisa 1 M3 Lantai 0.22 435,618.18 95,836.00 0.22 68,860.00 26,976.00 95,836.00
Kerja 1 PC : 3 PS : 5
KR
4 1 M2 Pasang Keramik 6.90 87,550.00 604,095.00 6.90 396,819.00 207,276.00 604,095.00
ruangan 40 X 40
5 1 M2 Pasang Keramik 11.30 109,930.00 1,242,209.00 11.30 902,757.00 339,452.00 1,242,209.00
wc 25 X 25
2,020,396.00 1,427,176.00 593,220.00 2,020,396.00
VI PEK PLAFOND
1 1 M2 Plafond Gypsum + 5.00 107,030.50 535,152.50 5.00 257,152.50 278,000.00 535,152.50
Rangka
535,152.50 257,152.50 278,000.00 535,152.50