Name of Project :DIG Warehouse Partation Work

BUILDER'S ESTIMATE
Sr
Particulars Quantity Unit Rate Per Amount Total
No
1 AC Sheet Partation Work with (3"x1.5" Hollow Pipe 2'x4' Frame)
534.00 Sft
Material
3"x1.5" MS Hollow Pipe 640.80 Rft 1100 Rft 704880.0
4mm AC Sheet(2 side) 35.04 Sheet 14000 Sheet 490612.5
No.12 welding 2.67 pack 12000 pack 32040.0
1" Screw 3.71 Gross 2300 Gross 8529.2
1236061.7
Labour
Partaition install charges 534.00 Sft 650 Sft 347100.0
347100.0 1583161.7

2 AC Sheet Ceiling Work


760.00 Sft
AC Sheet Ceiling 760.00 Sft 1700 Sft 1292000.0
1292000.0 1292000.0
3 Door Installation
56.00 Sft
Material
Teak Door Leaf 56.00 Bag 3600 Bag 201600.0
Butt Hinge 12.00 Sud 1200 Sud 14400.0
Screw 1.00 Gross 2300 Gross 2300.0
Door Lock 2.00 nos 9000 218300.0
436600.0
Labour
Carpenter 3.36 Nos 10000 Nos 33600.0
Worker 4.48 Nos 7000 Nos 31360.0
64960.0 283260.0

4 Painting Work(emulsion)
1828.00 Sft
Material
Putty 13.71 Gal 7000 Gal 95970.0
Sand Paper 9.14 Doz 2400 Doz 21936.0
Putty trowel 4.57 nos 1000 nos 4570.0
Emulsion Paint 18.28 Gal 11000 Gal 201080.0

1
Name of Project :DIG Warehouse Partation Work

BUILDER'S ESTIMATE
Sr
Particulars Quantity Unit Rate Per Amount Total
No
Roller 4.57 nos 0 nos 0.0
323556.0
Labour
Painter 36.56 Nos 10000 Nos 365600.0
Worker 18.28 Nos 7000 Nos 127960.0
493560.0 817116.0
Total 3,975,538

2
Name of Project :DIG Warehouse Partation Work

BUILDER'S ESTIMATE
Sr
Particulars Quantity Unit Rate Per Amount Total
No

3
Name of Project :DIG Warehouse Partation Work

BUILDER'S ESTIMATE
Sr
Particulars Quantity Unit Rate Per Amount Total
No