Calendar days
№ Description
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47

Preparation works before cooling of heating walls 144,145 -inspection


of anchorage system, bracing of backstays, coke pushing from chambers
1
under repair 143,144,145 and buffer chambers 142,146, installing of
façade and front bridges.
Switch off heating, cooling and dismantling of 8 vertical flues of
2
heating walls 144,145 from coke side
Removal/Installing equipment under repaired chambers 143,144,145
and heating walls 144,145 from coke side (doors, gas outlet standpipes,
3
frames, flash plates, upper part of backstay, upper tie-rods, frames of
charging hole) stage-by-stage
Bricklaying of heating walls 144,145 and roofing of chamber
4
143,144,145 from coke side
Switch off heating, cooling and dismantling of 8 vertical flues of
5
heating walls 144,145 from pushing side.
Removal/Installing equipment under repaired chambers 143,144,145
and heating walls 144,145 from pushing side (doors, gas outlet
6
standpipes, frames, flash plates, upper part of backstay, upper tie-rods,
frames of charging hole) stage-by-stage
Bricklaying of heating walls 144,145 and roofing of chamber
7
143,144,145 from pushing side

8 Heating up of heating walls 144,145 by heat transfer method

Works executed from the beginning of heating up till start of


operation of buffer chamber under repair. - Control of load
pressure of reinforcing, blowing and pouring grooves of transverse
9
tie bars, removing of fixing beam for backstays and tie rods,
removing bracing bulkheads from buffer and chamber under repair,
blowing of coke chamber sole(bottom)
Start-up of buffer and repaired chambers 142,143,144,145,146 in
10
operation.