Schedule of Lighting Pole Installation/Gumti 2nd Bridge

Particular 17 June '19 18 June '19 19 June '19 20 June '19 21 June '19 22 June '19 23 June '19 24 June '19 25 June '19 26 June '19

Cable Installation 100% Done

Cable Insulation and Continuity Test 100% Done

Lighting Pole Inspection 100% Done

Lighting Pole Repair Works 100% Done

Scaffolding Making S25-S14=12Nos S13-S1=14Nos

Nut Leveling S25-S14=12Nos S13-S1=14Nos

Cutting and Preparing Cable for wiring


N25-N14=12Nos N13-N1=14Nos 40% 50%
Pole.

Preparing Bakelite Plate Already 30% Done 30% 40%

Chipping area cleaning on Foundation


Already 25% Done 25% 25%
of LP

Lighting Pole Mobilize at Barge S25-S17=9Nos S16-S09=08Nos S08-S01=08Nos

Lighting Pole Wiring S25-S17=9Nos S16-S09=08Nos S08-S01=08Nos

Lighting Pole Installation S25-S17=9Nos S16-S09=08Nos S08-S01=08Nos

Formwork for Grouting S25-S14=12Nos S13-S1=14Nos

Grouting S25-S01=25Nos

Splicing & Connection of Junction Box


S01-S25=25Nos N1-N25=25Nos N26-N47=22Nos S26-S47=22Nos
to Lighting Pole
S01 - S47
Checking & Internal Inspection &
&
Housekeeping
N01 - N47

Date: 13 June 2019