You are on page 1of 28

29 April 2010

The Managing Director


Cancellations Nigeria Ltd.
20 East/West Road
Rumuodara – Port Harcourt
Rivers State/Nigeria.

Dear Madam,
QUOTATION FOR THE CONSTRUCTION OF CLASS ROOM

The above subject matter refers.

We hereby submit our quotation for the construction of the above mentioned subject
matters for your consideration and approval.

Below are the work estimates

(A) CONSUMABLES
S/No Particulars U/Price Amount (N)
1. 6 Bottles of Acetylene 12,000 72,000.00
2. 12 Bottles of Oxygen 3,500 36,000.00
3. 21 Packets of Electrode 1,500 31,000.00
4. 16 Pieces of Grinding stone 450 7,200.00
5. 32 Tins of red oxide 1,800 57,600.00
6. 4 Pieces of wire brush 350 10,000.00
7. 10 Pieces of painting brush 150 1,500.00
8. 8 Tins of thinner 2,500 3,900.00
9. P.P.E. - 50,000.00
10. Drilling/Bending of plate - 250,000.00
11. Welding Materials - 220,000.00
Total
N739,200.00

(B.) FABRICATION
S/No Items Nos. Duration U/Price Amount (N)
1. Fitters 3 17 3,500 178,500.00
2. Welders 4 17 3,500 238,000.00
3. Burner 1 17 3,500 59,500.00
4. Helpers 4 17 2,500 170,000.00
5. Supervision 1 17 5,000 85,000.00
6. Logistics Ls Ls Ls 200,000.00
7. Foreman Ls Ls Ls 250,000.00

Total N1,181,000.00
(C.) INSTALLATION
S/No Items Nos. Duration U/Price Amount (N)
1. Erector 6 14 4,000 336,000.00
2. Helper 4 14 2,500 140,000.00
3. Fitter 2 14 3,500 98,000.00
4. Welders 2 14 3,500 98,000.00
5. Derrick/Torfor 2 14 15,000 420,000.00
6. Foreman 1 14 5,000 70,000.00
7. Supervisor Ls Ls Ls 280,000.00
8. Logistic Ls Ls Ls 300,000.00
Sub-Total 1,742,000.00

Grand - Total N3,662,200.00

Grand Total (N3,662,200 X 6Nos.) = N21,974,200.00

Note: Roofing Sheet Installation is not inclusive in this quotation.

Thanks for your patronage.

Yours faithfully
PETTERS ENGINEERING WORKS LTD.

PETER ABRAHAM
Managing Director

NOTE:
Community settlement/transportation of materials will be settled by you.
MATERIALS FOR CLASS ROOM X 6 NOS.

S/No. Particulars U/Price Amount (N)


1. 62pcs of 65 X 65X5m angle iron 6,000 372,000.00

2. 182pcs of 50 X 50X6mm angle iron 5,200 946,400.00

3. 178pcs of 150 X 50 = Purline 3,800 676,400.00

4. 2 Sheets of 6mm plate 22,000 44,000.00

5. 1 Sheet of 12mm plate 50,000 50,000.00

6. 128pcs of 16mm X 300mm Wall bolt 300.00 38,400.00

7. 124pcs of 12mm X 125mm Zag rod 450.00 55,800.00

8. 840pcs of 12 X 50mm bolt 60.00 59,400.00

9. 112pcs of 16 X 50mm bolt 80.00 8,960.00

Total N2,260,320.00

N2,260,320.00 X 6NOS = N13,561,920.00


29 April 2010

The Managing Director


Cancellations Nigeria Ltd.
20 East/West Road
Rumuodara – Port Harcourt
Rivers State/Nigeria.

Dear Madam,
QUOTATION FOR THE CONSTRUCTION OF ADMIN BLOCK

The above subject matter refers.

We hereby submit our quotation for the construction of the above mentioned subject
matters for your consideration and approval.

Below are the work estimates

(A) CONSUMABLES
S/No Particulars U/Price Amount (N)
1. 10 Bottles of Acetylene 12,000 120,000.00
2. 20 Bottles of Oxygen 3,500 70,000.00
3. 42 Packets of Electrode 1,500 63,000.00
4. 36 Pieces of Grinding stone 450 162,000.00
5. 60 Tins of red oxide 1,800 108,000.00
6. 16 Pieces of wire brush 350 5,600.00
7. 18 Pieces of painting brush 150 2,700.00
8. 6 Tins of thinner 2,500 15,000.00
9. P.P.E. - 85,000.00
10. Drilling/Bending of plate - 270,000.00
11. Welding Materials - 250,000.00
Total
N1,151,300.00
(B.) FABRICATION
S/No Items Nos. Duration U/Price Amount (N)
1. Fitters 4 24 3,500 336,000.00
2. Welders 6 24 3,500 504,000.00
3. Burner 2 24 3,500 168,000.00
4. Helpers 6 24 2,500 360,000.00
5. Supervision 1 24 5,000 120,000.00
6. Logistics Ls Ls Ls 350,000.00
7. Foreman Ls Ls Ls 300,000.00

Total N2.138,000.00

(C.) INSTALLATION
S/No Items Nos. Duration U/Price Amount (N)
1. Erector 8 20 4,000 640,000.00
2. Helper 2 20 3,500 140,000.00
3. Fitter 3 20 3,500 210,000.00
4. Helper 6 20 3,500 300,000.00
5. Foreman 1 20 5,000 100,000.00
6. Supervision Ls Ls Ls 400,000.00
7. Derrick/Tirfor 2 15 15,000 450,000.00
8. Logistics Ls Ls Ls 350,000.00
Sub-Total 2,590,000.00

Grand - Total N5,879,300.00

Grand Total = N5,879,300.00

Note: Roofing Sheet Installation is not inclusive in this quotation.

Thanks for your patronage.

Yours faithfully
PETTERS ENGINEERING WORKS LTD.

PETER ABRAHAM
Managing Director
NOTE:
Community settlement/transportation of materials will be settled by you.

MATERIALS FOR ADMIN BLOCK

S/No. Particulars U/Price Amount (N)


1. 358pcs of 50X50X6mm angle iron 5,200 1,861,600.00

2. 152pcs of 65X65X5mm agle iron 6,000 912,000.00

3. 245pcs of 150X50 Z Purline 3,800 931,000.00

4. 5 Sheets of 6mm plate 22,000 110,000.00

5. 1480 pcs of 16mm X 50 bolt 60.00 88,800.00

6. 2 Sheets of 12mm plate 50,000 100,000.00

7. 280pcs of 12mm X 1250mm Zap rod 450.00 126,000.00

8. 288pcs of 16 X 300mm wall rack bolt 300.00 86,400.00

9. 168pcs of 16 mm X 50mm bolt 80.00 13,440.00

Total N4,229,240.00
29 April 2010

The Managing Director


Cancellations Nigeria Ltd.
20 East/West Road
Rumuodara – Port Harcourt
Rivers State/Nigeria.

Dear Madam,

QUOTATION FOR THE CONSTRUCTION OF HOSTEL

The above subject matter refers.

We hereby submit our quotation for the construction of the above mentioned subject
matters for your consideration and approval.

Below are the work estimates

(A) CONSUMABLES
S/No Particulars U/Price Amount (N)
1. 7 Bottles of Acetylene 12,000 84,000.00
2. 16 Bottles of Oxygen 3,500 56,000.00
3. 32 Packets of Electrode 1,500 48,000.00
4. 24 Pieces of Grinding stone 450 10,800.00
5. 52 Tins of red oxide 1,800 93,600.00
6. 12 Pieces of wire brush 350 4,200.00
7. 10 Pieces of painting brush 150 1,500.00
8. 5 Tins of thinner 2,500 12,500.00
9. P.P.E. - 70,000.00
10. Drilling/Bending of plate - 250,000.00
11. Welding Materials - 250,000.00
Total
N880,600.00

(B.) FABRICATION
S/No Items Nos. Duration U/Price Amount (N)
1. Fitters 6 18 3,500 252,000.00
2. Welders 2 18 3,500 378,000.00
3. Burner 2 18 3,500 126,000.00
4. Helpers 4 18 2,500 270,000.00
5. Foreman 1 18 5,000 90,000.00
6. Supervision Ls Ls Ls 350,000.00
7. Logistic Ls Ls Ls 300,000.00

Total N1,766,000.00

(C.) INSTALLATION
S/No Items Nos. Duration U/Price Amount (N)
1. Erector 6 14 4,000 336,000.00
2. Fitter 2 14 3,500 98,000.00
3. Welder 2 14 3,500 98,000.00
4. Helper 4 14 2,500 140,000.00
5. Foreman 1 14 5,000 70,000.00
6. Site Logistic Ls - - 350,000.00
7. Derrick/Tirfor 2 14 15,000 420,000.00
8. Supervision Ls - - 350,000.00
Sub-Total N1,862,000.00

Grand - Total N4,508,600.00

Grand Total (N4,508,600 X 6Nos.) = N27,051,600.00

Note: Roofing Sheet Installation is not inclusive in this quotation.

Thanks for your patronage.


Yours faithfully
PETTERS ENGINEERING WORKS LTD.

PETER ABRAHAM
Managing Director

NOTE:
Community settlement/transportation of materials will be settled by you.

MATERIALS FOR HOSTEL

S/No. Particulars U/Price Amount (N)


1. 403pcs of 50X50X6mm angle iron 5,200 2,095,600.00
2. 29pcs of 60X6015mm angle iron 6,000 174,000.00
3. 190pcs of 150X50 X 1.5mm Z Purline 3,800 722,000.00
4. 320pcs of 16mmX300 wall bolt 300.00 96,000.00
5. 3 Sheets of 12mm plate 50,000 150,000.00
6. 4 Sheets of 6mm plate 22,000 88,000.00
7. 1356pcs of 12mmX50mm bolt 60.00 81,360.00
8. 220pcs of 12mmX1250mm Zag rod 450.00 99,000.00
9. 120pcs of 16mmX50mm bolt 80.00 9,600.00

Total N3,515,560.00
N3,515,560.00 X 6NOS. = N21,093,360.00

29 April 2010

The Managing Director


Cancellations Nigeria Ltd.
20 East/West Road
Rumuodara – Port Harcourt
Rivers State/Nigeria.

Dear Madam,

QUOTATION FOR THE CONSTRUCTION OF THREATRE

The above subject matter refers.

We hereby submit our quotation for the construction of the above mentioned subject
matters for your consideration and approval.

Below are the work estimates

(A) CONSUMABLES
S/No Particulars U/Price Amount (N)
1. 11 Bottles of Acetylene 12,000 132,000.00
2. 23 Bottles of Oxygen 3,500 80,500.00
3. 32 Packets of Electrode 1,500 72,000.00
4. 68 Pieces of Grinding stone 450 14,400.00
5. 68 Tins of red oxide 1,800 122,400.00
6. 18 Pieces of wire brush 350 6,300.00
7. 20 Pieces of painting brush 150 3,000.00
8. 8 Tins of thinner 2,500 20,000.00
9. P.P.E. - 120,000.00
10. Drilling/Bending of plate - 350,000.00
11. Welding Materials - 300,000.00
Total
N1,220,600.00

(B.) FABRICATION
S/No Items Nos. Duration U/Price Amount (N)
1. Fitters 6 24 3,500 504,000.00
2. Welders 4 24 3,500 504,000.00
3. Burner 2 24 3,500 168,000.00
4. Helpers 6 24 2,500 360,000.00
5. Foreman 1 24 5,000 120,000.00
6. Supervision Ls Ls Ls 400,000.00
7. Logistic Ls Ls Ls 350,000.00

Total N2,406,000.00

(C.) INSTALLATION
S/No Items Nos. Duration U/Price Amount (N)
1. Erector 8 22 4,000 640,000.00
2. Fitter 3 22 3,500 231,000.00
3. Welder 3 22 3,500 231,000.00
4. Helper 6 22 2,500 330,000.00
5. Crane 1 2days 120,000 240,000.00
6. Foreman 1 22 5,000 110,000.00
7. Site Logistic Ls Ls Ls 400,000.00
8. Supervision Ls Ls Ls 400,000.00
9. Derrick/Tirfor 2 16 15,000 480,000.00
Sub-Total N3,062,000.00

Grand - Total N6,688,600.00

Grand Total = N6,688,600.00


Note: Roofing Sheet Installation is not inclusive in this quotation.

Thanks for your patronage.

Yours faithfully
PETTERS ENGINEERING WORKS LTD.

PETER ABRAHAM
Managing Director

NOTE:
Community settlement/transportation of materials will be settled by you.

MATERIALS FOR THREATRE

S/No. Particulars U/Price Amount (N)


1. 144pcs of 75X75X6mm angle iron 7,800 1,123,200.00
2. 60pcs of 60X60 X1.5mm angle iron 6,000 360,000.00
3. 222pcs of 50X50 X 1.5mm angle iron 5,200 1,154,400.00
4. 218pcs of 150mmX50 X1.5mm Z purline 3,800 828,400.00
5. 4 Sheets of 6mm plate 22,000 88,000.00
6. 1 Sheets of 12mm plate 50,000 50,000.00
7. 136pcs of 16mmX300mm bolt 300.00 40,000.00
8. 220pcs of 12mmX1250mm Zag rod 450.00 99,000.00
9. 130pcs of 16mm X 50mm bolt 80.00 10,400.00
10. 784pcs of 12mm X 50mm bolt 60.00 47,040.00

Total N3,800,440.00

N3,800,440.00 X 6NOS. = N22,802,640.00

29 April 2010

The Managing Director


Cancelations Nigeria Ltd.
Plot 20, East/West Road
Rumuodara – Port Harcourt
Rivers State/Nigeria.

Dear Madam,
QUOTATION FOR THE CONSTRUCTION OF TWO (02 NOS.) WORKSHOP

The above subject matter refers.

We hereby submit our quotation for the construction of the above mentioned subject
matters for your consideration and approval.

Below are the work estimates


(B) CONSUMABLES
S/No Particulars U/Price Amount (N)
12. 16 Bottles of Acetylene 12,000 216,000.00
13. 34 Bottles of Oxygen 3,500 119,000.00
14. 54 Packets of Electrode 1,500 81,000.00
15. 48 Pieces of Grinding stone 450 21,600.00
16. 76 Tins of red oxide 1,800 118,800.00
17. 16 Pieces of wire brush 350 5,600.00
18. 26 Pieces of painting brush 150 2,400.00
19. 8 Tins of thinner 2,500 3,900.00
20. P.P.E. - 90,000.00
21. Drilling/Bending of plate - 250,000.00
22. Welding Materials - 280,000.00
Total
N1,288,500.00

(B.) FABRICATION
S/No Items Nos. Duration U/Price Amount (N)
8. Fitters 6 30 3,500 630,000.00
9. Welders 8 30 3,500 840,000.00
10. Burner 2 30 3,500 210,000.00
11. Helpers 8 30 2,500 600,000.00
12. Supervision Ls Ls Ls 450,000.00
13. Logistics Ls Ls Ls 300,000.00
14. Foreman 2 30 5,000 300,000.00

Total N3,330,000.00

(C.) INSTALLATION
S/No Items Nos. Duration U/Price Amount (N)
9. Erecters 7 28 4,000 784,000.00
10. Fitters 4 28 3,500 392,000.00
11. Welders 4 28 3,500 392,000.00
12. Helpers 6 28 2,500 420,000.00
13. Supervision Ls Ls Ls 750,000.00
14. Foreman 1 28 5,000 140,000.00
15. Derrick/Tirfor 2 24 15,000 720,000.00
16. Marine Rope 4 nil 5,000 20,000.00
17. Site Logistics Ls Ls Ls 450,000.00
Sub-Total 4,060,000.00

Grand - Total N8,686,500.00


Grand Total (N8,686,500X2) = N17,373,000.00
Materials = N11,934,320.00
----------------------
Total Sum = N29,307,320.00
=============

Note: Roofing Sheet Installation is not inclusive in this quotation.

Thanks for your patronage.

Yours faithfully
PETTERS ENGINEERING WORKS LTD.

PETER ABRAHAM
Managing Director

MATERIALS FOR TWO (02) WORKSHOPS

S/No Particulars U/Price Amount (N)


1. 192 Lengths of 65X65 angle iron 6,000 1,152,000.00
2. 1284 Lengths of 50X50 angle iron 5,200 6,676,800.00
3. 7 Sheets of 12mm steel plate 50,000 350,000.00
4. 16 Sheets of 6mm steel plate 22,000 352,000.00
5. 750 Pieces of 150X50X1.5 Z purline 3,800 2,850,000.00
6. 2936 Pieces of 12mmX50mm bolt 60.00 176,160.00
7. 492 Pieces of 16mmX60mm bolt 80.00 39,360.00
8. 960 Pieces of 300X20mm bolt 300 288,000.00
9. Transportation of materials 50,000.00

Total N11,934,320.00

29 April 2010

The Managing Director


Cancellations Nigeria Ltd.
20 East/West Road
Rumuodara – Port Harcourt
Rivers State/Nigeria.

Dear Madam,
QUOTATION FOR THE CONSTRUCTION OF TWO (02 NOS.) WORKSHOP

The above subject matter refers.

We hereby submit our quotation for the construction of the above mentioned subject
matters for your consideration and approval.

Below are the work estimates


A. CONSUMABLES
S/No Particulars U/Price Amount (N)
1. 16 Bottles of Acetylene 12,000 216,000.00
2. 34 Bottles of Oxygen 3,500 119,000.00
3. 54 Packets of Electrode 1,500 81,000.00
4. 48 Pieces of Grinding stone 450 21,600.00
5. 76 Tins of red oxide 1,800 118,800.00
6. 16 Pieces of wire brush 350 5,600.00
7. 26 Pieces of painting brush 150 2,400.00
8. 8 Tins of thinner 2,500 3,900.00
9. P.P.E. - 90,000.00
10. Drilling/Bending of plate - 250,000.00
11. Welding Materials - 280,000.00
Total
N1,288,500.00

B. FABRICATION
S/No Items Nos. Duration U/Price Amount (N)
1. Fitters 6 30 3,500 630,000.00
2. Welders 8 30 3,500 840,000.00
3. Burner 2 30 3,500 210,000.00
4. Helpers 8 30 2,500 600,000.00
5. Supervision Ls Ls Ls 450,000.00
6. Logistics Ls Ls Ls 300,000.00
7. Foreman 2 30 5,000 300,000.00

Total N3,330,000.00

C. INSTALLATION
S/No Items Nos. Duration U/Price Amount (N)
1. Erecters 7 28 4,000 784,000.00
2. Fitters 4 28 3,500 392,000.00
3. Welders 4 28 3,500 392,000.00
4. Helpers 6 28 2,500 420,000.00
5. Supervision Ls Ls Ls 750,000.00
6. Foreman 1 28 5,000 140,000.00
7. Derrick/Tirfor 2 24 15,000 720,000.00
8. Marine Rope 4 nil 5,000 20,000.00
9. Site Logistics Ls Ls Ls 450,000.00
Sub-Total 4,060,000.00

Grand - Total N8,686,500.00

Grand Total (N8,686,500X2) = N17,373,000.00


Materials = N11,934,320.00
----------------------
Total Sum = N29,307,320.00
=============

Note: Roofing Sheet Installation is not inclusive in this quotation.

Thanks for your patronage.

Yours faithfully
PETTERS ENGINEERING WORKS LTD.

PETER ABRAHAM
Managing Director

MATERIALS FOR TWO (02) WORKSHOPS

S/No Particulars U/Price Amount (N)


1. 192 Lengths of 65X65 angle iron 6,000 1,152,000.00
2. 1284 Lengths of 50X50 angle iron 5,200 6,676,800.00
3. 7 Sheets of 12mm steel plate 50,000 350,000.00
4. 16 Sheets of 6mm steel plate 22,000 352,000.00
5. 750 Pieces of 150X50X1.5 Z purline 3,800 2,850,000.00
6. 2936 Pieces of 12mmX50mm bolt 60.00 176,160.00
7. 492 Pieces of 16mmX60mm bolt 80.00 39,360.00
8. 960 Pieces of 300X20mm bolt 300 288,000.00
9. 480pcsof 12mmX1250mm Zag rod 450 216,000.00

Total N12,150,320.00
29 April 2010

The Managing Director


Cancelations Nigeria Ltd.
Plot 20, East/West Road
Rumuodara – Port Harcourt
Rivers State/Nigeria.

Dear Madam,
QUOTATION FOR THE CONSTRUCTION OF DINNING HALL

The above subject matter refers.

We hereby submit our quotation for the construction of the above mentioned subject
matters for your consideration and approval.

Below are the work estimates

A. CONSUMABLES

S/No Particulars U/Price Amount (N)


1. 8 Bottles of Acetylene 12,000 96,000.00
2. 18 Bottles of Oxygen 3,500 63,000.00
3. 38 Packets of Electrode 1,500 57,000.00
4. 28 Pieces of grinding stone 450 12,600.00
5. 48 Tins of Red-oxide 1,800 86,400.00
6. 12 Pieces of wire brush 350 4,200.00
7. 14 Pieces of painting brush 150 2,100.00
8. 6 Tins of thinner 2,500 15,000.00
9. P.P.E. 65,000.00
10. Drilling/Bending of plate 270,000.00
11. Welding materials 250,000.00
N921,300.00
Total

B. FABRICATION
S/No Items Nos. Duration U/Price Amount (N)
1. Fitters 4 21 3,500 378,000.00
2. Welders 6 21 3,500 567,000.00
3. Burner 2 21 3,500 189,000.00
4. Helpers 6 21 2,500 315,000.00
5. Foreman 1 21 5,000 105,000.00
6. Logistics Ls Ls - 350,000.00
7. Supervision 1 Ls Ls 300,000.00

Total N2,204,000.00

C. INSTALLATION
S/No Items Nos. Duration U/Price Amount (N)
1. Erecters 8 22 4,000 640,000.00

2. Fitters 2 22 3,500 210,000.00

3. Welders 3 22 3,500 280,000.00

4. Helpers 6 22 2,500 300,000.00

5. Foreman 1 22 5,000 110,000.00

6. Site Logistics Ls - Ls 400,000.00

7. Derrick/Tirfor 2 18 20,000 480,000.00

8. Marine Rope 4 - 5,000 20,000.00

9. Supervision 1 - - 350,000.00

Sub-Total 2,990,000.00
Grand - Total N6,114,300.00

Grand Total = N6,114,300.00


Materials = N3,195,680.00
---------------------
Total Sum = N9,309,980.00
=============

Note: Roofing Sheet Installation is not inclusive in this quotation.

Thanks for your patronage.

Yours faithfully
PETTERS ENGINEERING WORKS LTD.

PETER ABRAHAM
Managing Director

MATERIALS FOR DINNING HALL

S/No Particulars U/Price Amount (N)


1. 68 Lengths of 65X65X5m angle iron 6,000 408,000.00
2. 274 Lengths of 50X50X6mm angle iron 5,200 1,424,800.00
3. 6 Sheets of 12mm plate 50,000 300,000.00
4. 5 Sheets of 6mm plate 22,000 110,000.00
5. 186 Lengths of 150X50X1.5 Z purline 3,800 706,800.00
6. 948 Pieces of 12mmX50 bolt 60.00 56,880.00
7. 120 Pieces of 16X60mm bolt 80.00 96,000.00
8. 144 Pieces of 300X20mm wall bolt 300 43,200.00
9. 140pcs of 12mm X 1250mm Zag rod 450 63,000.00
N3,258,680.00
Total

29 April 2010

The Managing Director


Cancelations Nigeria Ltd.
Plot 20, East/West Road
Rumuodara – Port Harcourt
Rivers State/Nigeria.

Dear Madam,
QUOTATION FOR THE CONSTRUCTION OF TOWN HALL

The above subject matter refers.


We hereby submit our quotation for the construction of the above mentioned subject
matters for your consideration and approval.

Below are the work estimates

A. CONSUMABLES
S/No Particulars U/Price Amount (N)
1. 6 Bottles of Acetylene 12,000 72,000.00
2. 14 Bottles of Oxygen 3,500 49,000.00
3. 32 Packets of Electrode 1,500 48,000.00
4. 24 Pieces of grinding stone 450 10,800.00
5. 43 Tins of red oxide 1,800 77,400.00
6. 12 Pieces of wire brush 350 4,200.00
7. 16 Pieces of painting brush 150 2,400.00
8. 5 Tins of thinner 2,500 12,500.00
9. P.P.E. - 75,000.00
10. Drilling/Bending of plate - 170,000.00
11. Welding Materials - 150,000.00
N671,300,.00
Total

B. FABRICATION
S/No Items Nos. Duration U/Price Amount (N)
1. Fitters 3 18 3,500 189,000.00
2. Welders 4 18 3,500 252,000.00
3. Burner 2 18 3,500 126,000.00
4. Helpers 6 18 2,500 270,000.00
5. Supervision 1 Ls Ls 250,000.00
6. Logistics Ls Ls Ls 200,000.00
7. Foreman 1 18 5,000 90,000.00

Total N1,377,000.00

C. INSTALLATION
S/No Items Nos. Duration U/Price Amount (N)
1. Erecters 6 15 4,000 360,000.00
2. Fitters 2 15 3,500 105,000.00
3. Welders 2 15 3,500 105,000.00
4. Helpers 6 15 2,500 225,000.00
5. Supervision Ls - - 350,000.00
6. Foreman 1 18 5,000 90,000.00
7. Derrick/Tirfor 1 6 20,000 150,000.00
8. Site Logistics Ls - - 250,000.00
Sub-Total 1,530,000.00
Grand - Total N3,578,300.00

Grand Total For Two Town Halls = N7,156,600.00


Materials For Two Town Halls = N4,257,200.00
---------------------
Total Sum = N11,413,800.00
=============

Note: Roofing Sheet Installation is not inclusive in this quotation.

Thanks for your patronage.

Yours faithfully
PETTERS ENGINEERING WORKS LTD.

PETER ABRAHAM
Managing Director

MATERIALS FOR TWO TOWN HALLS

S/No Particulars U/Price Amount (N)


1. 372 Lengths 50X50X6mm angle iron 5,200 1,934,400.00
2. 8 Sheets of 6mm plate 22,000 176,000.00
3. 8 Sheets of 12mm plate 50,000 400,000.00
4. 328 Pieces of 150X50X1.5 Z purline 3,800 1,246,400.00
5. 2760 Pieces of 12mm bolt 60.00 165,600.00
6. 1700 Pieces of 16mm bolt 80.00 136,000.00
7. 496 Pieces of 300X20mm wall bolt 300 148,800.00
8. 320pcs of 12mmX1250mm Zag rod 450 144,000.00
N4,401,200.00
Total

29 April 2010

The Managing Director


Cancelations Nigeria Ltd.
Plot 20, East/West Road
Rumuodara – Port Harcourt
Rivers State/Nigeria.

Dear Madam,
QUOTATION FOR THE CONSTRUCTION OF TWIN BED ROOM

The above subject matter refers.

We hereby submit our quotation for the construction of the above mentioned subject
matters for your consideration and approval.

Below are the work estimates

A. CONSUMABLES
S/No Particulars U/Price Amount (N)
1. 4 Bottles of Acetylene 12,000 48,000.00
2. 8 Bottles of Oxygen 3,500 28,000.00
3. 12 Packets of Electrode 1,500 18,000.00
4. 14 Pieces of grinding stone 450.00 6,300.00
5. 18 Tins of red oxide 1,800 32,400.00
6. Drilling/Bending of plate - 165,000.00
7. Welding Materials - 50,000.00

Total N347,700.00

B. FABRICATION
S/No Items Nos. Duration U/Price Amount (N)
1. Fitters 3 8 3,500 84,000.00
2. Welders 4 8 3,500 112,000.00
3. Burner 1 8 3,500 28,000.00
4. Helpers 4 8 2,500 80,000.00
5. Foreman 1 8 5,000 46,000.00
6. Supervision Ls Ls Ls 250,000.00
7. Logistics Ls Ls Ls 150,000.00

Total N694,000.00

C. INSTALLATION
S/No Items Nos. Duration U/Price Amount (N)
1. Erecters 6 10 4,500 240,000.00
2. Helpers 4 10 2,500 100,000.00
3. Welders 2 10 3,500 70,000.00
4. Fitters 2 10 3,500 70,000.00
5. Foreman 1 10 5,000 50,000.00
6. Derrick/Tirfor 1 10 20,000 90,000.00
7. Site Logistics - 6 15,000 150,000.00
8. Supervision Ls Ls Ls 250,000.00
Sub-Total 1,020,000.00

Grand - Total N2,234,700.00

Grand Total (N2,061,700X6) = N12,370,200.00


Materials = N 6,212,000.00
---------------------
Total Sum = N18,582,200.00
=============

Note: Roofing Sheet Installation is not inclusive in this quotation.

Thanks for your patronage.

Yours faithfully
PETTERS ENGINEERING WORKS LTD.

PETER ABRAHAM
Managing Director

MATERIALS FOR SIX (06NOS.) BUILDING TWIN BEDROOMS

S/No Particulars U/Price Amount (N)


1. 780 Pieces of 50X50X6mm angle iron 5,200 4,056,000.00
2. 5 Sheets of 12mm plate 50,200 250,000.00
3. 8 Sheets of 6mm plate 22,000 176,000.00
4. 348 Pieces of 150X50X1.5 Z purline 3,800 1,322,400.00
5. 624 Pieces of 300X20mm wall bolt 250.00 187,200.00
6. 2040 Pieces of 12X50mm bolt 60.00 122,400.00
7. 600 Pieces of 16X60mm bolt 80.00 48,000.00
8. 180pcs of 12mmX1250mm Zag rod 450 81,000.00
N6,293,000.00