You are on page 1of 15

DESIGN AND PRODUCTION

Fundamentals of Launching a
Precast Concrete Segmental
Operation for Bridge
Construction Projects

Arthur M. Palmer
Lead Construction Engineer
Parsons Brinckerhoff
Seattle, Wash.

Precast concrete segmental bridge construction is This article explores the necessary facility upgrades
continuously evolving to keep pace in a competitive a precaster will need to successfully undertake
environment. As segmental bridge construction the comprehensive planning, coordination, and
increases in national popularity, a number of transformation process required to enter the
precasters will consider upgrading plant facilities segmental bridge production arena and lists sources
to handle this relatively new product. Historically, for industry technical support for this endeavor.While
general contractors have produced the majority the challenges of upgrading operations to include
of precast concrete segments for existing precast precast concrete segmental bridge components
concrete segmental bridges, and it has been the are considerable, bold innovation and careful risk
exception when a contractor has purchased segments management and system integration can establish
from a precast concrete manufacturing facility. this product line as a true precaster product.

 PCI JOURNAL
A
n experienced precaster is the project within 150 miles (240 km) of Bid Document Review
best person to understand what an existing precast concrete operation, The next step is to derive an antici-
is required to run an efficient, the information presented in this arti- pated contract award date and identify
successful business in today’s competi- cle will be beneficial to the company’s project milestones to extract erection
tive construction market. The forward- future success. dates. Use this knowledge to formulate
thinking precaster may wish to consider The following list of publications will a general inventory for casting yard
expanding plant operations to include be handy reference material to start the start-up requirements, segment cast
a new and growing product line. Most segmental library; other sources will be out time frame, and maximum segment
precasters have some knowledge of listed throughout the article: storage area needed.
segmental bridge construction but may • “Deck Segmentation and Yard Carefully review contract drawings
have steered clear of segmental assem- Organization for Launched to determine segment types, quanti-
bly because of its perceived complexi- Bridges” by M. Rosignoli;1 ties, weights, anchor block configura-
ties. Upgrading a precast concrete op- • “Casting Box Girder Segments” tions, and special project requirements,
eration to handle production of bridge by Moreton and Janssen;2 including mixture proportions, curing
segments can understandably seem to • “Segmental Bridges: The Best in regimens, and testing protocol. Deter-
be a daunting task. the Business” by Barber;3 mine quantity and type of formwork
While a segmental product line is • American Association of State required, and identify the required
not the correct choice for every pre- Highway and Transportation versatility of each form to efficiently
caster, this business potential should Officials’ (AASHTO) Standard handle the project schedule. Map out a
not be dismissed without understand- Specifications for Highway preliminary casting yard layout, poten-
ing the assembly line accuracy, high Bridges and Guide Specifica- tial workforce requirements, and exist-
tolerance, and geometry control pre- tions for Design and Construc- ing (but in need of modification) and/or
cision of this next generation of pre- tion of Segmental Concrete new equipment needs.
cast concrete products. This article Bridges;4 In particular, thoroughly understand-
will explore the necessary upgrades • PCI’s Bridge Design Manual, ing the geometry control aspects of a
that an existing precaster must suc- MNL­-133;5 segmental product line will ensure a
cessfully navigate, including the • “Contractor Checklist: Precast successful outcome. A healthy fear of
planning, coordination, and transfor- Yards” by Palmer;6 a costly mistake is not a bad business
mation processes. The approach taken • American Segmental Bridge perspective to maintain, and successful
here will demystify the start-up pro- Institute’s (ASBI) Construction precasters use a detailed, methodical
cess and provide the precaster with Practices Handbook for Seg- approach to daily procedures. A com-
the information necessary to make an mental Concrete Bridges;7 and prehensive review of software (provid-
educated decision. While the limita- • For additional reading, review ed by others) and monitoring survey
tions of this article preclude provid- a list compiled by the Federal instrument maintenance will keep the
ing all the answers, it is hoped that Highway Administration at project on track.
sufficient material is provided herein www.fhwa.dot.gov/bridge/eli- The theoretical casting curve will be
to allow formulation of the pertinent brary.htm. detailed by the contract drawings and
questions in a methodical evaluation interpreted by the geometry control
process. software with the approved geometry
Segmental
control data files for each bridge span.
Production—Project This span-specific data will provide the
Evaluating a New Overview necessary information to understand
Product Line— the vertical, horizontal, and superel-
Advantages for the Depending on facility location, avail- evation alignment for the bridge. The
Precaster able storage area, transportation, site ac- daily, short-line casting operation will
cess, project size, geometric complexity, be controlled by varying the position
In light of the recent Senate pas- material specifications, delivery schedule, of the match-cast segment in relation
sage of almost $400 billion in funding quality control (QC), testing/inspection to the casting form or wet-cast seg-
for U.S. transportation infrastructure regimens, reinforcing system complex- ment. Horizontal control points are
repair and rehabilitation, the use of ity, deadlines, and the client, each seg- based on the project plane coordinate
precasters in small to medium-sized mental project will have unique aspects system, using north and east surveying
segmental bridge projects will provide that must be identified by the precaster conventions. The baseline alignment
significant improvements to product during the pre-bid process. First, the pre- is established as tangent and/or curved
quality, infrastructure durability, and caster needs to be generally familiar with sections through the horizontal control
project scheduling, all important ad- the segmental construction methods and points.
vantages to project owners and con- proposed erection scheme. Then the pre- Do not limit a review to the con-
tractors. caster should review topics discussed in tract’s structural drawings, but further
If there is an upcoming segmental the following sections. identify all electrical and mechanical

May–June 2006 
insufficient for the loads, overall size,
or delivery schedule for the pending
contract, the precaster must consider
upgrading facility trucking capability
or bidding the segments as freight-on-
board (FOB) plant.
Concrete Batching
Examine project concrete batching
and delivery requirements to properly
match all aspects of existing facility ca-
pacity with the specific project require-

Photo courtesy of Parsons Brinckerhoff.


ments and to identify any requirements
that may be beyond existing plant pro-
duction capacity. Seriously consider
the benefits of value engineering pro-
posals or a schedule acceleration, each
of which have the potential to dramati-
cally increase the chances of a success-
ful project. Concentrate on particular
Fig. 1. Warm-climate casting yard. in-house corporate skills or talents
that present a clear advantage over the
piping work to be installed within the to keep abreast of project changes and competition or capture value-added ad-
segments. All hardware and embed specifics, develop contractor contacts, vantages that may augment the overall
plate inserts should be laid out in the and know the competition. Most contrac- sales volume.
segment shop drawings provided by tors will welcome the precaster’s partici- Determine any concrete batch plant
others, but assume precast concrete pation and will provide answers to any component upgrades necessary to han-
plant installation of all these items ac- questions. Carefully determine a com- dle segmental batching requirements,
cording to plans and specifications. All prehensive scope of work to complete the including the adequacies of central
incoming material deliveries should project while addressing risk concerns. mixer size (production and volume),
be inspected and logged into a project cement silos, aggregate bins, and ad-
inventory system. Monitoring material mixture dispensing setups. Perform
Facility Assessment
usage and reorder points is usually the regional cost comparisons of concrete
precaster’s responsibility because com- An important aspect of a manufactur- materials that meet project specifications.
plete inventory control directly affects ing facility’s in-house self-examination
Form Enclosures
the production schedule. is to analyze existing plant and staff
strengths and weaknesses. A snapshot The type of casting enclosure re-
Specifications, Testing, and
perspective of the existing company quired for proper concrete curing
Certification
assets is vital to properly assess addi- depends on the climatic zone of the
Material specifications and testing tional action items for each department production site. In a warm or temper-
requirements of the concrete need to to undertake for this new product line ate climate, the precaster might use a
be closely reviewed. Typical require- to be competitive in the marketplace. temporary wood or fabric structure for
ments include petrographic analysis of If the concept stage is not brought to a protection during inclement weather to
the course and fine aggregates, testing thorough visualization by each depart- maintain productivity and enhance the
for alkali-silica reaction, determining ment, followed by a managerial cross- concrete curing process (Fig. 1). A cold
modulus of elasticity, and evaluating checking analysis to avoid omissions climate may require a more substantial
creep and shrinkage. These procedures and questionable areas, the overall pro- structure to protect the concrete and
will provide a critical analysis of the cess will be incomplete. ensure uninterrupted productivity. The
mixture proportions to ensure concrete If the existing facility is not large precaster may use an existing structure
durability and structural longevity. enough to handle a proposed project, or set up a pre-engineered metal build-
Certain tests will require completion the next step is locating a suitable man- ing to manage the anticipated adverse
by an AASHTO-certified lab at the ufacturing facility with an adequate climatic conditions.
precaster’s expense. casting yard area. Once the casting site To obtain a comprehensive picture
Assess any requisite casting per- is determined, the next step is to calcu- for each segmental form layout, the
sonnel certifications and experience late the maximum segments to be erect- approximate preliminary footprint will
needed, especially that of specialized ed per day and determine appropriate need to be known. For form assembly
labor for post-tensioning and grouting transport and site-delivery methods for width, consider the widest segment on
operations. Attend all pre-bid meetings the segments. If existing transport is the bridge and add 6 ft (1.8 m) to each

 PCI JOURNAL
side; this measurement should be close functioning properly, and local frost area relegated to the project based on
enough for a preliminary layout. Next, conditions do not have the potential to the parameters set by the contractor’s
form assembly length will be about adversely affect curing. A 12-in.-thick bid schedule. An aerial photograph
3.5 times the length of the longest seg- (305 mm) concrete floor slab in the plant showing the approximate storage area
ment—usually 10 ft (3 m). The form should be regarded as a minimal thick- (crosshatched) with estimated acreage
assembly overall height will be 3 ft to ness for segmental operations; driving is helpful.
5 ft (1 m to 1.5 m) plus the height of piles will be required to establish a
the tallest segment, with additional al- solid mechanical foundation. When a
Operational Planning
lowance for safety rails. Special limita- straddle crane will be extracting seg-
tions should be discussed with the form ments, the equipment foundations for Concrete Placement
manufacturers. the casting formwork should be iso- There are a number of choices for con-
One option for an existing precast lated from the lift crane travel lanes to crete placement in segmental production
concrete manufacturing building that is prevent adverse vibratory effects. depending on the material volume de-
too narrow in general plan is to consid- mands, project size, and expected budget
Segmental Unit Storage Capacity
er that the mandrel form can use rails (reimbursement). Options for concrete
to run outside the building. Another Figure 2 shows pier segments in placement range from a crane and con-
option is to have completed segments storage ready for shipment to the bridge crete bucket delivery to using a station-
moved along the rails to slide outside construction site. The assumed casting ary or truck-mounted concrete boom.
the building proper to be removed by schedule compared with erection de- Determining the most reasonable deliv-
crane or straddlecrane to the designat- livery dates will determine maximum ery method will depend on the number
ed plant storage areas. storage capacity requirements. Obvi- of forms, the total volume of concrete,
ously schedules change—due to ad- the needed height of forms versus clear
Casting Forms, Foundations,
verse weather or labor problems—and height to ceiling supports within the
and Layout
a significant buildup from an assumed building, and the proximity of the batch
Determine plant casting yard layout casting schedule could occur. Even plant and overall plant volume.
with an eye toward maximizing effi- environmental regulations protecting
Segment Geometry Control
cient workflow and minimizing equip- nesting birds at bridge sites have been
ment usage. Precise foundation design known to shut down construction. It A short-line casting procedure uses
for the casting formwork is crucial to is important, therefore, to consider at a stationary casting form to match cast
maintaining proper and consistent ge- what point the available storage yard succeeding segments against the previ-
ometry results in the completed seg- will be filled and whether overflow ous unit. The first segment is cast be-
ments. Review the plant site to ensure contingencies are established. tween bulkheads. Successive segments
consideration of these items: Concrete Another layout consideration pro- are cast, one at time, against the bulk-
slab thickness is adequate to support posal point is to clearly address the head on one end and the previous cast
production weights, site drainage is assumed maximum segment storage segment on the other end. A thorough

Photo courtesy of Parsons Brinckerhoff.

Fig. 2. Pier segments ready for shipment.

May–June 2006 
Labor Requirements

For preliminary estimating, start with


a direct labor force of a five-person
crew on forms and a four-person crew
on reinforcement jigs, and then adjust
the number of workers according to
the size and complexity of segments.
Discussions between management and
production can further identify the di-
rect and indirect personnel needed for
the project, including any specialized

Photo courtesy of Parsons Brinckerhoff.


equipment or tooling and integration
of existing machinery to meet project
material demands.
Site Delivery Requirements
A successful general contractor must
provide the maximum number of seg-
ments to be delivered per day to sus-
Fig. 3. Reinforcement jigs produce daily reinforcing steel cages. tain the construction schedule and the
overall erection schedule for bidding
Accelerated Curing purposes. For transport of precast con-
review of geometry control provisions crete segments, contact the appropriate
will lead to selection of appropriate A steam generator is typically used state and local authorities to determine
survey equipment followed by the erec- to accelerate the concrete curing pro- permitting authority for special haul-
tion of a survey tower layout. Keep the cess. A 1 million to 5 million BTU ing loads and permit requirements
survey tower layout simple, depending unit will service most casting yard and costs. Normally, the majority of
on the existing facility/site floorplan production output. The steam ma- bridge segment shipments will require
limitations. When setting up multiple chine manufacturer will provide a overweight permits, perhaps even ve-
forms, try to utilize each survey tower piping design to optimize the unit; hicle or police escort services. Axle
for maximum utility for more than one any variation on this design will loading diagrams will be needed to
form; this will reduce survey equipment drastically affect equipment perfor- specify trailer capacities, and several
needs and surveyor time restraints and mance. The steam generator units can transport dealers can usually provide
will speed up the casting cycle. be outfitted with a variety of options, technical assistance. A drop-deck or
from simple manual controls to a so- lowboy trailer configuration will often
Reinforcement Fabrication
phisticated computerized system with be necessary to lower a transport load’s
The Concrete Reinforcement Steel thermocouples at each form. Com- center of gravity. Never assume exist-
Institute’s (CRSI) Manual of Standard puterized steam systems can be pro- ing facility trailers will be adequate to
Practice is an excellent source of prac- grammed to start the unit after con- fulfill the requirements of segmental
tical information on reinforcing steel crete preset, provided that the correct transport without a complete analysis
standards.8 Figure 3 shows jigs pro- ramp up to optimum temperature is of project loads, sizes, and estimated
ducing the daily reinforcing steel cages set and that the ramp down setting the delivery cycles.
necessary to maintain the established unit for proper release strength is also
casting schedule. A consideration in calibrated. Carefully weigh the cost
Documentation
fabricating bent reinforcement for seg- benefits for each option—manual or
mental construction is whether to set automated—especially if the equip- and Process
up an in-house shop or hire a local re- ment capital outlay can be expensed
inforcement fabricator. Depending on over multiple projects. The multizone The complexities of undertaking a
the complexities of the segmental rein- systems can increase cost but add segmental unit operation demand a
forcing steel assembly, some caution is versatility and efficiency to the cast- thorough analysis of every start-up,
advisable to avoid casting delays when ing operation. A multizone system inventory, production, testing, QC,
contracting existing reinforcement fab- will separate each form into a sepa- and delivery task. The more complete
ricators. Their equipment is primarily rate concrete curing chamber using the analysis, the more clarity can be
set up to handle CRSI tolerances and a computerized value system, which achieved and expressed by the plant
not special bar bend tolerances typical is programmed to introduce enough team members. In this detailed and col-
of segmental design, which will have steam to provide the proper curing laborative effort, the precast concrete
to be specified. time and temperature controls. company energizes and empowers all

 PCI JOURNAL
department staff to focus the combined day following casting, a thorough seg- casting requirements of the plan and
expertise of each individual to ensure a ment review should take place. specifications. However, it is important
successful project. to remember that the manufacturer will
Post-Tensioning and Grouting
understandably design for form fabrica-
QC Manual Operations
tion ease for cost reduction, so the pre-
A concise and comprehensive QC The project specifications will de- caster must review the contract drawings
manual detailing every step of every tail the required concrete compressive from the perspective of labor analysis
process is a vital tool to underscore the strength to achieve prior to casting. To and in-house constructibility. Form
thoroughness of the precast concrete ensure a highly productive environ- needs are determined based on the tight-
plant and, moreover, to ensure the cli- ment, the concrete should be at post- est horizontal segment radius and maxi-
ent and owner’s representative that tensioning strength two to three days mum lengths of each type of segment.
every aspect of segmental production after casting. Prebagged grout mixture It is wise to analyze all of the form
has been carefully considered. If there suppliers can discuss equipment needs manufacturer proposals and make sure
is an existing QC manual, consider and technician availability for plant to look beyond the recommendations
augmenting the manual to include a training purposes. It should be noted of the lowest bidder. It’s very easy to
precast concrete segmental operation. that most project specifications reject base formwork purchase on price alone
prepackaged grout mixtures over six without considering an apples-to-ap-
Geometry Control Manual
months old. ples comparison to identify what the
A geometry control manual is typical- Specialized post-tensioning suppli- overall proposal includes and excludes.
ly provided by the contractor’s segmen- ers bidding the bridge project can dis- The initial form set up time and daily
tal engineer and will provide an excel- cuss the particular requirements of the operational costs are affected by labor
lent detailed account of daily operations, systems and can assist with employee costs and existing plant and equipment
including the geometry software pack- training. The supervisor responsible for needs to successfully transition or ac-
age procedures and hand calculation ex- grouting operations should have cur- commodate these new forms through
amples. Request a copy of a previously rent certification from the ASBI Grout- all the setup configurations. Efficient
used project manual for review and the ing Certification Training Program. form layout and plant set up are cru-
program software with some sample cial for smooth production cycles
data so the plant surveyor can become (Fig. 4). Make sure that a technical
Procurement Specifics
acquainted with program operation. representative will be at the plant for
Purchasing Segment Casting Forms form assembly. Normally, three to five
Repair Procedure Manual
Precasters forward contract drawings weeks is considered standard in the in-
Even if a repair procedure manual and specifications to segmental form- dustry. Maintain complete installation
is not mandatory for a given project, work manufacturers and discuss project overview responsibility, making sure
it is a highly recommended document requirements. The form manufacturer segmental form assembly ensures that
because it details numerous common will provide a design that satisfies the daily casting productivity is optimized.
plant repairs and lists any prior imple-
mentation approval required. Outlin-
ing a general agreement on a variety
of repair issues, materials, equipment,
and techniques will foster confidence
in the precast concrete team’s ability
to address typical industry concerns
regarding plant production, reliability,
and efficiency.
Prepour and Postpour Review
Prepour review consists of three main
inspections: raw material receiving and
inspection, reinforcement cage assem-
bly review when completed in the jigs,
Photo courtesy of Southern Forms.

and a thorough review of the segment


blockouts prior to casting. An initial
postpour review is conducted after
casting and prior to the match-casting
process. Postpour review involves a
structural inspection and a visual check
of the bulkhead face that will be used
to match cast the next segment. On the Fig. 4. Segmental casting machine setup before fixed bulkhead is installed.

May–June 2006 
Review component changes necessary daily adjustment procedures that will form prepping procedures between casts
to adapt form to anchor block modifi- be necessary to maintain the correct for productivity and safety concerns.
cations in a typical span. Review and geometry control. If the forms have to
Casting Forms—Miscellaneous
approve all form shop drawings prior adapt to different segment configura-
Items
to fabrication. tions, it is critical that the components
There are several review parameters are modularized to speed operations. Three to five ton (2700 to 4500 kg)
for analyzing the casting form propos- The hydraulic jacking system (pro- winch units with a 3/8 in. (9 mm) mini-
als. Segmental form limitations must vided by the form manufacturer) can mum cable diameter are typically used
be checked for the following: scupper be ordered with 110V or three-phase to move segments along the production
placement, maximum casting lengths, wiring, depending on the voltage speci- rail system. A pulley assembly, floor
acceptable bulkhead post-tensioned fied and the voltage that works best for mounted on the opposite side of the
blockout locations, tightest radius for plant operations. You must also calcu- rails, will allow movement in both di-
form constructibility, combined upper late any anticipated costs of integration rections using one winch. Air and elec-
and lower anchor block clearances, and into the plant system. trical winches are available depending
keyway layout interference. Questions that the precaster needs to on the plant operator’s particular pref-
ask include: Is there a thickened haunch erence. Of course, for extreme econo-
Typical Segment Forms (Nonpiers)
area, wing breaks, or scuppers pen- my, a forklift could be used to move
Figure 5 shows the mandrel or core etrating the segmental wingform? How the precast concrete segments, but the
form setup for daily casting operations. does each form manufacturer handle author does not recommend this equip-
The form manufacturer will provide in- these configuration changes, and will ment for segmental operations.
struction details for either a manual or the solutions or required modifications Within each segment, post-tensioning
hydraulic internal mandrel operation. affect casting labor costs? ducts will be required. Forming blad-
Discuss each option with the produc- Discussion of the mechanics in- ders—basically a long balloonlike liner—
tion supervisor to assess the casting volved in forming the segments will at the duct locations are inflated during
cycle implications and determine cost- provide a clear picture of any necessary casting to avoid migration of concrete
effective needs. changes to complete the project. into the voids and to maintain stability.
Also part of the review of the casting As an operational approach on seg-
Pier and Expansion Forms
form proposal is to look at simplicity ments, secondary external vibrators
and ease of daily wing setup and the The size and weight of the interior can be mounted on the lower third of
pallet’s smooth hydraulic operation, pier and expansion form components the form at the outside web area. The
which cannot be overestimated, in par- are important. Whether the interior com- aesthetic quality of the finished seg-
ticular, the rigidity of the fixed bulk- ponents are manually set or machine ments is greatly enhanced with exter-
head, as any movement in the form installed will dramatically affect labor nal vibrators, and this optional measure
will delay cycling time. Determine the costs and casting cycle times. Study all could save costs on remedial patching
after segments are cured. Of course,
all plant safety walkways, stairs, and
fencing installations must meet Occu-
pational Safety and Health Adminis-
tration (OSHA), state, and local work-
place regulations. A complete safety
walk-through and inspection of work
stations at regular intervals is mandat-
ed by OSHA.
Geometry Control
For geometric control of the seg-
ments, a one-second accuracy the-
odolite is used for centerline checks
and elevation readings. A builder’s
level capable of reading to an accu-
Photo courtesy of Southern Forms.

racy of 0.001 ft (0.3 mm) using an


invar rod is usually suitable. Review
project specifications thoroughly for
geometric tolerances. Monopod set-
ups for the survey instruments are
normally used with at least two per-
manent site benchmarks for instru-
Fig. 5. Mandrel or core form. ment calibration.

 PCI JOURNAL
Lifting Equipment Concerns Concrete Equipment
The standard choices for lifting Location, capacity, and accessories
segments at a precast concrete facil- of the concrete batch plant directly af-
ity are a straddle crane or crawler fect material quality. The quality and
crane. Both machines have accept- volume of concrete required for the
able capacity and maneuverability, bridge project will dictate the cement
but the characteristics of each ma- and aggregate storage capacity needs
chine have implications that bear on and the central concrete mixer capaci-
the entire operation. It is easier to ty. Local climate at the precast concrete
train an employee to operate a strad- manufacturing site will be the basis for
dle crane than a conventional crane. considering other items, such as an op-
In addition, the straddle crane can lift tional water chiller, ice machine, and

Photo courtesy of Parsons Brinckerhoff.


and transport the finished segments boiler components. Proper component
to the storage area, avoiding exces- choices and capacity, quality, and sup-
sive plant use of tractor-trailers. The ply of concrete material resources are
size of the plant storage yard and ex- the keys to producing a consistently
pertise of employees will determine high-quality product. The weight hop-
which piece of equipment is the best per will need certification for accuracy,
fit for production. Examine strong- and the plant will need to obtain Na-
back and rigging needs carefully for tional Ready-Mix Concrete Associa-
safe and efficient operation. A site- tion (NRMCA) Plant Certification. Fig. 6. The survey tower needs to be
specific safety manual and mandato- Concrete handling equipment can stable but can be a very simple design.
ry employee safety training will be vary depending on the overall com-
key components for any successful plexity of the project. A more lim- Additional Setup
precast concrete operation. ited operation can be handled with a Guidelines
When evaluating a straddle crane, straddle crane and a concrete bucket. Casting Forms Production Area
consider all equipment specifica- A larger operation may require ei-
tions, including lifting capacity, ther a stationary boom or boomtruck- Surveyors should lay out the entire
overall height, wheelbase, maxi- mounted concrete pump. The distance facility casting area, including the ac-
mum hook height, turning radius, between batch plant and the casting curate installation of brass plugs and
and travel speed. It is important to production area and the concrete itself wall targets—reference points for es-
remember that every aspect of cast- will determine concrete mixer truck re- tablishing form centerlines and fixed
ing, storage, and shipping operations quirements. bulkhead setup lines. Double check to
will be controlled by the capacity Concrete consolidation methods, ensure that delivered form components
and limitations of the segmental lift- such as internal and/or external vibra- arrive based on the required project
ing equipment selected. For material tors, should be used at every 18 in. (460 start-up needs. Depending on the seg-
handling, the use of a crane or fork- mm) concrete lift (maximum). A small ment and reinforcing assembly com-
lift depends on the project size and roller or air screed system to finish the plexity, each form setup should take
precaster preferences. Normally a deck surface is desirable. about three weeks.
forklift will be sufficient to handle Accelerated curing of the concrete is
Geometry-Controlled Equipment
most situations. Plant equipment most commonly handled with a steam
and Setup
selection will largely depend on the generator. Purchase of a steam genera-
demands of the daily tasks assigned tor is typically a long-lead item, and The plant’s survey equipment is
to each piece. the precaster is advised to obtain a firm positioned in a survey tower using
delivery schedule commitment. monopod setups. Each casting form is
Personnel
Successful segment handling can be outfitted with manual screws and/or hy-
Precast concrete manufacturing accomplished using several options: draulic jacks, which move the match-
plant personnel must utilize and fol- strand picking eyes, post-tensioned cast segment and casting form into cor-
low a safety manual and labor train- rod assemblies with holes formed near rect geometric position. Survey towers
ing schedule to ensure federal, state, the webs, and nylon slings wrapped need to be vertically and horizontally
and local compliance. The quantity under the wings. Each segment-han- stable but can be of very simple con-
of casting forms in operation will dling option has its advantages and struction, as shown in Figure 6.
add to the daily coordination diffi- associated labor costs, and final se-
Accelerated Curing
culties. Production efficiencies are lection will depend on the erection
enhanced by keeping activities in contractor’s equipment needs to some If propane is utilized in precast con-
close proximity, but a concentra- degree. It is imperative to carefully crete segmental operations, research
tion of work activities requires para- evaluate the handling system proposed the proper storage area distance from
mount safety vigilance. for bid purposes. the work zone mandated by OSHA

May–June 2006 
and perimeter safety requirements. span with each anchor block separately forcement assemblies and positioning
Sufficient total tank or tank farm ca- identified. in the forms. Most piers and expansion
pacity will depend on equipment Transporting Segments joints can be pre–tied up to the tops of
usage, local temperature extremes, and the webs, accelerating the casting pro-
anticipated hours of operation minus A casting manufacturing yard built cess, which is especially important in
minimum tank pressure capacity alongside the project will probably re- match-casting operations.10
before equipment stops are crucial quire a mobile segment hauler for site
Fabricating Post-Tensioning
operational concerns. delivery. For longer distances, custom
Blockouts
lowboy trailers designed with the par-
Post-Tensioning System
ticular local, federal, and state regula- Determine quantities of post-ten-
A good source of information is tions applicable to the project will be sioning anchorage blockouts or form
Acceptance Standards for Post-Ten- required. The precaster should consult assemblies that are not provided by the
sioning Systems.9 The contractor will the proper authorities to review the in- form manufacturer. These items can be
choose a post-tensioning supplier for tended travel route, permitting process, fabricated with wood or steel depend-
project components. Review the post- and required escorts. Once the travel ing on the plant production manager’s
tensioning systems being considered route has been determined, the neces- preference. Generally, the symmetry
because unique details could add sig- sary en route bridge survey data will of post-tensioning design will utilize
nificant specialized labor and equip- need to be checked for minimum clear- a given series of similar in repetition.
ment allocation costs. The post-ten- ance heights. Making an in-house reference mark for
sioning supplier will supply the strand, each setup could speed fabrication by
Reinforcement Jigs
chucks, jaws, and certain bursting having the fabrication shop staff begin
stress reinforcement. The precaster has Reinforcing steel bar assemblies can an inventory of typical blockouts.11
to determine which raw materials are to be made of wood or steel, depending
Transverse Post Tensioning and
be included in the supplier’s bid price. on a variety of factors. The author rec-
Grouting
ommends a minimum of two jigs for
Reinforcement Fabrication
each typical casting form. Each typical The majority of transverse post-ten-
Detailed procedures are necessary segment and reinforcement jig assem- sioning and grouting operations will
if reinforcement coatings are required, bly must operate in a simple, efficient be completed at the precast concrete
especially if coating processes require manner. These jigs, however, must facility. PTI Specification for Grout-
adapting existing plant reinforcement adapt to the versatility and variability of ing of Post-Tensioning Structures is
fabrication equipment. Consider the the casting forms that are served. Prior an excellent introduction manual
different reinforcement ordering choic- to fabrication, analyze every segment to become acquainted with present
es available in the market, and order configuration requirement to ensure industry standards to eliminate steel
steel reinforcing bars by segment or by smooth transitions between the rein- corrosion. 12

Photo courtesy of Parsons Brinckerhoff.

Fig. 7. Casting form prepped prior to placement of the reinforcing steel cage.

10 PCI JOURNAL
Photo courtesy of Parsons Brinckerhoff.
Fig. 8. Precise reinforcement and post-tensioning layout requirements produce excellent quality.

Grout pumps have become increas- Typical Casting Form Cycle


ingly more complex in recent years
to ensure proper mixing. Determine The following is a brief list of tasks 10. Complete any anchor block
the precise project requirements be- to be performed during an average configuration changes to the
cause most states will require a high- casting cycle; upon closer inspection, mandrel;
speed or colloidal grout mixer/pump the activities that can be completed si- 11. Complete QC reinforcement
setup. Adjust the precast concrete bid multaneously will be apparent: cage inspection and place the
numbers accordingly because high- 1. Quality control staff breaks con- cage into the casting form;
speed equipment is more expensive crete cylinders from previous cast; 12. Winch the match-cast segment
than regular paddle mixers. A few 2. Uncover segment; into place;
states still allow cement and water 3. Surveyor performs after-cast 13. Surveyor performs preliminary
mix designs, but today most owners survey; survey, and the form is secured
are specifying prepackaged grout. 4. Dismantle mandrel and lower for casting;
Depending on a precast concrete form wings for stripping com- 14. Crew preps the reinforcement
plant’s regional conditions, a grout pleted segment; cage, adds utility embeds,
with thixotropic qualities might be a 5. Winch mandrel from casting and completes post-tensioning
good choice. form; components; Figure 8 shows
Many suppliers produce mono- 6. Winch match-cast segment from the precise reinforcement and
strand jacks for post-tensioning, but wet-cast segment and remove post-tensioning layout require-
prior to pricing this item, check with from area; ments to produce excellent
the contractor about whether the 7. Winch wet-cast segment into quality;
post-tensioning jacks and appropri- match-cast position; 15. Surveyor completes final
ate calibration records are provided 8. Perform QC visual check survey and releases form
by the post-tensioning material sup- of completed segment and for casting;
plier. complete postpour report on 16. QC staff reviews the wet-cast
the previous day’s match-cast segment and releases for casting;
Final Segment Prep
segment; 17. Concrete is received and tested;
The segment’s match-cast joints 9. Clean and prep the casting form 18. Segment is cast and finished;
will require a light sandblast finish and mandrel for casting; Figure 19. Cover segment and start
prior to leaving the casting yard for 7 shows a casting form being concrete preset; and
erection to ensure epoxy adhesion un- cleaned prior to placement of the 20. After preset, begin the acceler-
less the project uses a dry-joint system. reinforcement cage; ated curing process.

May–June 2006 11
Bidding Process
Contractor Relations
Determine the proper scope of work
and risk assessment on each project.
Pay special attention to inclusions and
exclusions within the precast concrete
bid, especially because construction
updates during the bidding process
will complicate matters. Negotiate an
acceptable mobilization amount to
cover casting production facility setup,
equipment upgrades, and trucking op-
tions (Fig. 9), and clearly define the

Photo courtesy of Parsons Brinckerhoff.


payment schedule criteria. Discuss
any contract drawing modifications
required to ensure overall quality and
productivity enhancements. Notify the
contractor of strategic milestones for
material deliveries to avoid casting de-
lays.
The contractor should verify that all
embeds associated with the contract Fig. 9. Segment loaded on lowboy trailer ready for delivery.
drawings are present on the shop draw-
ings, including electrical embeds and
fire-retardant fiberglass sleeves, scup- and methods” are present on the shop are obtained before shop drawing sub-
pers, standpipes, and anchors for me- drawings, including picking devices, mittals: adjacent closure pour adjust-
chanical items. The contractor should erection sleeves, top slab access, and ments, electrical pass-through conduit
also verify that all embeds required openings. Ensure that the following as- alignment, column and pintle place-
by the contract’s “construction means built elevation and detail verifications ments, span length adjustments, and

New precast concrete segmental contract


The latest PCI-Certified Producer to enter precast concrete segmental ment maintenance facilities, PCI-Certified QC personnel and concrete
bridge casting is Bethlehem Construction Co. Inc. (BCI) in Cashmere, lab equipment, and the use of the BCI plant-established utilities sys-
Wash. BCI will fabricate over 2200 precast concrete segments for Sound tems for steam, electricity, and compressed air were strong benefits
Transit Authority’s Central Link Light Rail Project in Seattle, Wash. with value and reduced cost to the general contractor and owner over
The decision to enter this specialized precast concrete market was setting up a greenfield segmental casting site near the job. Precast
made after BCI was approached by PCL Construction Services Inc. concrete crews from BCI would staff the nontechnical production
(PCL) in Bellevue, Wash., about the project. The company had pre- jobs, and PCL technical experts in precast concrete segmental bridge
viously supplied precast concrete beams, columns, girders, stadia, construction would supervise the technical aspects, engineering, ge-
double tees, hollow-core, and precast concrete wall panel products to ometry, casting, planning, and scheduling.
PCL on over a dozen other successful projects, and PCL Civil Divi- The BCI plant upgrades to prepare for the project included a batch
sion was an experienced segmental bridge constructor. The concept plant upgrade to allow concrete production to meet the needs of the
of using the combined strengths of each firm to bring an advantage to project when combined with other BCI precast concrete project vol-
the project owner was developed over a period of several months prior umes, a yard reorganization to dedicate the necessary area for seg-
to the bid date. mental reinforcement jigs, segmental casting forms and handling
Bethlehem’s PCI-Certified plant brought the benefits of an estab- areas, and the acquisition of additional storage area for segments
lished precast concrete facility and precast concrete labor force, in- waiting to be shipped (Fig. 10).
cluding a concrete batch plant less than 200 yards from the casting From a PCI-Certified Producer’s perspective, this strategic partner-
area, thereby ensuring a dedicated source of concrete with a level of ship approach was an ideal situation to manage the risks associated
control over the high-strength concrete production and delivery. This with the new product that otherwise would not have been possible on
would not normally be possible from commercial concrete ready-mix a project of this scale. From the general contractors and owners’ per-
plants. The use of BCI’s existing casting beds for form and reinforce- spective, it allowed a lower bid price and cost savings to the project
ment jig setup, existing equipment, crane runways, shop and equip- along with the many others benefits noted.

12 PCI JOURNAL
elevation and layout changes between
projects. Inquire if the contractor will
check post-tensioning jacking clear-
ance at all interior anchorages, includ-
ing longitudinal and future tendons.
Managerial Assessment
After conducting a thorough review
of the precast concrete plant and equip-
ment, scrutinize the existing manage-
rial and production team expertise to
handle a segmental operation. Deter-

Photo courtesy of Parsons Brinckerhoff.


mine if an outside consultant should
be contracted to provide the needed
expertise to properly plan the product
line expansion. While a professional
segmental engineering consultant is an
added cost, remember that costly omis-
sions or a slow start-up could cripple
operations.
Final Estimate Fig. 11. Span-by-span precast concrete segmental construction using a launching gantry.

Every precast concrete plant depart-


Post-Award
ment must provide input for procure- strategic planning, the greater chance
ment needs, process, and procedures. After being awarded the segmental of a successful venture.
This input will include not only indi- contract, immediately open dialog with
vidual cost items but a thorough pre- plant staff on enhancements and value
Conclusions
sentation and assessment of problemat- engineering to ease forming restraints
ic areas that have the potential to cause and speed productivity. The more em- In some respects, gearing up to han-
delays and cost overruns. phasis placed on up-front analysis and dle precast concrete segmental bridge

by Bob Connelly, Area Manager/Project Manager, Bethlehem Construction, Cashmere, Wash.

Photo courtesy of Parsons Brinckerhoff.

Fig. 10. Bethlehem Construction batch plant additions to increase production.

May–June 2006 13
Photo courtesy of Parsons Brinckerhoff.
Fig. 12. Precast segment erection using balanced cantilever construction.

production is just another product line References and Construction of Segmental


to augment a precaster’s bottom line Concrete Bridges. Washington,
(Fig. 11). It is important to bear in 1. Rosignoli, M. 2001. Deck Segmen- DC: AASHTO.
mind, however, that segmental tech- tation and Yard Organization for 5. Bridge Design Manual Steer-
nology is still evolving in both design Launched Bridges. Concrete Inter- ing Committee. Bridge Design
and construction/erection techniques national (February): pp. 65–73. Manual. MNL-133. Chicago,
(Fig. 12). There are at present a number 2. Moreton, A., and A. Janssen. IL: Precast/Prestressed Concrete
of engineering and erection issues that 1995. Casting Box Girder Seg- Institute.
need refinement, and this potential for ments. Concrete Construction 6. Palmer, Arthur M. 2004. Contrac-
technological advancement can lead to Magazine (January 1). tor Checklist: Precast Yards. ACI
a strong competitive advantage for a 3. Barker, J. 1981. Segmental Journal, V. 26, No. 10:
precaster qualified to cast segments on Bridges: The Best in the Business. pp. 45–48.
regional transportation projects. Concrete Construction Magazine 7. American Segmental Bridge Insti-
Looking to increase future market (February 1). tute (ASBI). 2005. Construction
share, the precaster is well advised to 4. American Association of State Practices Handbook for Segmen-
consider upgrading facilities to manu- Highway and Transportation Offi- tal Concrete Bridges. Phoenix,
facture precast concrete segments as a cials (AASHTO). Standard Speci- AZ: ASBI.
propitious move to ensure a foothold fications for Highway Bridges and 8. Concrete Reinforcement Steel
toward incorporating future complex Guide Specifications for Design Institute (CRSI). Manual of Stan-
product lines beyond segmental bridg- dard Practice. Schaumburg, IL:
es. Understanding the quality initiatives CRSI.
This article is presented for infor-
needed and geometry control aspects of 9. Post-Tensioning Institute (PTI).
segmental construction is an ideal busi- 1998. Acceptance Standards for
mational use only as an introduction
ness opportunity to comprehensively Post-Tensioning Systems. Phoe-
prepare the precaster in competition nix, AZ: PTI.
to casting segmental bridge compo-
for the pending high-speed rail projects 10. Rosignoli, M. 1997. Evolution of
and specialty bridges. Precasters are ad- nents. The intent is to promote an a Technique, Incremental Bridge
vised to promote AASHTO/ASBI/PCI Launching. Concrete Internation-
precast concrete segmental standards understanding of casting yard con- al (February).
in their respective regions because stan- 11. Palmer, Arthur. 2003. Precast
dardization will help ensure that pur- siderations and does not cover all Segmental Casting Yards: Past,
chased segmental casting machines will Present And Future. PB Network,
be adaptable for future projects. ASBI situations or particular project spec- No. 57 (February).
is an excellent resource for developing 12. PTI. 2003. Specification for
contacts in the precast concrete segmen- ifications and plan requirements. Grouting of Post-Tensioning
tal industry. Structures. Phoenix, AZ: PTI.

14 PCI JOURNAL
May–June 2006 15
16 PCI JOURNAL

You might also like