Schedule of Lighting Pole Installation/Gumti 2nd Brid

Particular 16 May '19 17 May '19 18 May '19 19 May '19

Cable Installation 90% 100%

Cable Insulation and Continuity Test Preparation of Documents Inspection

Scaffolding Making S47-S36 S35-S26 S26-S16 S15-S01

Lighting Pole Inspection All

Nut Leveling S47 to S28 S27-S-01 Inspection

Lighting Pole Repair Works All

Lighting Pole Wiring S47 to S28

Lighting Pole Mobilize at Location S47 to S28

Lighting Pole Installation S47 to S38 S37 to S26 S27-S16


Inspection &
Grouting S47 to S38
S37 to S26
allation/Gumti 2nd Bridge
20 May '19 21 May '19 22 May '19 23 May '19 24 May '19

F
i
n
a
l

I
IRI TEST & INSPECTION OF n
SUPERSTRUCTURE WHOLE s
BRIDGE p
e
c
t
i
o
n
S15-S01
Inspection & Inspection &
S25 to S16 S15 to S01

Date: 15 May 2019


Schedule of Lighting Pole Installation/Gumti 2
Particular 16 May '19 17 May '19 18 May '19

Cable Installation 90% 100%

Cable Insulation and Continuity Test Preparation of Documents

Scaffolding Making S47-S33=15Nos S32-S16=17Nos S15-S01=15Nos

Lighting Pole Inspection All

Nut Leveling S47 to S33 Inspection S27-S-01

Lighting Pole Repair Works All

Lighting Pole Mobilize at Location S47-S33=15Nos S32-S16=17Nos

Lighting Pole Wiring S47-S33=15Nos S32-S16=17Nos

Lighting Pole Installation S47-S33=15Nos S32-S16=17Nos

Grouting S47-S33=15Nos
ghting Pole Installation/Gumti 2nd Bridge
19 May '19 20 May '19 21 May '19 22 May '19 23 May '19 24 May '19

Inspection F
i
n
a
l

I
Inspection n
IRI TEST & INSPECTION OF
s
SUPERSTRUCTURE WHOLE BRIDGE
p
e
c
S15-S01=15Nos t
i
S15-S01=15Nos o
n
S15-S01=15Nos
Inspection & S32- Inspection & S15-
S16=17Nos S01=15Nos

Date: 16 May 2019


Schedule of Lighting Pole Installation/Gumti 2nd Bridge
Particular 10 June '19 11 June '19 12 June '19 13 June '19 14 June '19 15 June '19 16 June '19 17 June '19 18 June '19

Cable Installation 100% Done

Cable Insulation and Continuity Test 100% Done

Remaining 1 Arm of Double Arming


N47-N35=11Nos N36-N26=11Nos
Lighting Pole from P9 to A2

Scaffolding Making N25-N14=12Nos N13-N1=14Nos

Lighting Pole Inspection 100% Done

Nut Leveling N25-N14=12Nos N13-N1=14Nos Inspection

Lighting Pole Repair Works 100% Done

Cutting and Preparing Cable for wiring


N25-N14=12Nos N13-N1=14Nos 40% 50%
Pole.

Preparing Bakelite Plate Already 30% Done 30% 40%

Chipping area cleaning on Foundation of


Already 50% Done 25% 25%
LP

Lighting Pole Mobilize at Location N25-N14=12Nos N13-N1=14Nos

Lighting Pole Wiring N25-N14=12Nos N13-N1=14Nos

Lighting Pole Installation N25-N14=12Nos N13-N1=14Nos

Formwork for Grouting N25-N14=12Nos N13-N1=14Nos

Grouting N25-N01=25Nos

Date: 30 May 2019


Schedule of Lighting Pole Installation/Gumti 2nd Bridge
Particular 10 June '19 11 June '19 12 June '19 13 June '19 14 June '19 15 June '19 16 June '19 17 June '19 18 June '19

Cable Installation 100% Done

Cable Insulation and Continuity Test 100% Done

Remaining 1 Arm of Double Arming


N47-N35=11Nos N36-N26=11Nos
Lighting Pole from P9 to A2

Scaffolding Making Upstram Side 100% Done

Lighting Pole Inspection 100% Done

Nut Leveling N25-N14=12Nos N13-N1=14Nos Inspection

Lighting Pole Repair Works 100% Done

Cutting and Preparing Cable for wiring


N25-N14=12Nos N13-N1=14Nos 40% 50%
Pole.

Preparing Bakelite Plate Already 30% Done 30% 40%

Chipping area cleaning on Foundation of


Already 50% Done 25% 25%
LP

Lighting Pole Mobilize at Location N25-N14=12Nos N13-N1=14Nos

Lighting Pole Wiring N25-N14=12Nos N13-N1=14Nos

Lighting Pole Installation N25-N14=12Nos N13-N1=14Nos

Formwork for Grouting N25-N14=12Nos N13-N1=14Nos

Grouting N25-N01=25Nos

Date: 30 May 2019