You are on page 1of 2

BILL OF QUANTITIES

DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST

I. MOBILIZATION 1 lot 30,000 30,000

II EXCAVATION 1 lot 20,000 20,000

III CONCRETE WORKS and MASONRY WORKS 440,866.13


Portland Cement 416 bag 262 108,992.00
Sand 34 cu.m. 1432 48,688.00
Gravel or Crushed Stone 14 cu.m. 1417 19,838.00
Concrete Hollow Blocks
100 x 200 x 400 403 piece 12 4,836.00
150 x 200 x 400 2011 piece 18 36,198.00
Reinforcing Steel Bars, Deformed
10mm x 6.00 meters 976.5945 kg 39 38,087.19
16mm x 6.00 meters 2595.0435 kg 39 101,206.70

Forms, Scafffolding and Staging 1 lot 42941.5058 42,941.51


Consumables 1 lot 40078.7388 40,078.74

IV PLUMBING WORKS 63,307.20


Floor Drain, Chrome Plated, 100mm x 100mm 2 piece 280 560.00
Gate Valve 1 piece 480 480.00
Water Meter 1 piece 1288 1,288.00
Water Closet 2 piece 7000 14,000.00
Lavatory 2 piece 2000 4,000.00
Faucet 1 piece 900 900.00
Showerheads 2 piece 600 1,200.00

Pipes
75mm dia. X 3m uPVC Sanitary Pipe 7 piece 420 2,940.00
150mm dia. X 3m uPVC Sanitary Pipe 4 piece 1200 4,800.00
1/2" dia. X 3m PPR Cold Potable Pipe 15 piece 396 5,940.00
2500mm dia. X 1m RC Pipe 24 piece 639.5 15,348.00

Coupling
150mm dia. uPVC SanitaryCoupling 4 piece 100 400.00
1/2"mm dia. PPR Waterline Coupling 15 piece 60 900.00
Consumables 1 lot 10551.2 10,551.20

V ELECTRICAL WORKS 67,565.95


Switch
Single gang Switch 8 piece 105 840.00
Two Gang Switch 6 piece 150 900.00
Three Gang Switch 1 piece 190 190.00
Convinience Outlet 31 piece 144 4,464.00
Weather Proof Convinience Outlet 9 piece 211 1,899.00
Range ConvinienceOutlet 1 piece 230 230.00
Oven Convinience Outlet 1 piece 230 230.00
Refrigirator Convinience Outlet 1 piece 230 230.00
Airconditioning Outlet 3 piece 150 450.00
Recessed Mounted Pinlight w/ 12w LED Light 45 piece 396 17,820.00
Keyless Porcelein receptacle w/ 20w LED center light 2 piece 0.00
Pendant Light 3 piece 0.00
Panel Box 1 piece 30000 30,000.00
Electrical Tape 10 piece 45 450.00
Junction box 42 piece 25 1,050.00
Corrugated Plastic conduit 1 lot 8812.95 8,812.95
15mm RSC Philflex Wires 1 lot 16891.4875 16,891.49
VI ROOFING 172,127.92
Pre-painted Metal Roofing Sheet GA 24 Longspan 195 sq.m. 506.11 98,691.45
C-Purlins 2" x 4" x 1.50mm 58 pcs 415 24,070.00
Channel 2" x 6" x 3.00mm 24 pcs 1190 28,560.00
Ordinary Gutter, GA 24 34 ln.m 151.72 5,158.48
Consumables 1 lot 15647.993 15,647.99

VII FINISHING 123,210.00


Ceramic Tiles, 600mm x 600mm 368 piece 80 29,440.00
Tile Adhesive 12 bag 250 3,000.00
White Cement Filler 67 bag 120 8,040.00
Paint
Concrete Neutralizer 5 gal 422 2,110.00
Primer 42 gal 635 26,670.00
Latex - Semi Gloss 83 gal 650 53,950.00
Consumables 1 lot 8273 8,273.00

VIII CARPENTRY WORKS 50,820.00


Ceiling
Gypsum board 55 sheet 528 29,040.00
Metal furring 1 lot 21780 21,780.00

iX SCHEDULES OF DOORS AND WINDOWS 141,000.00


Windows
Window 1 7 set 5000 35,000.00
Window 2 2 set 3000 6,000.00
Doors
Door 1 10 set 10000 100,000.00
Sliding Door 2 set 20000 40,000.00
Flush Door 2 set 2500 5,000.00

X MISCELLANEOUS ITEMS 105,889.72


Miscellaneous Items will cover Items not listed above
XI DEMOBILIZATION 1 lot 30,000 30,000

A. ESTIMATED COST OF MATERIAL 1,244,786.92


I. MOBILIZATION 30,000.00
II. EXCAVATION 20,000.00
III. CONCRETE WORKS and MASONRY WORKS 440,866.13
IV. PLUMBING WORKS 63,307.20
V. ELECTRICAL WORKS 67,565.95
VI. ROOFING 172,127.92
VII. FINISHING 123,210.00
VIII. CARPENTRY WORKS 50,820.00
IX. SCHEDULES OF DOORS AND WINDOWS 141,000.00
X. MISCELLANEOUS ITEMS 105,889.72
XI DEMOBILIZATION 30,000.00

B. ESTIMATED COST OF LABOR 497,914.77

C. ESTIMATED EXPENSES FOR CONTINGENCIES 124,478.69

ESTIMATED TOTAL DIRECT COST 1,867,180.38

ESTIMATED TOTAL COST 1,867,180.38

You might also like