You are on page 1of 23

KARNATAKA POWER TRANSMISSION CORPORATION LIMITED

Estimate No:- Date:


Estimate for Replacement of 1x10MVA Power Transformer-2 by 1x20MVA Power
Transformer at 110/11KV Sub-station Mayasandra in Turuvekere Taluk, Tiptur
nodal center in K.B.Cross division,Tumakuru circle.
Main Abstract
Sl No. Particulars

Part-A:Capital work Replacement of


1x10MVA,110/11KVPower Transformer-2 by
1 1x20MVA 110/11KV Power Transformer at
110/11KV Sub-station Honnavalli in C.N.Halli nodal
center in K.B.Cross division,Tumakuru circle.

Part-B:Revenue work Dismantling of existing 1x10


MVA 110/11kV Power Transformer-2 and allied
2
equipments in 110/11KV Substation Honnavalli in
C.N.Hally Nodal center, K.B.Cross Division.

Total DPR (Part-A+Part-B)

( Rupees two crore thirty four lakhs forty three thousand only)

Assistant Engineer (Ele) Asst.Executive Engineer(E)


110/11KV MUSS Nodal officer,110/11KV MUSS
Mayasandra Tiptur

Executive Engineer (Ele)


220KV R/S Division
KPTCL, K.B.Cross
CORPORATION LIMITED
Date:
Transformer-2 by 1x20MVA Power
dra in Turuvekere Taluk, Tiptur
n,Tumakuru circle.

Amount (in Rs.Lakhs)

233.50

0.93

234.43

rty three thousand only)

st.Executive Engineer(E)
dal officer,110/11KV MUSS
Tiptur
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED
Estimate No:- Date:-
Estimate for Replacement of 1x10MVA Power Transformer-2 by 1x20MVA Power
Transformer at 110/11KV Sub-station Mayasandra in Turuvekere Taluk, Tiptur nodal
center in K.B.Cross division,Tumakuru circle.
ABSTRACT-I

Sl No. Particulars Amount (in Rs)

1 Material cost including GST 19150000

2 Spares at 3 % on material cost [3% on Sl.No.1] 574500

3 Erection/Labour charges 280000

4 Applicable GST on Errection/Labour charges(on Sl.No.3)@18% 50400

5 Testing and commissioning charges 70000

Applicable GST on Testing and commissioning charges(on


6 12600
Sl.No.5)@18%

Total of material and Errection/labour charges {sum of


7 20137500.00
Sl.No.1 to 6 }

Cost of Civil Engineering works based on current KPWD SR


8 650000.00
with GST 18%

Total work cost (material cost+erection+Testing


9 charges+civil Engg.cost) (Sum of Sl.No 7 & 8)= Amount put 20787500
to tender

Establishment charges at 5% on material cost and Errection


10 1006875
charges(on Sl.No.7)

Contingencies at 3% on[ Material cost + Errection/Labour


11 charges+establishment charges] [on Sl.No.7&10] 634331

Performance guarantee & loss of interest on margin money for


12 20787
Bank Guarantee @ 0.1 % on works cost (Sl.No 9)

13 Interest during construction @4% on (Sl.No 9+10+11+12) 871980

Total estimated cost for comparision purpose [ Sum of


14 23321473
Sl.No. 9to 13]

Statutory charges for payment to civic bodies,Electrical


15 28527
inspectorate charges

16 Total estimated cost of the work (14+15) 23350000

( Rupees Two crore thirty five Lakhs fifty thousand only)


Assistant Engineer [Ele], Assistant Executive Engineer
110/11 KV S/s, Nodal Centre 110/11 KV S/S
Maysandra Tiptur

Executive Engineer [Ele],


220/110/11 KV R/s,
KPTCL, K B Cross.
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED

Estimate No:- MYSR-29 Date:-01/07/2020

Estimate for Replacement of 1x10MVA Power Transformer-2 by 1x20MVA Power Transformer at 110/11KV Sub-station Mayasandra in
Turuvekere Taluk, Tiptur nodal center in K.B.Cross division,Tumakuru circle.

1. Part- A : Supply of Material ,Erection and Commissioning

Wiring,Testing and
Supply of Material Erection charges
Sl No. Name of the Equipment/Materials Unit Qty Comissioning chareges

Unit Rate Amount Unit Rate Amount Unit Rate Amount

A1 POWER TRANSFORMER :

Power Transformer: 20MVA,110/33/11KV Delta/star,


Dyn11, 3Ph, 50Hz, Core type winding with OLTC,
RTCC Panel, etc., complete filled with transil oil with
10% spare oil with Terminal connectors suitable for
Drake ACSR on 110KV side and Drake ACSR/2 Nos of
100x6mm copper flat for each phase from LV side of
1 No. 1 14644000 14644000 166297 166297 57756 57756
transformer to cable at 11KV cable terminating structure
with suitable support insulator on LV side of
transformer and 2 Nos of 100mmx6mm copper flats
from neutral terminal to earth mat through NCT along
with necessary support pin insulators. Erection as per
annexure

A2 Nitrogen Fire Extinguisher

Nitrogen Fire Extinguisher system for 20MVA


1 No 1 776057 776057
transformer

A2 11KV CT and NCT

11 KV CT's 1200-800/1-1-1 A (for 500 MVA SWG) for


1 Nos 3 20000 60000 537.67 1613 3849.67 11549
incomer breaker

2 11KV NCT ratio 1200-800/1-1-1A No 1 28000.00 28000.00 467 467 73 73

1.1KV class PVC insulated Copper Control cable


A6 with lugs/ferrules/glands as per technical
specifications

1 19 Core 2.5 Sqmm Mts 330 347 114510 11 3630

2 4 Core 6 Sqmm Mts 230 163 37490 11 2530

3 2 X 6 Sq.mm Mtrs 50 102.00 5100 11 550

4 4 x 2.5 Sq.mm Mtrs 160 94.00 15040 11 1760


5 2 X 2.5 Sq.mm Mtrs 259 62.00 16058 11 2849
A7 Mounting structure
1
11kV NCT's(0.142 MT as per structure) No/MT 0.15 12460.50 12460.50 2032 302.97

2 11kV cable terminating structure for LV side of


No/MT 0.14 6054.75 12109.50 2032 294.44
110/11kV transformer( 0.069MT) for 2 Nos

A8 11kV 1000Sqmm UG Cable & termination kits

1 11 kv class 1*1000 sqmm UG cable XLPE Mtr 240 810.20 194448.00 54 12960
Heat srinkable type cable termination kits suitable for
2 1*1000sqmm XLPE CABLE (INDOOR TYPE) Nos 4 2910.00 11640.00

Heat srinkable type cable termination kits suitable for


3 1*1000sqmm XLPE CABLE ( OUTDOOR TYPE) Nos 4 3000.00 12000.00

4 Copper flats for transformer secondary 100x10mm size Nos 4 41507.00 166028.00
2.5m length ( Market rate )
Bi metallic plates 150x150x2mm for LV terminals of
5 Nos 10 900.00 9000.00
transformer/NCT connections.(As per market rate)

6 11 kV Pin Insulator Shell with pin as per BESCOM SR Nos 6 105.00 630.00

Supplying & fixing 2 Part of wooden clamps with bolts


7 & nuts suitable for S.C 1000 Sq.mm 11KV UG cable as set 3 600.00 1800.00
per specification

A9 Grounding of equipment
Providing cast iron pipe of 100mm ID 13mm thickness
2.75m long with two part GI flat 50X6mm clamp
1 welded around the pipe etc.,including the cost Set 2 10988 21976
excavation(All materials supplied by the contractor.)

Grounding of Equipment with 50X6mm GI flat and


2 connecting equipement to the earthmat /ground pit Rmtr 60 226 13560
including all connected works.

Supplying and fixing 450mm diax450mm height 1.5" to


3 No 2 1012 2024
2" Hume pipe for earth pits

4 Earthing name plates No 2 400 800

A9 Sub-Total 15280314.00 231613.41 69378.00

F & I at 6% on SR rates 916818.84

GST applicable
2915483.9112
Extra allowance over basic labour rates for station and
34742.01
line works to take care of contractors overheads at 15%

Scattered area mobilisation allowance over the basic


11580.67
labour rates at 5 %

Miscellaneous & round off L/s 37383.25 2063.91 622.00

A12 19150000.00 280000.00 70000

Assistant Engineer(E) Assistant Executive Engineer(E)

110/11KV MUSS, Nodal Officer,110/11KV MUSS

KPTCL,Mayasandra Tiptur

Executive Engineer, [Ele.]

KPTCL TL & SS Division

K.B Cross
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED
Estimate No. :-
Estimate for Replacement of 1x10MVA Power Transformer-2 by 1x20MVA Power
Transformer at 110/11KV Sub-station Mayasandra in Turuvekere Taluk, Tiptur
nodal center in K.B.Cross division,Tumakuru circle.
Annexure-1 : Erection of Power Transformer
Moving transformer into the Plinth. For a distance of 20 MT /
1 52/ 23 48.00
meters as per site condition with wt 52 MT Mts

Assembly of transformer parts like bushings, radiators,


2 MT 20 975.00
Conservator tank etc

Filling oil to the power Tr. conservator and radiators (for


3 maintenance purpose only) For 20 MVA Tr 10% oil only and Ltr 1984 2.44
filtering the same.KPTCL SR-2019

Filtering of the oil using filter machine of the contracor , to


3 Ltr 15,066 4.88
bring the the insulation value to I.E specifications.

Wiring of transformer marshalling box , Bucholtz relay ,


4 fixing thermometer , OLTC wiring upto control panel and Nos 1 11026.00
assisting in commissioning by RT/MT/Firm engineers.

Total Rs

Annexure-2 : Decommissioning for 10 MVA Power transformer


Sl
Particulars Unit Qnty Rate
No.
MT /
1 Moving transformer into the Plinth to loading point , Mts
37.6/16 48.00

Dismantling transformer & associated fixture parts


2 MT 8 975.00
like bushings, radiators and accessories etc

Draining out oil from the Power Transformer &


collecting the oil in barrels (supplied by KPTCL)
shifting barrels to safe place (in the station premises
3 Ltr 1,368 1.05
only) with proper tightness of cork/lid to avoid entry of
moisture. ( Draining of oil from conservator tank ,
radiator , transformer )

Releasing of transformer wiring( 75 % of errection)


4 Nos 1 8269.50
Page no 120, (including RTCC,OLTC,MB)

Total Rs

Asst. Engineer(E) Asst. Executive Engineer(E)


110/11KV MUSS,KPTCL 110/11KV MUSS Nodal Officer
Maysandra Tiptur
Executive Engineer, [Ele.]
KPTCL TL & SS Division
K.B Cross
IMITED

1x20MVA Power
e Taluk, Tiptur
e.

57,408.00

19,500.00

4840.96

73,522.08

11,026.00

166,297

former

Amount

28,876.80

7,800.00

1,436.40

8,269.50

46,382.70

tive Engineer(E)
USS Nodal Officer
iptur
Certificate :- Certified that I have personally visited the spot and prepared the estimate by using MWSR
2019 with GST for most economical and safe way of execution of work.

REPORT:- This estimate is prepared for an amount of Rs 2,34,43,000/-( Rupees two crore thirty
fourlakhs forty three thousand only) for augmentation of 110/11KV,10 MVA Power transformer-2 by 20
MVA at 110/11 KV Sub-station Mayasandra in Tiptur nodal center.

The Existing Power Transformers at 110/11KV Mayasandra sub station is over loaded.The supply
mainly feeding to Government hospital, villages , water supply, lightings & IP set installations. The load is
increasing day by day.
As the existing Transformer-2 is overloaded,it is proposed to increase the Transformer capacity
from 1 X 10 MVA by 20 MVA Power Transformer and also providing spare 1000 Sq.mm. U.G.Cable for
Transformer to avoid the power supply interruption at the time of pot head failure.The existing 11 KV NCT
ratio is 800-400/1A & this is not suitable for 20 MVA Transformer. In this estimate the existing NCT is
proposed to replace by 1200-800/1-1 A ratio. The capacity of existing Bank CT's are 800-400/1-1A and
they are to be replaced by 1200-800/1 A CT's.The provision for oil sump is made for CTR protection system.
The existing C & R panel of Transformer is suitable to 20 MVA Transformer. The released power
transformer,RTCC panel and 11KV NCT, CT, control cables and mounting structures are shown as credit.

This estimate is prepared as per the approved DPR vide No:B19/2387/95-96 Dated 02-05-2018.
The above augmentation work is approved in 72nd th TCCM meeting dated 17.02.2017.

Hence this estimate may be kindly sanctioned to take up the work at the earliest.

Asst.Engineer(E) Asst.Executive Engineer(E)


110/11KV MUSS, Nodal Officer,110/11KV MUSS
Mayasandra Tiptur

Executive Engineer, [Ele.]


KPTCL TL & SS Division
K.B Cross
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED.
Estimate for Replacement of 1x10MVA Power Transformer-2 by 1x20MVA Power
Transformer at 110/11KV Sub-station Mayasandra in Turuvekere Taluk, Tiptur nodal
center in K.B.Cross division,Tumakuru circle.
Material(s) split up-Control cable detail(s)
1 19 core 2.5 Sqmm
No Mtr
OLTC drive MB to RTCC ( Interconnection ) 4 52
Transformer MB to RTCC ( Fan control ) 2 51

1 20
RTCC to C&R Panel ( Protection indication in TCS )
Total ( in metres )
2 4 core 6 Sqmm
Transformer MB to ACDB ( For Fan control ) 1 70
RTCC to DCDB for DC supply 1 30
OLTC drive MB to ACDB for 3 ph AC supply 1 60
CTR to ACDB 1 70
Total ( in metres )
3 2 core 6 Sqmm
Transformer MB to RTCC ( Load current ) 1 50
4 4 core 2.5 Sqmm
Transformer C&R panel to 11kV Bank ( LV breaker 2 80
status+inter trip)
5 2 core 2.5 Sqmm
DCDB to transformer MB 1 59
Transformer MB to RTCC (AC supply) 1 55
Transformer C&R panel to HV breaker ( breaker
1 60
status )
RTCC to DCDB for CDC supply 1 20
CTR to DCDB 1 65
Total ( in metres )
6 GI flat for earthing
Transformer body earthing/supporting structure earthing.
11KV Cable supporting structure
Total ( in meters )
7 CI Pipe earthing
Transformer body earthing

Assistant Engineer (Ele) Asst.Executive Engineer(E)


110/11KV Substation Nodal officer,110/11KV MUSS
Mayasandra Tiptur

Executive Engineer (Ele)


220KV R/S Division
KPTCL, K.B.Cross
ION LIMITED.
-2 by 1x20MVA Power
kere Taluk, Tiptur nodal
cle.
s)

Total
208
102

20

330

70
30
60
70
230

50

160

59
55

60

20
65
259

40
20
60

ive Engineer(E)
r,110/11KV MUSS
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED
Estimate for Replacement of 1x10MVA Power Transformer-2 by 1x20MVA Power Transformer at 110/11KV
Sub-station Mayasandra in Turuvekere Taluk, Tiptur nodal center in K.B.Cross division,Tumakuru circle.

Part-B:Dismantling Of Equipments
Sl no Particulars Unit Qty Rate
B1 POWER TRANSFORMER :

POWER TRANSFORMER : 110/11KV, 10 MVA,


delta/Star, DY11, 3 Ph,50 Hz, Core type winding
1 No 1 46,382.70
with OLTC,RTCC panel etc., complete filled with
Transil Oil with 10% spare oil. [37.6MT].

B2 11KV CT of ratio 800-400/1-1-1A Nos 3 1,209.75

B3 11KV NCT of ratio 800-400/1-1-1A No's 1 350.25


Mounting structure 11KV NCT's(0.142 MT per
B4 No/MT 1/0.142 1601.25
structure)

11 KV cable terminating structure 0.0690 MT No/MT 1/0.069 1601.25


B5 Lynx conductor bus bar Per bay 1 5546.25
B6 Copper control cable Mtr 40 8.25
B7 Sub Total
Scattered area mobilisation allowance 5% on
B8
labour
Allowance to take care of the contractors
B9
overhead @15% on labour

B7 Miscelleneous and other unforseen materials L/s


Part-D Total Rs
Assistant Engineer (Ele) Asst. Executive Engineer [Ele]
110/11 KV Substation 110KV MUSS, Nodal Officer
KPTCL, Mayasandra Tiptur

Executive Engineer El.,


220KV R/S Division
KPTCL, K.B.Cross
LIMITED
er Transformer at 110/11KV
s division,Tumakuru circle.

Amount

46,382.70

1,209.75

350.25

227.38

110.49
5,546.25
330.00
54,156.82
2,707.84

8,123.52

5011.82
70,000.00
ve Engineer [Ele]
S, Nodal Officer
iptur
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED
Estimate No:- Date:-

Estimate for Replacement of 1x10MVA Power Transformer-2 by 1x20MVA Power Transformer at


110/11KV Sub-station Mayasandra in Turuvekere Taluk, Tiptur nodal center in K.B.Cross
division,Tumakuru circle.

PART-C: Civil portion


Sl. No. Description Unit Qnty Unit Rate Amount
1 2 3 4 5 6
C1 Foundations

Engineering, supply of all labour, material and


construction of RCC footings of any depth, pedestals
including the cost of excavation, concreting, cement,
reinforce-ment steel, for all works, grouting, under-
pinning etc., for the following station towers and
mounting structures

1 11kV NCT(0.190 MT per structure) No 1 8206.98 8206.98

2 11kV Cable terminating structure for LV side of No 2 8353.35 16706.70


66/11KV Tr(0.0690 MT per tower)

3 Foundation for CTR protection equipment No 1 34291.85 34291.85

Cable ducts: Construction of RCC main cable duct


type SSY-II type of inernal dimension 750 x 1160
C2 mm as per technical specification design and Mtr 25 9305.02 232625.50
drawings including materials,cement, steel and flats
(As per annexure)
Oil sump pit: providing and construction of oil sump
pit as per technical specification, design and drawing
C3 Lot 1 230000.00 230000.00
including cost of material, labour (size 3.0 x 4.0 x
2.0 m)n as per annexure

Providing,Laying and jointing PVC pipes confirming


to IS with necessary
C4 collars,bends,elbows,Tee,nipples,plugs with cuts and
threads as per the directions of field engineer with all
lead and lifts
i) 110 mm outer dia pipe Rmtr 30 240.37 7211.10

ii) 90 mm outer dia pipe Rmtr 30 160.88 4826.40

Excavation of UG cable trench for laying of new &


C5 rearranging existing cable.KPTCL SR 2016 Pg Cmtr 20 449.00 8980.00
No:109,Item No:B(i)
Backfilling the cable trench with selected availble
ridded earth from trench excavation.KPTCL SR 2016 Cmtr 20 121.00 2420.00
Pg No:109,Item No:C(i)

Sub-Total 545268.53

GST at 18% 98,148.34

Miscelleneous and other unforseen materials 6583.13


Grand Total 650000.00

Assistant Engineer (Ele) Asst. Executive Engineer [Ele]


110/11 KV Substation 110KV MUSS, Nodal Officer
KPTCL, Mayasandra Tiptur

Executive Engineer El.,


220KV R/S Division
KPTCL, K.B.Cross
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED
Estimate No:- Date:-
Estimate for Replacement of 1x10MVA Power Transformer-2 by 1x20MVA Power Transformer at 110/11KV Sub-
station Mayasandra in Turuvekere Taluk, Tiptur nodal center in K.B.Cross division,Tumakuru circle.

PART-D:Credit(As furnished by field staff)


% age
Origional Written
Depreciati
Conditio value down value
Sl No Particulars Unit Qty. DOC on
n
Rate in Rs Rate in Rs Rate in Rs

POWER TRANSFORMER : 110/11KV, 10


MVA, delta/Star, Dyn11, 3 Ph,50 Hz, Core
Released
1 type winding with OLTC,RTCC panel etc., No 1 1993 3156568.00
Good
complete filled with Transil Oil. Make
:NGEF, Sl No.B-2800055751,YOM:1996

Released good 11KV NCT of ratio 800- Released


2 No 1 1993 25000.00
400/1 A ,YOM:1993 Good
Released
3 Released CT's 800-400/1 A Nos 3 1993 75000.00
Good
Released
Released scrap copper control cable of
4 Mtr 200 1993 Scrap
various sizes
copper

Released NCT structure and cable Released


5 Kg 40 1993 800.00
termination structure Scrap Iron

Assistant Engineer [Ele] Asst. Executive Engineer [Ele]


11/11 KV Substation 110KV MUSS, Nodal Officer
KPTCL,Mayasandra KPTCL,Tiptur

Accounts Officer Executive Engineer [Ele]


TL & SS Division , KPTCL TL & SS Division , KPTCL
Tumakuru. K B cross
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED
Estimate No:- Date:
Estimate for Replacement of 1x10MVA Power Transformer-2 by 1x20MVA Power
Transformer at 110/11KV Sub-station Mayasandra in Turuvekere Taluk, Tiptur
nodal center in K.B.Cross division,Tumakuru circle.

ABSTRACT-II

Sl No. Particulars Amount (in Rs)

1 Erection/Labour charges 70000.00

2 Applicable GST on Errection/Labour charges(on Sl.No.3)@18% 12600

3 Total of material and Errection/labour charges 82600.00

Establishment charges at 5% on material cost and Errection


4 4130.00
charges(on Sl.No.3)
Contingencies at 3% on[ Material cost + Errection/Labour
5 charges+establishment charges] [on Sl.No.3&4] 2601.90

Performance guarantee & loss of interest on margin money for


6 Bank Guarantee @ 0.1 % on material cost and Errection 82.60
charges(on Sl.No.3)
7 Interest during construction @4% on (Sl.No 3 to 6) 3576.58
8 Total estimated cost of the work (Sl.No 3 to 7) 92991
( Rupees seventy three thousand sixty four only)

Assistant Engineer (Ele) Asst.Executive Engineer(E)


110/11KV MUSS Nodal officer,110/11KV MUSS
Mayasandra Tiptur

Executive Engineer (Ele)


220KV R/S Division
KPTCL, K.B.Cross